Professional Documents
Culture Documents
DAY- 2 :
Contact Person : Mr. Rishikesh Mishra : 9820459356 / Mr. Manoj Mishra 9820631320
8/29/2020
AN OVERVIEW
N Manohar Rao
• US 20.4%
• China 17.7%
• Russia 6.0%
• Japan 4.5%
• India 3.8%
• Canada 2.9%
• Rest 44.7%
1%
1%
6%
31%
53%
9%
Share of OIL & Gas in world is 59%, in India 40% of Total Energy
To push the growth, Hydrocarbon Vision 2025 introduced
Source: BP Statistical Review of World Energy- June 2010
1
8/29/2020
Key Developments
• APM dismantling
• LNG import
Key Developments
• Regulatory mechanisms
• Strategic Storages
2
8/29/2020
Modes of transportation
Road
Rail
Pipeline
Sea route
3
8/29/2020
CRUDE OIL
PRODUCT
PETROL
DIESEL
ATF
NAPTHA
KEROSENE
Manpower Requirements
4
8/29/2020
Manpower Requirements
5
8/29/2020
Hydrostatic Testing.
6
8/29/2020
DEFECTS DISTRIBUTION
CORROSION
defined as
deterioration of a substance
(usually metal) or its properties
because of reactions within its environment
is a well-known natural phenomenon
and
one of most important factors that affects
integrity & management
Industrial & Infrastructure assets
13 Miscellaneous
Source: Shri R P Nagar
7
8/29/2020
14 Instantaneous Failure
16 Vandalism
18 Cold Weather
21 Earth Movements
22 Unknown
Safety
Electrochemical
Cost & Unique
Availability
Chemical
Metallurgical
Fabricability Appearance
Physical
Thermal & Electrical
Characteristics
INCREASE AWARENESS OF
High Cost of Corrosion & Potential Savings
CHANGE MISCONCEPTION
That nothing can be done about corrosion
IMPROVE
Education & Training of Personnel
&
Corrosion Technology through Research
Development & Implementation
8
8/29/2020
DEVELOP ADVANCED
Design practices for better Corrosion Management
Life Prediction & Performance
Assessment Methods
INTRODUCE
Policies, Regulations, Standards
And Management Practices
To increase Corrosion savings through
Sound Corrosion Management
Thank You !
9
29-08-2020
PRE-DESIGN SURVEY
Presented by
Pankaj Panchal
NACE, Corrosion Specialist
NACE, Cathodic Protection Specialist
Mobile : +91 93772 76131
E-mail : info@corrosionps.com
OUTLINE
Soil Resistivity
Soil Chemical Analysis
Parallel Pipeline Details
Existing CP System in vicinity
AC / DC Powerlines
SOIL RESISTIVITY
1
29-08-2020
Resistance Test
Instrument
C1 C2
P1 P2
a a a
C1 P1 P2 C2
r=2paR
Pipeline Integrity Management System
2
29-08-2020
SOIL ANALYSIS
pH
SRB
Chloride
Sulphates
Other
3
29-08-2020
CORPS
CORROSION ASSESSMENT
I am CP Current and not following Owner, Project’s Paths.
I always take shortest path.
CORPS
CORROSION ASSESSMENT
4
29-08-2020
CORPS
CORROSION ASSESSMENT
Bonding
5
29-08-2020
EXISTING STRUCTURES
CORROSION ASSESSMENT
6
29-08-2020
Attenuation
General
■ Attenuation is electrical losses in a conductor caused
by current flow.
■ Attenuation is a major factor in the design of CP
System for long pipelines.
■ The poorer the dielectric properties, the greater the
attenuation.
■ Attenuation can be significantly reduced with the
increase in dielectric properties of coating.
■ Good-quality coating will significantly diminish
attenuation, also at the same time it will enhance the
uniformity of current distribution.
Attenuation
Ideal Current Distribution
■ The current must enter the structure from remote earth to
complete the path.
■ The resistance of the structure to remote earth is
composed of an infinite number of individual parallel
leakage resistances that are equal in value.
■ Ideally the internal resistance of the structure is zero.
■ Because the assumptions made to produce ideal current
distribution are unrealistic, plus the fact that CP
equipment cannot be located at remote earth, the ideal
current distribution cannot be achieved in practice.
7
29-08-2020
Attenuation
■ When new a buried pipeline is bonded with existing
buried pipelines in a common corridor the attenuation for
existing and new pipelines gets altered.
■ Coating resistance for existing buried old pipeline and
new proposed pipeline is not the same.
■ Linear resistance for new pipeline and existing pipeline
that may be different in diameter, wall thickness and also
the materials of new pipeline may be different from
existing one.
■ The CP current density required for protecting the
existing old poorly coated pipeline shall be different then
the new pipeline.
8
29-08-2020
Attenuation
OFFSHORE – PIPELINES
9
29-08-2020
AC CORROSION
AC CORROSION
AC CORROSION
10
29-08-2020
RISK OF AC CORROSION
RISK OF AC CORROSION
AC CORROSION FAILURES
11
29-08-2020
We are Grateful to o
Y u
12
29-08-2020
Pipeline Coating
Presented By
CURRICULUM VITAE
Dr.Buddhadeb Duari is Director of Lalita Infraprojects Pvt Ltd who are major Manufacturer and Applicator of
corrosion resistant organic coatings and linings.
Dr.Buddhadeb Duari has done B. Tech (Hons) in Mechanical Engineering from I.I.T Kharagpur,
MBA from Jamnalal Bajaj Institute for Management Studies (JBIMS) and
Ph.D (Engg) in Metallurgy & Material Engineering from Jadavpur University.
He is a NACE Corrosion Specialist, a NACE Protective Coating Specialist from
NACE (National Association of Corrosion Engineers), Houston, USA and
SSPC Protective Coating Specialist from SSPC (Society for Protective Coating), Pitsburgh , USA.
He is a member of BIS (Bureau of Indian Standard) for CHD 20 (Chemical & Paint Division),CHD 21 (Raw Material
for Paints),MTD 24 (Metallurgical Technical Division - Corrosion Protection Group) and MTD 19 (Pipes and Tubes).
He has more than 35 years experience on Corrosion, Coating and Cathodic Protection of Metals, Structure and
Concrete. He has published more than forty five (45) Technical Papers in reputed journals out of which fifteen (15)
are international ones like MP Materials Performance, JPCL, Coating & Maintenance and Corrosion Management.
Dr. Buddhadeb Duari is also guiding students for doing their Ph.D in Jadavpur University as well as IIT - Guwahati.
Consultancy:
Dr. Buddhadeb Duari has been roped in by the following companies as their principal consultant on corrosion related
services :
(a) Engineers India Limited, (b) Kolkata Metro Rail Corporation, (c) Siemens Power, (d) L&T Power, (e) Kolkata
Municipal Corporation (KMC), (f) Different State Public Health Engineering Depts etc.
Relative Risk
Likelihood of Consequences
Failure of Failure
....
Coating type
Coating Condition
Cathodic protection
Soil Type
……
1
29-08-2020
Coating are the first line of defense and they play a major role in protecting steel
(pipeline from corrosion).
A good coating system always balances the surface environment design to obtain
desired performance and service life-cycle at least cost.
An ideal coating system which is 100% holiday or pinhole free is good enough to
protect structural steel/ pipeline from corrosion.
Practically it is not possible as there are damages during transportation and handling
leading to several holidays.
Polyurethane 1970
2
29-08-2020
ABRASIVE
CLEANING
White Metal NACE 1/ SSPC SP- 5 Sa 3
3
29-08-2020
POLYURETHANE COATING
4
29-08-2020
3 LAYER PE/PP
5
29-08-2020
Blistering
Osmetic Blistering
Electroendosmosis
6
29-08-2020
Coating Thickness
Coating Thickness
Polyurethane 1 - 2 mm
Coaltar Enamel
PRIMER
COALTAR
ENAMEL
WITH TWO
LAYERS OF
FIBERGLASS
REINFORCEMENT
FIBREGLASS
OUTER WRAP
7
29-08-2020
Polyurethane Coating
8
29-08-2020
STANDARDS
3 Layer PE / PP Coating
DIN 30670: Polyethylene Coatings for Steel Pipes and Fittings
ISO 21809-2011: Petroleum and Natural Gas Industries- External Coatings for Buried or
Submerged Pipelines used in Pipeline Transportation Systems- Part 1
IS 15659 (Part 1) : Petroleum and Natural Gas Industries- External Coatings for Buried or
Submerged Pipelines used in Pipeline Transportation of Gas and Liquid Hydrocarbon
IS 15659 (Part 2) : Petroleum and Natural Gas Industries- External Coatings for Buried or
Submerged Pipelines used in Pipeline Transportation of Gas and Liquid Hydrocarbon
IS 16676 - Solventless Liquid Epoxy System for Application on Interior and Exterior
Surface of Steel Water Pipeline
STANDARDS
Coal Tar Enamel (Plasticized Pitch)
IS 10221 :2008 : Coating and Wrapping of Underground Mild Steel Pipelines-Code of Practice
AWWA C203-08: Coal- Tar Protective Coating and Linings for Steel Water Pipelines- Enamel and
Tape- Hot Applied
Polyurethane Coating
AWWA C222-18 : Polyurethane Coatings and Linings for Steel Water
Pipe and Fittings
BIS Draft : Cold Applied Tape Coating System For Exterior of Steel Pipeline
9
29-08-2020
Cathodic
Disbondment(mm)
23°C/28 days(-1.5V),Max 7 7
65°C/24hrs(-3.5V),Max 7 7
T-max /28;-1.5V, Max 15 15
10
29-08-2020
CONCLUSION
Ranking (based on quality)
Pipeline Coating
I) 3 Layer PE/PP
II) FBE
III) Polyurethane
IV) Cold Applied Tape Wrap
V) Epoxy
Joint Coating
I) Heat Shrink Sleeves
II) FBE
III) Polyurethane
IV) Epoxy
Rehabilitation Coating
I) Polyurethane
II) Cold Applied Tape Wrap
III) Epoxy
REFERENCES/ BIBLIOGRAPHY
(1) Corrosion Prevention by Protective Coatings by C. G .Munger – NACE Publication
(2) Fusion Bonded Epoxy (FBE) by J. Alan Kehr – NACE Publication
(3) CIP Level 2 - NACE Publication
(4) Coatings and Linings for Immersion Service – NACE Publication
(5) Corrosion and Coatings by Richard W. Dvisko, PhD ,
James F. Jenkins – SSPC Publication
(6) Surface Preparation Specification and Practices – SSPC Publication
(7) Protective Coatings by Clive H. Hare – SSPC Publication
(8) Paint Film Degradation by Clive H. Hare – SSPC Publication
(9) Protective Coatings for Water and Waste water Facilities – SSPC Publication
(10) Coating and Lining Inspection Manual –SSPC Publication
(11) SSPC – VIS 1 - Guide and Reference Photographs for Steel Surfaces
(12) SSPC – VIS 3 – Guide and Reference Photographs for steel Surfaces
(13) ISO 8501 – 1 Preparation of steel substrates before application of paints.
11
8/27/2020
V.S. RAJA
Professor
Department of Metallurgical Engineering and
Materials Science
I.I.T Bombay, Mumbai, INDIA
Email: vsraja@iitb.ac.in
Tel:+91-9869769984
Corrosion Basics
Environment
Material
Corrosion
Design
1
8/27/2020
• Mechanical • Physical
– Strength – Thermal Conductivity
– Ductility – Electrical Resistance
– Toughness – Magnetic
– Wear – Optical
• Dimensional Stability – acoustic
• Wear
• Machinability • Chemical
– Catalytic
Corrosion Tendency
Exposure to
Corrosive/chemical medium
Metal
Energy
level
Ore
State/time
VS Raja, Aqueous Corrosion Laboratory 5
R
Ox
e M+
e M+
Metal Environment
R
Ox
2
8/27/2020
2H+ + 2e H2
(Hydrogen reduction reaction)
O2 + 2H2O+ 4e 4(OH)-
(Reduction of dissolved O2 in water)
Forms of corrosion
Uniform Corrosion Galvanic Corrosion
b
IGC
HIC
100 m
SCC
Cavitation
Crevice
Corrosion
Pitting
3
8/27/2020
Material: Environment:
chemical, chemical
Material Environment
structural, species, pH,
microstructural temp….
Corrosion
Design:
DesignStresses,
geometry
Corrosion Basics
VS Raja, Aqueous Corrosion Laboratory 12
4
8/27/2020
0.5Cr-0.5Mo 510 reactor vessels, heat-exchanger shells, separator drums, and piping for processes involving
hydrogen
at temperatures above 260 °C
2.25Cr-1Mo steel 540 sulfidic corrosion as well as to high-temperature hydrogen attack; furnace tubes, heat-
exchangers shells, and piping and separator drums. ( need post weld heat treatment)
5Cr-0.5Mo 620 For sulfur corrosion in liquid hydrocarbons or for hydrogen service
7Cr-0.5Mo 635
9Cr-0.5Mo 650
Type 304/316 stainless 595 include linings and tray components in fractionation towers; piping; heat-exchanger tubes;
steel reactor cladding; tubes and tube hangers in furnaces; various components for compressors,
turbines, pumps, and valves; and reboiler tubes.
Incoloy 800 (18Cr-35Ni) <900 High temperature and reformer furnaces
5
8/27/2020
6
8/27/2020
Monitoring
Maintenance
Cost
Material availability
Data availability
VS Raja, Aqueous Corrosion Laboratory 19
Stainless Steels
At least 10.5 wt% Cr steels
7
8/27/2020
Alloying elements
Cr - Corrosion resistance
• PREN + % Cr + 3% Mo + 16% N.
• An increase in PREN (Pitting Resistance Equivalent
Number) means an increase in pitting resistance of a
stainless steel.
• The Adjective “Super” _ferritic, austenitic, duplex-
stainless steels ; based on PREN number ( 40)
8
8/27/2020
1. Pitting
2. Crevice corrosion
3. Weld decay
4. Stress corrosion cracking (austenitic)
5. Hydrogen embrittlement (ferritic and
martensitic)
S39277 39-46
S32750 38-44
J93380 38-46
S32520 37-48
S31260 34-43
S32803b 33-41
S32550 32-44
S32950 32-43
J93345 31-47
S31200 30-36
J93370 30-34
S32404 27-32
S32900 26-35
PREN
S32654 54-60
J95370 48-54
S31266 46-62
J93254 42-47
42-45
S31254
N08926 41-48
N08925 40-47
N08320 34-43
N08904 32-40
N08020 29-40
S32200 29-40
N08007 25-32
20-23 N08367
PREN
9
8/27/2020
Precipitation No No
Hardenable
Welding
• Stainless Steels
• High Strength Low Alloy Steels
10
8/27/2020
Intergranular Corrosion
Welding causes such an IGC attack.
Weld decay(sensitization) in austenitic stainless steel and methods for it’s prevention .Panel of four
different AISI 300-series stainless steels were joined by welding and exposed to hot HNO3 and HF
solution.The weld decay evident in the type 304 panel was prevented in the other panels by reduction in
carbon content (type 304 L) or by addition of carbon stabilizing elements(Ti in 321, and Nb in 347 (ASM
Handbook Vol 13)
VS Raja, Aqueous Corrosion Laboratory 33
11
8/27/2020
12
8/27/2020
Cooling
water Inlet
Air outlet 31C – 33 C Tube leakages = 63 Nos.
38C – 42 C
TGSCC
MOC change to
DS 2205
13
8/27/2020
Appearance of crack in the nozzle is shown. The crack seems to emanate from
the pipeline-nozzle joint. Stress concentration seems to be the reason for the
cracking
Solution
14
8/27/2020
Ferrous Group
Resistant To Resistant To
SCC Super Duplex SS Pitting/Crevice
Resistance To SCC
+N, +Cr
Cost
Resistant To Inconel Higher
Duplex SS
SCC +Ni (30%)
+Cr ,-Ni
Pitting/Crevice 304L,316L SCC
Resistance Cu Base +Mo, +N
Alloys
IGC
Resistant
316SS Super
Austenitic/Ferrite IGC
+Ni
Problems In
Exhibit Passivity Ferritic Welding,low
Strength HE
+Cr/-C
Basic Structural Poor Corrosion
Material C-steel
Resistance
-C
Lowest cost
VS Raja, Aqueous
CastCorrosion
Iron Laboratory Poor Fabrication 43
Structural Material
Superferriitic
stainless steels Ni-Cr-Fe Alloys
303, 303Se
Superduplex
stainless steels
Add Ni for corrosion resistance
in high temperature environment
Add Cr, Mo Add S or Se
Add Cr, Ni, Mo, N
for machinability
409,430 309,310,314,330
Duplex stainless
steels
No Ni, ferritic Add Cr and Ni for
strength and oxidation resistance Add Cr, No, N,
lower Ni
for strength
Add Nb + Ta to reduce Add Cu, Ti, Al,
347 304 Precipitation-hardening
sensitization lower Ni
Fe-19Cr-10Ni stainless steels
for
precipitation hardening
Add Ti to reduce
321 Add Mo for Add Mn and N,
sensitization
pitting resistance lower Ni for higher strength
304L
Lower C to reduce 316
316L
sensitization
201, 202
317L
Add more Mo for
pitting resistance No Ni addition,
lower Cr, Add Mo, N
martensitic
Prone to Ammonia,
Resistant to Erosion 3m/s Cu, Ni Chlorination
-Zn +Ni
Resistant to Admiralty brass
Dezincification Prone to Erosion
Corrosion
+Zn
Resistant to Low Strength
Cu
Pitting
VS Raja, Aqueous Corrosion Laboratory 45
15
8/27/2020
Heat Treatment
Prone to Pitting,
High Strength High Strength Al-Alloys Exfoliation SCC/HE
Galvanic Corrosion
• Unprotected underground plain carbon steel pipelines connected to
above-ground tanks and other
• Structures that are electrically grounded with buried copper rods or
cables
• Stainless steel shafts in "canned" pumps rotating in carbon or graphite
bushings in a strong electrolyte
• Copper-nickel or stainless steel heat exchanger tubes rolled in plain
carbon steel tubesheets exposed to river water for cooling
• Aluminum thermostat housings on cast iron auto engine blocks in
contact with glycol-water mixtures
VS Raja, Aqueous Corrosion Laboratory 48
16
8/27/2020
Prevention Methods
17
8/27/2020
18
8/27/2020
Take Away
• Corrosion failures need to be addressed
• Materials selection is one of the important ways to control
corrosion
• Corrosion failures are complex-there is no universal
alloy/material that can withstand all types of corrosion
• Technologies evolve, there is a continuous need to develop
materials
• Environment?
– Chemistry, temperature, pressure,
Environment
Material
Corrosion
flow static, inhibitors,
• Design
– Stresses
Design
– Stagnancy
• Materials
– Compatibility
– Fabrication
– Process conditions
– Coatings/lining/cathodic protection57
VS Raja, Aqueous Corrosion Laboratory
19
8/27/2020
20
29-08-2020
For
1
29-08-2020
https://portal.phmsa.dot.gov/analytics/saw.dll?Portalpages&PortalPath=%2Fshared%2FPDM%20Public%20Website%2F_portal%2FGT%20Perf
ormance%20Measures&Page=Onshore%20Significant%20Incident%20HCA.
Pipeline integrity :
Pipeline integrity means ensuring a pipeline and all its related
components are running properly.
In short, it's about keeping the pipeline safe for life. ...
Design Requirements
Materials & Equipments specification and Integrity check
Pipeline route selection & maintaining inter distance between
various facilities.
Development of procedures for construction and testing
activities as per best engineering practices
Calibration, suitability and traceability check of instruments and
equipments required for testing/inspection.
Qualifications requirement for welding procedures & welders.
Selection of NDT methods & qualifications and acceptance
criteria.
Field Joint Coating
Pipeline Integrity Management System
2
29-08-2020
Design requirements
3
29-08-2020
As per GSR 808 (E)- The selection of design for Natural gas pipelines shall be
based on the gas properties, required flow rates, operating pressures and
the environment. All components of the pipeline shall be designed to be
suitable and fit for purpose throughout the design life.
As per GSR 612 (E)- Supply of gas at a constant pressure at consumer end,
and - The design should recognize the need for safe guard against
malfunction of any equipment and provide sufficient redundancy to ensure
that the supply is secured against such malfunctions.
Pipeline Integrity Management System
where
S= specified minimum yield strength, psi (MPa),
t = nominal wall thickness, in. (mm)
D= nominal outside diameter of pipe, in. (mm)
F= design factor obtained from Table 841.
E= longitudinal joint factor obtained from
T= temperature derating factor obtained from Table
841.1.8-1
P= design pressure, psig (kPa)
4
29-08-2020
In all existing cases where thickness of pipe is less than 6.4 mm for pipe
size 4 inch and above. Quantitative Risk Assessment shall be carried
out and the risk level shall be reduced to ALARP (As low as reasonably
possible).
Pipeline Integrity Management System
5
29-08-2020
Pigging Facilities :
Main gas pipelines and feeder lines, spur lines and branch lines of
4" and above size and length greater than 10 km shall be provided
with pigging facilities.
Spacing between consecutive pigging stations shall be
determined based on the diameter of pipeline, nature of pigging
operation and capability of the pigs. Spacing in excess of 200 km
shall be avoided.
Pigging stations shall be provided with all weather access road
from the nearest road
6
29-08-2020
Bends
The minimum radius of Cold
Field Bend shall be as per Table
Use of Mitre bends shall not be
permitted.
Insulating Joints
Insulating joints shall be provided
to electrically isolate the buried
pipeline from the above ground
pipeline and station piping
7
29-08-2020
Steel Pipe
As per Line Pipe Specification API 5L, shall be Seamless, Electric Arc
Welded (EAW) or Longitudinal / Helical Submerged Arc Welded
(LSAW/HSAW) conforming to (PSL 2).
Carbon Equivalent
Maximum limits on Carbon Equivalent for line pipes shall not be 0.43%.
Pipeline Integrity Management System
Notch Toughness
For steel pipes of size NPS 2 and above, notch toughness shall be
specified
Pipeline Integrity Management System
8
29-08-2020
BS 1873- Specification for Steel globe and globe stop and check
valves (flanged and butt-welding ends) for the petroleum,
petrochemical and allied industries
Pipeline Integrity Management System
9
29-08-2020
Flanges :
Flanges made of cast iron, ductile iron and non-ferrous materials (brass
or bronze) shall not be used in CGD networks.
Use of flanges in natural gas transmission and distribution piping is not
permitted except for station piping e.g. CGS, DRS, MRS etc.
For piping class 150 or above all the flanges shall be with raised face.
• ASME B16.5 Steel pipe flanges and flanged fittings - Size upto 24"
NB.
• ASME B16.36 Orifice Flange
• MSS SP-44 Steel Pipeline Flanges
• API 590 Steel Line Blanks
Pipeline Integrity Management System
10
29-08-2020
All plastic fittings used in CGD networks must have been type
tested by an internationally recognized testing agency prior to
their use.
11
29-08-2020
ASTM A194 Standard Specification for Carbon and Alloy Steel Nuts
for Bolts for High Pressure or High Temperature Service, or both.'
ASME B18.2.1 Square and Hex Bolts and Screws, Inch Series
Integrity Check :
All materials and equipments shall confirm design ,
specification and standard requirement.
Inspection shall be carried out by competenet inspection
agency before installation.
Inspected and Accepted material shall reched at site and same
shall be verified with manufacture record and inspection
reports/ rlease notes at site before installation.
Material damaged during transportation shall not use.
12
29-08-2020
Pipeline route
selection &
Inter distance
between
various
facilities
Pipeline Route :
construction for crossing road, pipeline, cable, railway, river, canal and
other existing obstacles.
The risks associated with proposed pipeline, mains and service routes
shall be assessed to ensure that all reasonably practicable steps have
been taken to minimize the risks to people & property in the event of an
unplanned release of Gas.
Pipeline, which is constructed inside the area of high voltage lines, may
be electrically influenced by this high voltage line. The voltage caused
by the influence may at times be so high as to pose a danger to
personnel working on the pipeline.
If it is not possible for plant and / or materials to come beyond 50m of
the centre of the high voltage system, special measures must be taken
to prevent any pproach beyond that distance,
Pipeline Integrity Management System
13
29-08-2020
Notes :
1. All distances are in meters.
2. For all the distance from the compound wall
# As per State Electricity Board recommendations.
Pipeline Integrity Management System
(a) As per GSR 808 (E) - MINIMUM INTER DISTANCES FOR VARIOUS
STATION FACILITIES : All distances are in meters.
Sr. From / To 1 2 3 4 5 6 7 8 9 10
Notes : PB - Pig receiver / Launcher Barrel, GC- Gas Coolers / Meters / filterste
Electricity Board recommendations.
Pipeline Integrity Management System
14
29-08-2020
15
29-08-2020
16
29-08-2020
17
29-08-2020
18
29-08-2020
When welders qualified under API 1104 are employed for station
piping, their qualification shall be based on destructive mechanical
testing as per API 1104.
Pipeline Integrity Management System
19
29-08-2020
20
29-08-2020
21
29-08-2020
Radiation safety
22
29-08-2020
BEVELLING OF
POLYETHYLENE
COATING EDGES
23
29-08-2020
24
29-08-2020
Holiday Test
HOLIDAY TEST
A holiday test is a non-destructive test method applied on
protective coatings to detect unacceptable discontinuities such as
pinholes and voids. Holiday testing involves checking an electric
circuit to see if current flows to complete the circuit. This testing is
used to find coating film discontinuities that are not readily visible.
25
29-08-2020
HOLIDAY TEST
Concrete Coating
26
29-08-2020
27
29-08-2020
In rocky areas and areas with hard soils / gravels, minimum 150
mm thick padding of soft soil / sand shall be provided all around
the pipe. If required protective layer of rock-shield / rock guard or
concrete coating may be provided to prevent damage to coating /
steel pipe during installation and testing in place of soft padding,
No dwellings or construction in any form shall be permitted within
RoU.
Clearance between
Pipelines
28
29-08-2020
(a) When a buried steel pipeline or main has to cross any existing
underground pipeline, cable, drain or other services, the pipeline
shall be laid at least 300 mm below from such services.
(b) When laid parallel to any existing underground cable, drain or
other utilities, the pipeline or main shall be laid with a clear
distance of at least 300 mm from existing utility.
(c) As far as practical, a minimum separation of three (3) meter
should be maintained between the steel pipeline or main and
footing of transmission tower.
Miters bends and wrinkle bends are not permitted in pipelines and
mains used in CGD networks regardless of operating hoop stress.
29
29-08-2020
Excavated soil from the trench shall be used for backfilling unless the
same is not suitable . The backfill material shall contain no extraneous
material and / or hard lumps of soil, which could damage the pipe and /
or coating or leave voids in the backfilled trench.
30
29-08-2020
31
29-08-2020
Vent Lines
Vent line shall be designed and installed to vent out the gas from
relief valves , if provided, to atmosphere. Blow down piping
connected to vent line should extend to location where the
discharge of gas shall not create a hazard to the compressor
station or the surrounding area. The discharge from safety valve
shall be vented vertically upwards to atmosphere at an elevation
of 3 meter (minimum) above working level
Pipeline Integrity Management System
Gauge Pigging
Pipeline Gauging
32
29-08-2020
Pipeline Gauging
Magnetic Flux Leakage (MFL) and Ultrasonic Testing (UT) are the
two primary methods for in-line inspection of pipelines and each
have their own strengths and weaknesses. UT Intelligent Pigging
is used for its higher accuracy and easier mobilization.
Pipeline Integrity Management System
33
29-08-2020
UT tools are well suited for heavy walled pipe. UT tools do require
a liquid cuplant through which ultrasonic pulses can travel to and
from the pipe wall. The presence of any gas between sensors and
pipe wall will interfere with the inspection but gas pipelines can
still be inspected using ultrasonic techniques by running the tool in
a liquid slug between two high-sealing pigs.
Most in-line inspection tools and hard body utility pigs are
designed to negotiate bends with a radius of 3D or greater,
Non pigable piping system with short radious bands are used in
the CGD network hense ILI could not performed on the CGD
network.
Hydrostatic Testing
34
29-08-2020
In case water is used as test medium, test duration shall start after
achieving thermal stabilization.
35
29-08-2020
Maintaining Construction
&
Inspection Records.
36
29-08-2020
37
29-08-2020
38
29-08-2020
39
29-08-2020
40
29-08-2020
41
28-08-2020
By:
Ashish Khera, P.Eng Date: 29th August 2020
TLC
Pipeline Integrity Management System
SCC
1
28-08-2020
External corrosion
MIC
Shut-down planning
7- Do I need to make a planned shut down to assist in integrity management for a pipeline?
Repair planning/schedules/retrieval
8- Repair plan and type of repair to manage my P safe and support the asset?
ILI HYDRO
- Piggable TEST
- Unpiggable
2
28-08-2020
When?
If line < 25 years old then
within 10 years of
Why is OISD asking for ICDA or commissioning
“complete wall thickness”? When?
If line > 25 years old then
within 26th years of
commissioning
Pipeline Integrity Management System
DA Model Process
Data collection and assessment, Corrosion/ leak
History, Selecting DA regions, Appropriate IDI
tools, Suspectibility
3
28-08-2020
Very beneficial if the sole purpose is for pipeline’s integrity rather than a
regulatory compliance
Stress Corrosion Cracking Direct Assessment (SCCDA) External SCC on the pipe surface and underneath the coating
NACE SP0204-2008
(low and high pH)
Wet Gas
On upstream systems, GLR > 5,000 (i.e., a ratio of
(WG-ICDA)
5,000 ft3 gas at STP/ 1 ft3 H2O ) or ~ 35 bbls
NACE SP0110-2010 H2O/MMSCF
Multiphase Flow
(MP-ICDA)
BS&W > 5% by vol.
NACE SP0116-2016
STP: 15C at 1 atm
- Onshore/ Offshore
- All products
Pipeline Integrity Management System
4
28-08-2020
5
28-08-2020
Firewater PipelineNitrosomonas
Nitrospira 2%
3%
Planctomyces
5%
Extensimonas
6%
Leptolinea
29%
Merismopedia
7%
Terrimonas
8%
Stenotrophomonas
10%
Thauera
Candidate_division_OP11 20%
10%
6
28-08-2020
7
28-08-2020
Example:
To show the different flow regimes encountered in a gas pipeline for a typical time period era.
Total 4 flow regimes found and 15 ICDA sub-regions made for a 0.8 km gas pipeline
Downstream Client
Terminal
Upstream
Operator
Terminal
Flow Direction (Current)
8
28-08-2020
Bi-directional flow……
9
28-08-2020
Number of Locations???
Finally DA provides quantifiable DEx locations!!
Minimum Number of Final Assessment Sites
Continuous
Pipeline Minimum
Length of All Number of
WG-ICDA Low Wall Moderate Wall High Wall Severe Wall Final
Regions and
Subregions in
Loss Loss Loss Loss Assessment
Pipeline < 20% 21–40% 41–60% > 60% Sites per
Segment (km) Pipeline
(1 km = 0.62 Segment
mi)
100.1–500.0 1 2 3 4 10
> 500 2 3 4 5 14
** Please refer WG-ICDA standard page-21
Wall loss profile considering pitting factor. The red circle indicate the sites recommended for direct examination
10
28-08-2020
1 2
3
4
7
Pipeline Integrity Management System
Absolute Difference in
Nominal Wall ICPM Predicted Internal Wall
Actual Measured Internal Wall Loss
SITE Thickness Loss with Pf
Wall Loss (%) [Predicted – Measured]
(mm) (%)
(%)
“Excellent Correlation”
Operator managed to assess the
integrity “non-intrusively”
11
28-08-2020
Post Assessment
Key Ingredients for “Successful” ICDA:
$$$$$
LFP Valve
12
28-08-2020
SMART DIGGING
13
28-08-2020
Based on the prediction of solids deposition and water accumulation, pitting factor and the
cumulative % wall loss was calculated
Comparison of ICPM with In-the-ditch direct UT measurements
“Excellent Correlation”
Operator managed to assess the integrity of Offshore line “non-intrusively” and now way forward……
20
-10% Tolerance
Measured Actual Wall Loss (%)
18
+10% Tolerance
16 12" WO-1
14 12" MS/LAN - R2
12
10
12" HSD/SKO - R2
8 24" MS/LAN
6
24" HSD CCK - R4
4
2 12" BO-1
12" HSD/SKO-R1
24" HSD/SKO 12" BO-2 12" MS/LAN - R1
0
0 5 10 15 20
Predicted Wall loss (%)
Average ICPM wall loss (%) and the measured actual wall loss (%) for the 8 pipelines
India- 8 pipelines
Pipeline Integrity Management System
14
28-08-2020
Pipelines transporting aromatic products (lower density) require higher critical velocities to entrain water in the
product during transfer
5
4.57
4.5
4.01
4
Critical Velocity (m/s)
1.5
0.93 0.93
1
0.55 0.65 0.55 0.65
0.5
0
LAN
LAN
LAN
LDO
LDO
SKO
SKO
HSD
HSD
HSD
MS
MS
MS
HFHSD
HFHSD
Benzene
FO-180
FO-380
FO-180
FO-380
12” BO-1 12” BO-2 12” HSD/SKO 24” HSD/SKO 24” 12” WO-1 12” 24”
CCK MS/LAN MS/LAN
6 8
Elevation (m)
1016 m , 8601.7 m, 6
4
IC WA 4 1356 m ,
2 8601.7 m,
2 IC WA
0 0
-2 0 5000 10000 -2 0 5000 10000
Distance (m) -4 Distance (m)
-4
8
Elevation (m)
5
6 3921.4 m 8197 m,
4 1149.9 m 1285 m, , WA IC
0
2 , WA IC 0 2000 4000 6000 8000
0 -5
-2 0 1000 2000 Distance (m)
Distance (m)
• Runs parallel to 2 x identical service 34” pipelines and 1 x parallel 48” pipeline
15
28-08-2020
“This standard is intended to provide an integrity assessment methodology for internal corrosion for
pipelines where ILI cannot be performed; however, the MP-ICDA methodology may also serve,
complement, or assist in those cases in which ILI was conducted or is contemplated to demonstrate the
reliability of the ICDA process.
“It can also be used for optimizing the selection/justification, inspection frequency, or prioritization of
pipelines that are subjected to ILI.”
- NACE International SP0116-2016 Multiphase Flow Internal Corrosion Direct Assessment MP-ICDA Methodology
for Pipelines
• However, severe metal loss was found at North and South sections by using ILI tool
105 105
Metal loss (%)
Elevation (m)
0.80 1.20
100 100
1.00
0.60 95 95
0.80
0.40 90 90
0.60
0.20 85 85
0.40
0.00 80 0.20 80
0 1000 2000 3000 4000 5000 6000 0 500 1000 1500 2000 2500 3000 3500
Distance (m) Distance (m)
North South
16
10
8
250, 7.73
6
150, 5.40
4
2
50, 1.25
0
0 100 200 300 400 500 600
Solids particle size (microns)
Calculated critical velocity (m/s) for solids deposition as a function of the solids particle size
16
28-08-2020
• The chlorides levels observed and the operating conditions indicate the pits formed in the pipeline was found to
passivate in about 59 – 72 days.
450
[Cl-] - 5659 ppm; [Fe2+] - 550 Minimum concentration
400
Pitting Corrosion Rate
ppm measured
350 Pitting Corrosion Rate is
300 [Cl-] - 13332 ppm; [Fe2+] - 133 Maximum
Never Linear! ppm
(mpy)
250 concentration
measured
200
[Cl-] - 20000 ppm; [Fe2+] - 50 Sensitivity test - 1
150 ppm
100 mpy =
100 2.5 mm/yr
50 [Cl-] - 30000 ppm; [Fe2+] - 50 Sensitivity test - 2
ppm
0
0 10 20 30 40 50 60 70 80
Days
Effect of chloride ion on pitting corrosion rate showing pit initiation & propagation and pit
passivation
100
90 enpICDA™
80
70
Wall Loss (%)
60
50
40
30
20
10
0
0 1000 2000 3000 4000 5000 6000
tie-in Distance from Tie-in (m) Tankage
NORTH
Pipeline Integrity Management System
100
90 ILI enpICDA™
80
70
Wall Loss (%)
60
50
40
30
20
10
0
0 1000 2000 3000 4000 5000 6000
tie-in Distance from Tie-in (m) Tankage
NORTH
Pipeline Integrity Management System
17
28-08-2020
0.6 90
Elevation (m)
0.5
70
0.4
0.3 50
0.2
30
0.1
0 10
0 1000 2000 3000 4000 5000 6000
Distance (m)
0.6 90
Metal Loss (%) - ILI
Elevation (m)
0.5
70
0.4
0.3 50
0.2
30
0.1
0 10
0 1000 2000 3000 4000 5000 6000
Distance (m)
0.31
125
0.26
105
0.21
85
Solids deposition (%)
0.16
65
Elevation (m)
0.11 45
Elevation (m)
0.06 25
0.01 5
0 1000 2000 3000 4000 5000 6000
Distance (m)
18
28-08-2020
0.26
105
0.21
85
Solids deposition (%)
0.11 45
Elevation (m)
0.06 25
0.01 5
0 1000 2000 3000 4000 5000 6000
Distance (m)
The contributing factors that led to metal degradation in a Middle East crude oil pipeline are:
• Water accumulation
• Solids Deposition
• Initiation and acceleration of under-deposit pitting corrosion under a high chloride ion
concentration
Scenario 1: Transporting the crude oil through one (1) 34” line and one (1) 48” line
instead of the existing three (3) parallel running 34” lines and one (1) 48” line = 2 lines
instead of 4!
Scenario 2: Transporting all the crude oil from through only one (1) 34” line; with the
other three pipelines depressured, cleaned and subsequently suspended with proper
anti-corrosion measures = 1 lines instead of 4!
19
28-08-2020
Learnings……
• Owner has realized the strength of
Key Ingredients forICDA for managing ICDA:
“Successful” integrity of piggable
and non-piggable pipelines
1. SME’s
• Now(Subject
applying it Matter
for their Experts)
critical lines in the pre-FEED stage, engineering time,
as a PROACTIVE assessment to design and operate within the Integrity
2. ICPM Liquid,( IOW’s)
(Solid,Window
Operating Bacteria, Sour, CR- general and pitting, % Wall
Loss)
• Be informed about susceptible locations and corrosion rates BEFORE they
occur and operate the asset safely
3. SME + ICPM + ICDA Team WITH Experience of performing
“successful” ICDA’s
• Trying to get out offor
the ALL 4 circle
vicious stepsof REACTIVE inspection and
+ Verymaintenance
Keen and Mature Pipeline Owner
Deliverables of ICDA
• Inclination angle (critical angles of and velocity for liquid/ solid accumulation)
• Flow regime in each sub region
• Pressure variation
• Temperature drop
• Average pH in each sub region
• Water accumulation rates and locations
• Liquid and Solid hold-up rates and locations
• Uniform corrosion rate
• Sensitivity analysis- amount of gas/ water on CR, production rates, composition of gas
variations
• TLC (water dew point and hydrocarbon dew point calculations)
• Assessment of MIC’s, Erosion and corrosion due to oxygen
• Root cause analysis
• Inhibitor/ biocide/ scavanger requirement and effectiveness- mitigation
• Remaining wall thickness
• Mitigation recommendation
• Types and locations for Monitoring
• Chemical Treatment engineering
• Reassessment interval
• ICDA effectiveness
Pipeline Integrity Management System
20
28-08-2020
Pre-Assessment (1.2.2.1)
• Collects historic and current data – must be sufficient to go on to the next points
• Must be performed in a comprehensive and thorough fashion
• Used to determine if ECDA is feasible
• Defines ECDA regions
• Selects indirect inspection tools
• Document pre-assessment results and decisions
21
28-08-2020
2nd Step of Indirect Inspection can ONLY start upon COMPLETING the above…. Are we almost there??
Coating Holidays 2 1, 2 2 2 1, 2
Stray Currents 2 1, 2 2 2 1, 2
Shorted Casings 2 2 2 2 2
Uncased Crossings 2 1, 2 2 2 1, 2
Cased Piping 3 3 3 3 3
Wetlands (limited) 2 1, 2 2 2 1, 2
Rocky Terrain/Rock Ledges/ Rock
3 3 3 2 2
Backfill
22
28-08-2020
As per NACE:
ECDA is NOT
Feasible i.e.
- Coating and CP
Surveys are NOT
feasible when……
23
28-08-2020
Results of No Access!
24
28-08-2020
25
28-08-2020
Ideal CIPS Waveform from “good” Interruption Cycle and Electrode Having
a Good Soil Contact
New Age Surveys- Transperently show Bad data- Inaccurate data on Concrete
New Age Surveys- Transperently show Bad data- Broken Copper Wire
26
28-08-2020
New Age SURVEY OUTPUTS- CIPS- If T/R switches off unscheduled momentarily on 4”
Pipeline
CP CIPS
Chart
PSP vs
Distance
300mV positive /
anodic Influence @
SAME
Pipeline Integrity Management location!
System
27
28-08-2020
New Gen. Integrated IIT= CP CIPS, DCVG, ACVG, ACCA, DOC, & Depth of Cover with
Elevation profile
28
28-08-2020
New Age = Continuous recorded non-editable raw logs that are auto-integrated
makes this possible
Pipeline Integrity Management System
29
28-08-2020
GPS
NDT
Environment
Anomalies
“Most Accurate”
Pipeline Integrity Management System
• Not ‘bell holes’ but rather sites with at least a girth weld (approx. 15
m long)
30
28-08-2020
31
28-08-2020
• An example of Passed Shrink Sleeve- only a few locations for subject line based on DEx
32
28-08-2020
10” Insulated line: DEx- Electrolyte Present between for PUF and HDPE
G
W
FeCO3
FeO
33
28-08-2020
-1.0
-2.0
Output Imperial
-3.0
Effective Length of Corrosion: 5.000 in
Start: 10.000 in
-4.0
End: 15.000 in
Pit Depth (mm)
-5.0
Total Length of Corrosion: 19.000 in
-6.0
Effective Area of Corrosion: 0.710 in2
Maximum Pit Depth: 0.240 in
-7.0
-9.0
Modified B31G (0.85dL) Method: Fail
Maximum Safe Pressure:
-10.0 833 psig
Burst Pressure: 1067 psig Pit Length (mm)
Factor of Safety: 0.84 Is my P Safe > P operating?
ASME B31G Method:
Maximum Safe Pressure: 503
Fail
psig
If Not
Burst Pressure:
Factor of Safety:
644
0.50
psig
What can I do to bring my P safe higher?
Pipeline Integrity Management System
- Reassessment Intervals
34
28-08-2020
Conclusions….
• Direct Assessment is an integrity assessment process through which an
operator may be able to assess and evaluate the integrity of a pipeline
segment.
• Direct Assessment is intended to address EC, IC, and SCC threats to pipeline
integrity.
Conclusions….
• Direct Assessment will usually include the following stages:
• Each DA methodology will employ at least one non-destructive (NDE) inspection technique to
physically inspect and assess pipeline.
• Provides Root Cause Analysis – Why is the Corrosion occurring?
ADVANTAGES OF DA
Proactive and designed to prevent lapses in pipeline integrity
Answers the key questions- Why corrosion exist? And How to mitigate it (go forward plan)?
Defect modeling can be developed from the DA process which can be used for forecasting and “what if.. Scenarios”
to optimize production with existing threats
When possible, complementary to ILI and Hydrostatic testing for greater data accumulation, data verification etc
A pipeline need not be put out of service during the process of assessing, thus no productivity downtime
No cost required for preparing the pipeline to enable the usage of this assessing technique
35
29-08-2020
Presented by
Pankaj Panchal
NACE, Corrosion Specialist
NACE, Cathodic Protection Specialist
Mobile : +91 93772 76131
E-mail : info@corrosionps.com
1
Pipeline Integrity Management System
OUTLINE
2
Pipeline Integrity Management System
CIPL SURVEY
Voltmeter
Copper Wire
Test Station
Electrolyte
Pipe
3
Pipeline Integrity Management System
1
29-08-2020
CIPL SURVEY
4
Pipeline Integrity Management System
CIPL SURVEY
5
Pipeline Integrity Management System
CIPL SURVEY
ON/Off Potentials On/Off & Depolarized Potentials
Potential Profile
ON
OFF
Depolarized
6
Pipeline Integrity Management System
2
29-08-2020
CIPL SURVEY
7
Pipeline Integrity Management System
CIPL SURVEY
8
Pipeline Integrity Management System
CIPL SURVEY
9
Pipeline Integrity Management System
3
29-08-2020
CIPL SURVEY
10
Pipeline Integrity Management System
CIPL SURVEY
11
Pipeline Integrity Management System
DCVG SURVEY
12
Pipeline Integrity Management System
4
29-08-2020
DCVG SURVEY
13
Pipeline Integrity Management System
DCVG SURVEY
14
Pipeline Integrity Management System
DCVG SURVEY
dA
SD S A SB S A
dA dB
where:
SD = signal strength at defect (mV)
SA = signal strength at Point A (mV)
SB = signal strength at Point B (mV)
dA = distance from A
dB = distance from B
1372 m
SD = 200 mV + (300 mV -200 mV ) = 275 mV
1372 m+ 457m
15
Pipeline Integrity Management System
5
29-08-2020
DCVG SURVEY
Pipe-to-Remote Earth =
Σ Earth Gradients
= 25+15+6+4+3+1+1 mV
= 55 mV
55mV
10020% IR
275mV
DCVG SURVEY
17
Pipeline Integrity Management System
DCVG SURVEY
18
Pipeline Integrity Management System
6
29-08-2020
19
Pipeline Integrity Management System
DCVG SURVEY
20
Pipeline Integrity Management System
DCVG SURVEY
21
Pipeline Integrity Management System
7
29-08-2020
DCVG SURVEY
22
Pipeline Integrity Management System
DCVG SURVEY
23
Pipeline Integrity Management System
24
Pipeline Integrity Management System
8
29-08-2020
25
Pipeline Integrity Management System
26
Pipeline Integrity Management System
a1 r1 avg rL1 L1
a2 r2 avg
r3 rL2 L2
a3 avg
rL3 L3
27
Pipeline Integrity Management System
9
29-08-2020
LAYER RESISTIVITY
r1 avg = 2a1R1
L1 = a1
RL1 = R1
rL1 = 2L1 RL1
Resistances R1, R2, and R3 r2 avg = 2a2R2
measured with respect to spacings L2 = a2 – a1
a1, a2, and a3 or L1, L2 and L3 RL2 = (R1 R2)/(R1 – R2)
rL2 = 2L2 RL2
r3 avg = 2a3R3
L3 layer = a3 – a2
RL3 = (R2 R3)/(R2 – R3)
rL3 = 2L3 RL3
28
Pipeline Integrity Management System
LAYER RESISTIVITY
RESISTIVITY
RESISTIVITY LAYER LAYER
SPACING RESISTANCE AVERAGE RESISTANCE rlayer
(ft) [cm] R (Ω) rave (Ω–cm) RL(Ω) (Ω–cm)
29
Pipeline Integrity Management System
IN LINE INSPECTION
30
Pipeline Integrity Management System
10
29-08-2020
IN LINE INSPECTION
31
Pipeline Integrity Management System
IN LINE INSPECTION
32
Pipeline Integrity Management System
DATA COMPARISON
11
29-08-2020
34
Pipeline Integrity Management System
12
RISK ASSESSMENT
by:
Upama Darshan
GM(Elect)
IEOT, ONGC
Upama Darshan
Pipeline Integrity Management System
Name : Upama Darshan
Designation: General Manager (Electrical), IEOT, ONGC
Herbert Heinrich
showed that for
every accident
resulting in a
fatality or major
disabling injury,
there are
approximately 300
unsafe incidents.
• Design Defects
• Operational Lapses
• Natural Hazards
• Equipment Layouts
• Concept Phase
• Design Phase
• Pre- Start Phase
• Operation Phase
• Modification Phase
• Expansion Phase
Upama Darshan
Pipeline Integrity Management System
HAZOP TERMINOLOGY
Guide-words
• Words or phrases used to qualify or quantify the
intention & associated parameters in order to
discover deviations
Deviations
• Departures from the design intention discovered by
systematically applying the guide-words to the
parameter at each node
Causes
• Reasons why deviations may occur
Consequences
• Results of the deviations
Upama Darshan
Pipeline Integrity Management System
HAZOP TERMINOLOGY
Safeguards
• Protective provisions present either to reduce the
chances of a deviation occurring or to mitigate the
consequences
Recommendations
• Suggested actions necessary either to reduce the
chances of a deviation occurring or to mitigate the
consequences or for further study
Recording
• Documented in HAZOP worksheets
Upama Darshan
Pipeline Integrity Management System
HAZOP TEAM COMPOSITION
• Typically HAZOP team is Multi-disciplinary
• Process Engineer
• Design Engineer
• Instrumentation Engineer
• Operations Engineer
• Health, Safety & Environment Engineer
• Experts with different backgrounds can identify
problems more efficiently when working together than
if working separately and combining their individual
results.
• Team should have knowledge & experience on the
facility under consideration
Upama Darshan
Pipeline Integrity Management System
HOW TO PERFORM HAZOP ?
• Plant considered section-by-section, line-
by-line and item-by-item but never in
complete isolation.
• Using guide-words, process deviations from
design intention are identified and study
considers:
• Possible causes of deviations
• Possible consequences of deviations
• Checks for available safety measures
• Suggests remedial action if required
Upama Darshan
Pipeline Integrity Management System
HAZOP GUIDEWORDS
No/Not/ None :The complete negation of the
intention
More of :Quantitative increase
Less of :Quantitative decrease
As well as :Qualitative increase
Part of :Qualitative decrease
Reverse :Logical opposite of the intention
Other than :Complete substitution
Upama Darshan
Pipeline Integrity Management System
PROCESS GUIDEWORDS
Guideword Process parameters
Flow Temp Presuure Level
No, None No Flow
Less Less Flow Less Less Less
Temp Pressure Level
More More Flow More More More
Temp Pressure level
As well As Contamination
Part of Composition
Reverse Reverse Flow
Upama Darshan
Pipeline Integrity Management System
HAZOP WORKSHEET
Upama Darshan
Pipeline Integrity Management System
REVERSE FLOW
Defective check valve
Siphon effect
Leakage/ Rupture
Upama Darshan
Pipeline Integrity Management System
MORE FLOW
Exchanger tube leaks
Increased pumping capacity,
Increased suction pressure, reduced delivery
head
Restriction orifice plates deleted
Cross connection of systems
Control faults
Upama Darshan
Pipeline Integrity Management System
LESS FLOW
Line restrictions
Defective pumps
Upama Darshan
Pipeline Integrity Management System
MORE LEVEL
Upama Darshan
Pipeline Integrity Management System
LESS LEVEL
Leak
Draining of vessel
Upama Darshan
Pipeline Integrity Management System
MORE PRESSURE
Thermal overpressure
PCV Malfunction
Upama Darshan
Pipeline Integrity Management System
LESS PRESSURE
Generation of vacuum condition
Condensation
Undetected leakage
Vessel drainage
PCV Malfunction
Upama Darshan
Pipeline Integrity Management System
MORE TEMPERATURE
Ambient conditions
Fire situation
Defective control
Ambient conditions
Reducing pressure
Leakage in exchanger tubes
Loss of heating
Failure of
Instrument air, steam, water, nitrogen
Hydraulic power, electric power
Telecommunications, computer and
interfaces
Upama Darshan
Pipeline Integrity Management System
PREVENTIVE MEASURES
Awareness of Toxic and hazardous properties of
process materials
Fire and gas detection
Emergency shutdown
Fire-fighting facility
Testing of emergency equipment
Emergency Response Plans
Training
Upama Darshan
Pipeline Integrity Management System
HAZOP RECOMMENDATIONS
Recommendation must be:
• Clear
• Concise
• Unambiguous
• Relevant
• Prioritised
• Follow the “3Ws” Rule
• What do you want?
• Where do you want it?
• Why do you want it?
Upama Darshan
Pipeline Integrity Management System
WRITING HAZOP RECOMMENDATIONS
Notes Full Recommendation
• Remove the Remove the manual valve on
manual valve the drain line from pH meter
No. xyz, to prevent the meter
being over-pressurised if the
valve is closed.
Upama Darshan
Pipeline Integrity Management System
WRITING HAZOP RECOMMENDATIONS
Notes Full Recommendation
Upama Darshan
Pipeline Integrity Management System
EXERCISE -1
Upama Darshan
Pipeline Integrity Management System
PROCESS FLOW
Upama Darshan
Pipeline Integrity Management System Worksheet -2
STRENGTHS OF HAZOP
•Based on well- understood HAZOP approach
•Uses experience of operating personnel as part of
team
•Systematic, comprehensive & can identify all
process deviations
Upama Darshan
Pipeline Integrity Management System
EXERCISE -1
Risk
WHAT IS RISK ?
ASSOCIATED CONSEQUENCES.
Upama Darshan
Pipeline Integrity Management System
RISK MANAGEMENT
Understanding
Risk
Human Life
Property
Environment
Corporate Reputation
•Regulatory requirement
•Decision-making tool
Evaluate Estimate
Consequences Frequencies
Risk Analysis
Options to Mitigate No No
Options to Decrease
Risks Controlled ?
Consequences Frequencies
Yes
Optimize Options to
Manage Risks
Upama Darshan
Pipeline Integrity Management System
SYSTEM DEFINITION
W/F
COMPRESSOR
R S GDU Gas out
E Well Manifold E
C P
E
E
R
I A
V T
O
E
R
R SURGE
TANK Oil out
MOL PUMP
Upama Darshan
Pipeline Integrity Management System
HAZARD IDENTIFICATION
Hazard identification is one of the most critical
steps in any risk analysis study. A hazard
omitted is a hazard not analyzed.
Upama Darshan
Pipeline Integrity Management System
FREQUENCY ANALYSIS
• Frequency analysis involves estimating the likelihood of
each of the selected failure cases, which were defined in
the hazard identification stage. Typical requirements are
frequencies of pipe leaks, flange/valve/small bore fitting
leaks, heat exchanger leaks, vessel leaks, pump leaks etc.
Upama Darshan
Pipeline Integrity Management System
FREQUENCY ESTIMATION
• Fi = Fn/ Ni
• where, Fi is individual equipment failure frequency per
year
• Fn is number of failures of that equipment in past
• Ni is number of exposed equipment-years (number of
that equipment multiplied by the number of years)
• Ft = Fi * Nn
• where, Ft is total failure frequency per year (future)
• Fi is individual equipment failure frequency per year
• Nn is number of that equipment present
Upama Darshan
Pipeline Integrity Management System
FREQUENCY ESTIMATION
EXAMPLE
• Example Description
• Say, there were 30 valve leaks observed in a plant over
a period of past 10 years among 3000 valves present of
that type
• Now, in a new plant it is proposed to install 10 valves of
the same type
• Then what is the likelihood of having a valve leak in the
new plant?
Example
Upama Darshan
Pipeline Integrity Management System
CONSEQUENCE ANALYSIS
• Effect modelling to evaluate the physical effects of
Upama Darshan
Pipeline Integrity Management System
RISK ESTIMATION SOFTWARE
Software are available in the market for risk
calculation.
Upama Darshan
Pipeline Integrity Management System
RISK CRITERIA
• Risk criteria are the standards which are used to
translate numerical risk estimates (e.g. 10-7 per
year) as produced by QRA into value judgement
(e.g. negligible risk) which can be set against
other judgement (e.g. high economic benefits) in
a decision-making process.
Upama Darshan
Pipeline Integrity Management System
RISK CRITERIA TERMINOLOGY
• An Intolerable region, within which the risk is generally
intolerable whatever the benefit may be. Risk reduction
measures or design changes are considered essential.
Upama Darshan
Pipeline Integrity Management System
INPUTS FOR QRA
• PFD/ P&IDs
Pressure
Temperature
Inventory
Pipeline/ Equipment sizing
Meterological Data
Onsite Manning/ Offsite Population Data
INPUT - POPULATION
SOFTWARE RUN
VIEW RESULTS
SOFTWARE OUTPUT
QRA OUTPUT
SOCIETAL RISK F-N CURVE
Upama Darshan
Pipeline Integrity Management System
QRA OUTPUT
SOCIETAL RISK
Upama Darshan
Pipeline Integrity Management System
INDIVIDUAL RISK CRITERIA
Upama Darshan
Pipeline Integrity Management System
INDIVIDUAL RISK CRITERIA
(Suggested by Health & Safety Executive, U.K)
for onshore installations
RISK LEVELS PUBLIC PLANT
(per year) PERSONNEL
(per year)
Maximum 1x 10 -4 1x 10 -3
Tolerable
Negligible 1x 10 -6 1x 10 -6
Upama Darshan
Pipeline Integrity Management System
SOCIETAL RISK CRITERIA
Upama Darshan
Pipeline Integrity Management System
SOCIETAL RISK CRITERIA
(Suggested by Health & Safety Commission, U.K)
for onshore installations
Cost of safeguards
Cost of accidents
Degree of Safety
Upama Darshan
Pipeline Integrity Management System
CHALLENGES IN QRA
Upama Darshan
Pipeline Integrity Management System
Upama Darshan
Pipeline Integrity Management System
29-08-2020
Regulatory Requirements
N Manohar Rao
Applicability
1
29-08-2020
Scope
shall cover all existing and new city gas distribution networks
including sub-transmission pipelines, city gas station, distribution
mains and piping facilities downstream of inlet isolation valve of city
gate station (inclusive of primary, secondary and tertiary networks)
including consumer meter for commercial or industrial customer and
up to final isolation valve including connecting hose to gas appliances
for domestic consumer.
Objectives.
2
29-08-2020
Objectives
The objective of Integrity Management System (IMS) is to –
ensure the integrity of CGD networks at all times to ensure public protection of
environment, maximum availability of CGD networks and also minimizing
business risks associated with operations of gas network.
ensure the quality of CGD network integrity in all areas which have potential
for adverse consequences
3
29-08-2020
Schedule 2
Management of Change
Quality Control
Pipeline Integrity Management System
Schedule 3
4
29-08-2020
Schedule 3
Schedule 3
Schedule 3
Other description
5
29-08-2020
Schedule 4
Selection of appropriate Integrity Management System
Schedule 4
Selection of appropriate Integrity Management System
Schedule 5
Integrity Assessment Tools
6
29-08-2020
Schedule 5
Integrity Assessment Tools
Stable Threats:
– Manufacturing related defects
– Defective pipe seam
– Defective pipe
Pipeline Integrity Management System
7
29-08-2020
Identification of Threats
Welding /fabrication related
• Defective pipe girth weld
• Defective fabrication weld
• Wrinkle bend or buckle
• Stripped threads /broken pipe /coupling failure
Equipment
• Gasket O-ring failure
• Control/relief equipment malfunction
• Seal pump packing failure
• Miscellaneous
Identification of Threats
Time independent Threats:
Identification of Threats
Incorrect operational procedure
8
29-08-2020
9
29-08-2020
Integrity Assessment
The following methods can be used for Integrity Assessment -
– Hydro testing before commissioning at test pressure as per
T4S standards;
– External Corrosion Direct Assessment(ECDA);
– Cathodic protection system surveys etc
10
29-08-2020
– Process measures
– Operational measures
– Direct integrity measures
Pipeline Integrity Management System
Schedule 6
Communication Plan
11
29-08-2020
Essential items will be focused for any internal and external audit
– Baseline Plan is being updated and followed
– qualifications of Operation and Maintenance personnel and
contractors based on education qualification, formal training,
demonstrated practical skills, and experience records
– adequate documentation to support decisions made
– Achievement of annual performance measures
Pipeline Integrity Management System
12
29-08-2020
13
29-08-2020
14
29-08-2020
– Design Stage
– Construction Stage (Commissioning)
– Facilities (erection, commissioning and O&M stage) – i.e. City
Gate Station, Odorant stations, Pressure Reducing Station
(PRS), Metering and Regulating Station (MRS)
– Operation and Maintenance (gas network)
15