Deliverables:
Scope of work package
Approved installation drawings and materials
User’s specifications and requirements
Pre-bid documents
Initial and Final Request for Proposal
Subcontractor’s bid evaluation report
Signed contracts with chosen subcontractor
Baseline schedules
All equipment/facility installation permits
Bi-weekly meetings and reports:
Project percentage performance
Project safety reports
Project QA inspection reports
Budget performance reports
Scope updates
Schedule updates
Change Requests
Work Breakdown Structure ENTC-5630
Project Title: Interdisciplinary research facility ETSU Date: 6/18/2017
WBS
Level Element Name Definition
Code
3 1.4.5 Punch listing (Scope validation) This are all works such as to minor repairs to make corrections, finishing operations,
cleanup after completion, works related to completing installations and uncompleted
work on changes made to project scope. These would have been identified during
execution of the job that does not conform to client requirement.
It is the responsibility of the Project Manager (client) to have a walkthrough exercise
with the building contractor in ensuring that all identified items on the punch list are
completely addressed.
Deliverables: Punch list timeline, Project record deliverables updates
2 1.5 Planning & Monitoring
3 1.5.1 Design approvals Shop drawings for the entire construction work must be submitted for
stakeholder/sponsor’s approval as and when indicated on project schedule milestones.
The project manager (client) to follow up on contractor to ensure designs are done
with stated tools and techniques in contract and client requirements.
Deliverables: Shop drawings and material submittals
2 1.5.2 Execution works monitoring Monitoring and control is throughout the project life cycle. Monitoring efforts shall be
intensified during the actual construction phases to ensure building contractor adheres
to approved designs, resources, schedule and enterprise stated factors. Fulfilling
stakeholder’s interest is critical at this stage.
All highlighted requirements in WBS 1.4.1 – 1.4.4 are applicable and to be complied
with.
Deliverables: As indicated in WBS 1.3.3; 1.3.4, sections 1 and 2.
3 1.5.3 Works inspection and approvals All works must be inspected by the project inspection team/project manager (client) to
ensure client’s requirements are satisfied in all aspects. The Project Manager (client
shall call the attention of the contractor to any identified work that does not meet the
client’s requirements, and document such on project punch list for walkthrough on a
later date.
Deliverables: Project percentage performance report, Project safety reports and Project
QA inspection reports
Work Breakdown Structure ENTC-5630
Project Title: Interdisciplinary research facility ETSU Date: 6/18/2017
WBS
Level Element Name Definition
Code
3 1.5.4 Work completion inspections Thorough inspection of project upon completion to be carried out and shall cover as
aspects of work from WBS 1.4.1 – 1.4.4. The inspection exercise be in two stages:
1. Client’s inspection team (including Project Manager – client) and the
contractor shall execute complete inspection and walkthrough of all works
done, including ensuring items on punch list have been addressed and closed-
out.
2. Stakeholder’s inspection of completed project.
Deliverables: Project acceptance/reject documentation, Project percentage
performance report, Project safety reports and Project QA inspection reports
3 1.5.5 Project takeover and handover Client to formally accept project as a post inspection exercise.
Deliverable: Final acceptance document
2 1.6 Project Delivery All works related to project handover and commissioning
2 1.6.1 Liability period During the project life cycle, it is the contractor’s responsibility to manage both legal
and risk management services associated with the execution of the job, in areas of
contracting issues, union relations, personnel issues, facility or equipment issue or
losses, and workers compensation.
It is also the contractor’s liability to pay state sales tax for all materials or equipment
leased or acquired for the project. It is the client’s responsibility to reimburse the
contractor for state sales tax for work performed during the contract execution.
However, contractor must follow due process to include all anticipated taxes within
project costing, bid markup cost or cost adjustments during the course of the project.
3 1.6.2 Release of final payments, dues Upon completion of work and all inspections have been concluded in WBS 1.6.3,
and resources contractor is to submit final invoices for unpaid balances to the client for approval and
onward payments.
Deliverables: Contractor and subcontractor payment invoices
Work Breakdown Structure ENTC-5630
Project Title: Interdisciplinary research facility ETSU Date: 6/18/2017
WBS
Level Element Name Definition
Code
3 1.6.3 Project closeout works At close out, the Project Manager (client) must ensure the following are completed on
the Project Close out checklist:
Project Charter
Project Management Plan
Project Management Control documents
Contract files
Correspondence
Status reports
Meeting notes
Technical Documents
Project resources (equipment/facilities, PCs, staff, etc.) utilized at client office
during the project are turned in to the office of Facilities Management,
Planning & Construction and signed out.
All financial records pertaining to the project
All Checklists
Documentation of project successes
Lessons Learned
Post-project Review/evaluation
The Project Manager, along with the project team the above activities are completed