You are on page 1of 6

Imperial Journal of Interdisciplinary Research (IJIR)

Vol-3, Issue-5, 2017


ISSN: 2454-1362, http://www.onlinejournal.in

Time Overrun in Construction Projects


of Developing Countries
Muhammad Akram Akhund1* , Ali Raza Khoso2 , Uroosa Memon3 ,
Shabeer Hussain Khahro 4
1
PhD. Scholar, Civil Engineering Department, Mehran UET, Jamshoro.
2
Lecturer, Civil Engineering Department, Mehran UET, Jamshoro.
3
Lecturer, Civil Engineering Department, Isra University, Hyderabad.
4
Lecturer, Department of EM, CoE, Prince Sultan University , Kingdom of Saudi Arabia.
Abstract: Delay in timely completion is one of the projects which were observed by the clients,
main issues in public sector construction projects of contractors and the consultants. They also studied the
developing countries. Time overrun can be defined causes which affected the productivity. They
as “a condition where a construction project does discovered differences on important factors between
not complete within the designed schedule”. these groups of their experiences, possible narrow
Different stakeholders are responsible for delay in mildness and lack of proper communication.
construction projects. This paper provides a
conceptual framework to overcome this issue. Two
important kinds of time overrun are considered in 2. Time Overrun in Construction
this study for developing the frame-work: one is Projects
excusable delay and second is non-excusable delay.
Based on the frame-work it identifies the critical Generally a time overrun (delay) is a condition the
factors causing time overrun. This study is aimed to actual work does not complete in an estimated time
help the industry practitioners in taking necessary period. Most of the construction projects experienced
measures for avoiding delay in public Sector from time overrun. Delay is the process in which the
construction projects. construction project slows down without stopping it
entirely while suppression is the stoppage of the
Keywords: Time overrun, Stakeholders, Construction project directed from the clients to the contractor.
projects, Developing Countries. Time overrun (delay) based on the two methods one
is the Inexcusable delay (Non - Excusable delay and
1. Introduction second is the Excusable delay shown in the bellow
figure 1. to see if your print area fits within the space
Time overrun is defined as “a condition where a allowed.
construction project does not complete within the
designed time period”. It happens when the work of 2.1. Inexcusable delays (Non- Excusable
contract does not complete in its prescribed time [ 1, delays)
2] . Time overrun is a most common incident which
occurs nearly in all the projects related to the Contractor or its suppliers are responsible for
construction industry. Time delay is critical in inexcusable delay and they are entitled to accelerate
developing countries where it exceeds its 100 % of their work done in estimated time are to pay
estimated time while constructing a project [3, 4]. A compensation to the owner. The contractor
lot of researches have been made to study delay compensate on the basis either on liquidated
causes in different countries. A study conducted by damages or actual da mages, provided that there is no
the Ogunlana et. a l., [ 5] on delay in building section of liquidated damages in the contact.
construction projects in Thailand, as an example of Liquated damages base on the daily rate of estimated
developing countries .They summarized that in costs which is likely to incur in the delay of
developing countries the problems related to the construction projects the owner by the contractor.
construction can be listed in three categories: 1.
caused by incompetence of contractors; 2. caused of 2.2. Excusable delays
shortages of constructing material 3. caused by
clients and consultants; and in Hong Kong There are two kinds of excusable delays discussed
Kumaraswamy and Chan [ 6] conduct a survey on as bellow:
the factors responsible for delay in construction

Imperial Journal of Interdisciplinary Research (IJIR) Page 124


Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-5, 2017
ISSN: 2454-1362, http://www.onlinejournal.in

2.1.1. Non-compensable delays: It is a delay survey was investigated by 23 contractors, 19


which is not caused by the owner and the contractor consultant and 15 owners. In this researcher 73
rather it is acted by third party. Examples include factors of delays were identified and these factors
natural calamity, unhealthy weather and wrong doing were grouped into 9 categories. It was concluded in
by masses (strikes, fires, acts of government in its survey that all factors related to the labour,
sovereign capacity, etc). Due to this, contractor gets contractor, project, owner and consultant are on the
extension in tie and does not pay any compensation highest rank and all three parties agreed to change
to the owner and contractor for delay damages. order.
Sambasivan and Soon [9] has surveyed the causes
2.1.2. Compensable delays: It is a delay which is of time overrun in Malaysian construction projects
not caused by third party but it is acted by the owner by surveying about 150 respondents. In this study he
or the owner's agents. An example of non- examined those 10 most important causes out of 28
completion of drawings in the required time by the different causes of delay. The ten most important
architect of the owner and it leads to the extension of causes were as bellow: Lack of communication
the schedule and it imposes economical da mages to between parties, improper planning, poor site
the owner by the contractor. In this condition, the management, inadequate contractor experience,
contractor will have to face extra indirect costs for inadequate client’s finance and payments for
both extended field office and home office. completed work, problems with subcontractors,
shortage in material, labor supply, Equipment
availability and failure and mistakes during the
construction stage.
In this research Abdullah et. al., [10] classify the
dominant causes of delay in large MA RA (Majlis
Amanah Rakyat) construction project from the
viewpoint of project management consultant (PMC).
The method used is questionnaires surveys which are
12 large MARA construction project were selected
for the survey. The data collected was analyzed by
using SPSS software. The result shown the five most
significant cause of construction delay are (1) cash
flow and financial difficulties by contractors, (2)
contractor's poor site management, (3) inadequate
contractor experience, (4) shortage of site workers
and (5) ineffective planning and scheduling by
contractors.
Chan and Kumaraswamy [11] conducted a
research survey in Hong Kong to evaluate and
3. Previous Studies on Time Overrun established the relative importance of significant
Many researchers have examined the main causes factors which were responsible for delays in
of construction delay in various types of construction construction projects. They evaluated and listed the
project. In Egypt a study conducted by Gündüz, et. main causes of delays in two categories (a ) the role
al., [7] in which he indicate that in the construction of the clients, consultants and contractor in the local
industry, The contractors increased their market construction project and (b) projects type. This
share for achieving the maximum profit. To achieve research concluded that there were five main causes
this plan, the contractors examined the factors wh ich for delay in construction projects were: poor site
are responsible for estimated impacts for the success management and supervision, unforeseen ground
of project before the bidding stage. These projects conditions, low speed of decision making involving
may differ in size, range, objectivity, ambiguity, all project teams, client initiated variations and
complexity, deadlines, etc. Delay means is a situation necessary variations of works.
where the actual work does not complete in an In Lebanon Mezher [12] took a survey from the
estimated time period which is agreed by the owners, contractors, and architectural/engineering
contractor. firms to find out the causes of delays in construction
In Saudi Arabia, Assaf et al. [ 8] conducted a project. It was analyzed that economical issues were
research about time overrun (delay) in different kinds most concerned with owners and contractors give
of construction project in the state. It was more importance to contractual relationships and
summarized that only 30% of construction projects consultants give priority to the project management
were complete within the time while 70% of issues.
construction projects experience time overrun. This Frimpong et al., [13] conducted a research survey
in Ghana to evaluate and established the relative

Imperial Journal of Interdisciplinary Research (IJIR) Page 125


Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-5, 2017
ISSN: 2454-1362, http://www.onlinejournal.in

importance of significant factors which were


responsible for delays in ground water construction
projects. A research of 26 factors on ground water Table.1. Average index value and rank of each factor
drilling projects in Ghana through questionnaire was causing time overrun
setup from the preliminary investigations conducted
1970 and 1999. The questionnaire was conducted No. Factors of Time Overrun A.I Rank
from the three groups working in ground water
projects were contractors, owners and consultants. Non-Excusable Delay
The questionnaire was distributed in 125 respondents
randomly out of which 55 respondents were owners, Delay in shop drawings and
1 3.89 1
sample materials
40respondants were contractors and 30respondants
were consultants. The outcome of survey revealed Poor communication and
2 3.89 1
the main factors of delays in ground water coordination between parties
construction projects were monthly payment Slowness in decision making
3 3.25 2
process.
difficulties from agencies; poor contractor
management; material procurement; poor technical 4 Suspension of work 3.10 3
performance; and inflation of material prices. 5 Inflexibility of consultants 3.05 4
In Jordan , a quantitative study carried out by Al- 6 Late in reviewing and approving 3.05 4
Momani [ 14] for identifying the delay causes in Design documentary by the
construction projects. It was summarized that there 7 2.99 5
consultants
were 7 main causes of construction delay were the
Conflicts between consultants and
designers, user changes, climatic changes, and site 8 2.99 5
design engineers
conditions, late deliveries of material, economic
9 Absence of consultants at site 2.95 6
conditions and increase in quantity.
Similarly, Odeh and Battaineh [15] a lso Delay to finish and deliver the
10 2.93 7
surveyed from the construction contractors and site work to the contractor
consultants to sort out main causes of delays in Change orders during
11 2.83 8
construction projects. It was concluded that the construction by the owners
contractors and consultant indicated that the top ten Financial problems (delayed
most important factors were owner interference, 12 Payments, financial difficulties, 2.80 9
inadequate contractor experience, financing and and economic problems).
payments, labor productivity, slow decision making, Contract modifications (replace
improper planning, and subcontractors. 13 and add new works to the project; 2.60 10
change in specifications)
4. Data Collection and Analysis Lack of consultant’s site staff
14 Experience (managerial and 2.60 10
Data collection was carried out using a structured supervisory personnel)
questionnaire survey to understand the opinion of the Supervision too late and slowness
15 2.60 10
construction practitioners to the time overrun in making decisions.
factors. The targeted respondents were the Unavailability of incentives for
stockholders registered with Pakistan Engineering 16 Contractor for finishing ahead of 2.58 11
Council (PEC). A five likert scale was adopted as 1- schedule
5 (Not Significant - Extremely Significant). Level of
significance were assessed with Statistical Software Excusable Delay (Non-Compensable)
Package SPSS using frequency and Average Index
(A I) method calculated with formula adopted from 1 Fire 2.99 1
Memon, A.H et a l., [16]. AI is calculated by using 2 Natural changing in environment 2.80 2
the following formula. The ranking of all factors are
3 Wind 2.78 3
shown in table. 1.
4 Snow fall 2.70 4
5 Delay in Transportation 2.70 4
AI = (1X1 + 2X2 + 3X3 + 4X4 + 5X5) 6 Contractor modification 2.10 5
 (X1 + X2 + X3 + X4 + X5) 7 Labour dispute and strike 2.95 6
8 Suspension in construction works 2.95 6

Excusable Delay (Compensable Delay)

1 Poor site management and 4.05 1

Imperial Journal of Interdisciplinary Research (IJIR) Page 126


Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-5, 2017
ISSN: 2454-1362, http://www.onlinejournal.in

supervision by contractor Non-Excusable Delay


Poor communication and 1. Delay in shop drawings and sample
2 coordination by contractor with 4.05 1 materials.
other parties
2. Poor communication and coordination
between parties.
3 Delays in sub-contractors work 4 2
3. Slowness in decision making process.
4 Frequent design changes 4 2 4. Suspension of work.
Inadequate planning and Non-Compensable Delay
5 4 2
scheduling 1. Fire
6 Lack of coordination on site 3.98 3 2. Natural changing in environment
Difficulties in financing project by 3. Wind
7 3.95 4 4. Snow fall
contractor
Compensable
Improper construction methods
8 3.92 5 1. Poor site management and supervision by
implemented by contractors
contractor.
Poor communication between 2. Poor communication and coordination by
9 3.92 5
contractors and other parties contractor with other parties.
Rework due to error during 3. Delays in sub-contractors work.
10 3.92 5
construction 4. Delays in sub-contractors work.
Underestimation of productivity
11 3.78 6
and inadequate review The results of table 1: showing that, “Delay in shop
12 Material Procurement 3.75 7 drawings and sample materials” is the top most
13 Material and fabrication Delays 3.75 7 causative factor of time overrun (Non-Excusable
Delay), similarly fire and Poor site management and
14 Poor skill labour 3.70 8
supervision by contractor are also the top most
15 Lack of high technology 3.68 9 causative factor of time overrun (Excusable Delays)
16 Underestimation of productivity 3.65 10 with an average index 3.89, 2.70 and 4.05
Conflicts in sub-contractors respectively.
17 3.40 11
Schedule in execution of project
Poor qualifications of the 6. Conclusion
contractors and sub-contractors
18 3.39 12
and technical staff at construction
The issue of time overrun in construction projects
site
has been unavoidable for many years. Its impacts are
so numerous that it leads to slow down the
5. Result and Discussion completion of plans of any country. The
improvement of time overruns causes both technical
A total of 160 questionnaires were distributed and project management related factors. This
randomly in different practitioners involved in improvement may also improve the influence of
construction industry in Pakistan. The resulting human attitudes, behavior, skills and mentality.
showing of received questionnaire set responses is Similarly, taking the same issues and problems the
106, of which 10 questionnaire sets were filled delay network has been proposed by a different angle
incomplete and invalid for analysis. Table 2 shows as shown in figure 2. The purpose of this study is to
the summary of data collection. provide positive and negative factors which cause
time overrun in a construction projects by the
Table.2. Summary of data collection theoretical frame work for the future study. To
No. of questionnaires were distributed to 160
respondents
validate the significant of the frame work it is
No. of questionnaires were received from 106 required the reliability and criticality of the
respondents framework.
No. of incomplete filled questionnaires from 10
respondents 7. Suggestion
No. of questionnaires valid for analysis 96
Suggestions’ to stockholders for controlling these
On the basis of average index the top most excusable and non-excusable delays of time overrun
factors of time overrun in the form of non- in construction industry of Pakistan.
excusable, non-compensable and compensable delay
found on construction industry site as follows. Stockholders playing a vital role for controlling
the time overrun issues by applying these methods to
the construction site.

Imperial Journal of Interdisciplinary Research (IJIR) Page 127


Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-5, 2017
ISSN: 2454-1362, http://www.onlinejournal.in

Effective site management and supervision,


Proper site investigation, Effective communication, Acknowledgements
Frequent progress meeting, Effective planning and The authors are thankful to the Chairman,
scheduling, Effective site management and Department of Civil Engineering, Mehran University
supervision, Establish system for design, Quality of Engineering and Technology, Jamshoro, Sindh,
and experienced labor, On time delivery of materials, Pakistan for his support in completing this research
Effective communication, Effective financial work.
management and control.

Time overrun (Delay)

Non-Excusable Delay
Excusable Delay

Non-Excusable Delay
Non-Compensable Compensable

 Delay in shop drawings and


sample materials. Fire. Poor site management and supervision
 Poor communication and Natural changing in environment. by contractor.
coordination between parties. Wind. Poor communication and coordination
 Slowness in decision making Snow fall. by contractor with other parties.
process. Delay in Transportation. Delays in sub-contractors work.
 Suspension of work. Contractor modification. Frequent design changes.
 Inflexibility of consultants. Labour dispute and strike. Inadequate planning and scheduling.
 Late in reviewing and approving. Suspension in construction works. Lack of coordination on site.
 Design documentary by the Difficulties in financing project by
consultants. contractor.
 Conflicts between consultants and Improper construction methods
design engineers. implemented by contractors.
 Absence of consultants at site. Poor communication between
 Delay to finish and deliver the site contractors and other parties.
work to the contractor. Rework due to error during
 Change orders during construction construction.
by the owners. Underestimation of productivity and
 Financial problems (delayed inadequate review.
Payments, financial difficulties, Material Procurement.
and economic problems). Material and fabrication Delays.
 Contract modifications (replace Poor skill labour.
and add new works to the project; Lack of high technology.
change in specifications). Underestimation of productivity.
 Lack of consultant’s site staff Conflicts in sub-contractors Schedule in
Experience (managerial and execution of project.
supervisory personnel). Poor qualifications of the contractors
 Supervision too late and slowness and sub-contractors and technical staff
in making decisions. at construction site.
 Unavailability of incentives for
Contractor for finishing ahead of
schedule.
Imperial Journal of Interdisciplinary Research (IJIR) Page 128

Figure 2: Frame-Work of Time Overrun


Imperial Journal of Interdisciplinary Research (IJIR)
Vol-3, Issue-5, 2017
ISSN: 2454-1362, http://www.onlinejournal.in

References International Journal of Project Management, 2002.


20(1): p. 67 - 73.
[17]. Hussin, J.M., I.A. Rahman, and A.H. Memon, The
[1]. Kaliba, C., M. Muya, and K. Mumba, Cost Way Forward in Sustainable Construction: Issues
escalation and schedule delays in road construction and Challenges. International Journal of Advances
projects in Zambia. International Journal of Project in Applied Sciences, 2013. 2(1): p. 15 - 24.
Management, 2009. 27(5): p. 522 - 531.
[2]. Memon, A.H., I.A. Rahman, and A.A.A. Azis, Time
and Cost Performance in Construction Projects in
Southern and Central Regions of Peninsular
Malaysia. International Journal of Advances in
Applied Sciences, 2012. 1(1): p. 45 -52.
[3]. Azhar, N., R.U. Farooqui, and S.M. Ahmed, Cost
overrun factors in construction industry of Pakistan.
Advancing and Integrating Construction Education,
Reseach & Practice, 2008: p. 499-508.
[4]. Le-Hoai, L., Y. Dai Lee, and J.Y. Lee, Delay and
cost overruns in Vietnam large construction projects:
a comparison with other selected countries. KSCE
journal of civil engineering, 2008. 12(6): p. 367-
377.
[5]. Ogunlana, S.O., K. Promkuntong, and V. Jearkjirm,
Construction delays in a fast-growing economy:
comparing Thailand with other economies.
International Journal of Project Management, 1996.
14(1): p. 37 - 45.
[6]. Kumaraswamy, M.M. and D.W. Chan, Contributors
to construction delays. Const ruct ion Management
& Economics, 1998. 16(1): p. 17-29.
[7]. Gündüz, M., Y. Nielsen, and M. Özdemir,
Quantification of Delay Factors Using the Relative
Importance Index Method for Construction Projects
in Turkey. Journal of Management in Engineering,
2013. 29(2): p. 133-139.
[8]. Assaf, S.A. and S. Al-Hejji, Causes of delay in large
construction projects. Internat ional Journal of
Project Management, 2006. 24(4): p. 349-357.
[9]. Sambasivan, M. and Y.W. Soon, Causes and effects
of delays in Malaysian construction industry.
Internat ional Journal of Project Management, 2007.
25(5): p. 517-526.
[10]. Abdullah, M., A. Abdul Azis, and I. Abdul Rahman,
Causes of delay and its effects in large MARA
construction project. International journal of
Integrated Engineering (Issue on Mechanical,
Materials and Manufacturing Engineering), 2009.
[11]. Chan, D.W. and M.M. Kumaraswamy, A
comparative study of causes of time overruns in
Hong Kong construction projects. International
Journal of Project Management, 1997. 15(1): p. 55 -
63.
[12]. Mezher, T.M. and W. Tawil, Causes of delays in the
construction industry in Lebanon. Engineering,
Construction and Architectural Management, 2006.
5(3): p. 252 - 260.
[13]. Frimpong, Y., J. Oluwoye, and L. Crawford, Causes
of delay and cost overruns in construction of
groundwater projects in a developing countries;
Ghana as a case study. International Journal of
Project Management, 2003. 21(5): p. 321 - 326.
[14]. Al-Momani, A.H., Construction delay: a quantitative
analysis. International Journal of Project
Management, 2000. 18(1): p. 51-59.
[15]. Odeh, A.M. and H.T Battaineh, Causes of
construction delay: traditional contracts.

Imperial Journal of Interdisciplinary Research (IJIR) Page 129

You might also like