The challenge
Power plants cooled with sea or river water require major
outage work and time for maintenance and service of the
essential cooling water intake systems. Due to the corrosive
nature of the sea or river water, these safety-classified
systems are often made of steel piping with inner rubber
coating, and regular inspection is highly recommended.
Even during outage, minimum one system has to be
operational. However, these systems have seen a series of
Sediments and corrosion on steel pipes
corrosion failures and even leaks in the past. These failures
due to cracked rubber coating and corrosion underneath
the coating required huge repair and maintenance efforts.
AREVA NP
Monitoring and Diagnositics
Leakage Monitoring and Detection System for GRP Pipes – GIMOS 2/2
Technical details
Conductive sensor layers are integrated during the GRP
manufacturing process. An external effect on the conduc-
tive layers gives an electric feedback. Using both sensor Monitoring
Module
layers as capacitors in combination with a test signal results
in leakage detectability and pre-leakage alarm signaling.
A connection to the outside of the pipe for every conduc-
tive layer is established with a metal bolt. These bolts act
as electric connection for diagnosis electronics to the pipe.
The diagnosis electronic is sealed in a robust metal box.
It contains a power supply, a micro controller-based mea-
surement system and a bus controller for communication
Coupling Sensor Simulated Erosion
with the central monitoring unit. Additional accelerometers
and temperature sensors can be applied to get further Pre-series demonstrator
information for aging and fatigue monitoring.
Monitoring Module
Sensor Layer