1 1 Drone To Home Project Fri 1/5/18 Fri 11/30/18
2 1.1 Create Project Management Plan Fri 1/5/18 Thu 2/1/18
3 1.1.1 Create Project Communication Plan Fri 1/5/18 Fri 1/5/18
4 1.1.1.1 Establish lines of Communication
5 1.1.2 Create Project Charter/Scope Mon 1/8/18 Fri 1/19/18
6 1.1.2.1 Define Business Objective and Case
7 1.1.2.2 Define Project Deliverables
8 1.1.2.2.1 Define Project Management
Deliverables
9 1.1.2.2.2 Define Software Development
Deliverables
10 1.1.2.2.3 Define Software Testing Deliverables

11 1.1.2.3 Evaluate Project Constraints


12 1.1.2.3.1 Evaluate In Scope Constraints
13 1.1.2.3.2 Evaluate Out of Scope Constraints
14 1.1.2.4 Create Project Organizational Structure
15 1.1.2.4.1 Appoint Roles and Responsibilities
16 1.1.2.4.2 Verify Stakeholders
17 1.1.2.4.2.1 Establish Internal Stakeholders
18 1.1.2.4.2.2 Establish External Stakeholders
19 1.1.2.5 Create High Level Milestones
20 1.1.2.5.1 Calculate Executive Milestones
21 1.1.2.6 Create Project Stategy
22 1.1.2.6.1 Develop Project Integration Plan
23 1.1.2.6.2 Develop Quality Management Plan
24 1.1.2.7 Create Risk and Mitigation Plan
25 1.1.2.7.1 Develop Risk Analysis Plan
26 1.1.2.7.1.1 Conduct Risk Analysis for Project
Reports
27 1.1.2.7.2 Develop Mitigation Approach

Page 1
ID Task WBS Task Name Start Finish
Mode
28 1.1.2.7.2.1 Conduct Mitigation Approach for
Project Reports
29 1.1.2.8 Estimate Project Plan / Schedule
30 1.1.2.8.1 Create Project Charter/Scope
31 1.1.2.8.2 Create WBS
32 1.1.2.8.3 Conduct Software Development
33 1.1.2.8.4 Conduct Software Testing
34 1.1.2.8.5 Conduct Implementation
35 1.1.2.8.6 Conduct Training
36 1.1.2.9 Create Risk Management Plan
37 1.1.2.9.1 Conduct Risk Analysis for Project
Reports
38 1.1.2.9.2 Conduct Mitigation Approach for
Project Reports
39 1.1.2.10 Develop Status Reports Plan
40 1.1.2.10.1 Determine Date/Time of Status Reports

41 1.1.2.10.2 Determine date/time of Close-out


Report
42 1.1.2.11 Develop Training Strategy
43 1.1.2.11.1 Initiate Technical Team Training
44 1.1.2.11.2 Establish End User line of
communication
45 1.1.2.11.3 Conduct End User Training and Provide
Manual
46 1.1.3 Create WBS Mon 1/22/18 Wed 1/31/18
47 1.1.3.1 Design Tasks and Workpackages
48 1.1.3.2 Create Resource Sheet Mon 1/22/18 Mon 1/22/18
49 1.1.3.2.1 Allocate Resources
50 1.1.3.3 Create Event Schedule
51 1.1.4 Conduct Project Status Report Thu 2/1/18 Thu 2/1/18
52 1.2 Initiate Software Development Fri 2/2/18 Wed 9/26/18
53 1.2.1 Provide Detailed Business Requirements Fri 2/2/18 Mon 2/5/18
Page 2
ID Task WBS Task Name Start Finish
Mode
54 1.2.2 Create Requirements Traceability Matrix Tue 2/6/18 Wed 2/7/18
55 1.2.3 Establish Programming Specifications Thu 2/8/18 Fri 2/9/18
56 1.2.4 Define High Level Solution Design Mon 2/12/18 Tue 2/13/18
57 1.2.5 Define Detailed Solutions Design Wed 2/14/18 Thu 2/15/18
58 1.2.6 Conduct Project Status Report Fri 2/16/18 Fri 2/16/18
59 1.2.7 Validate Custom Design Approval Fri 2/16/18 Fri 2/16/18
60 1.2.8 Intiate Wilmont Inventory Management Mon 2/19/18 Wed 3/21/18
System Modifications
61 1.2.9 Conduct Project Status Report Thu 3/22/18 Thu 3/22/18
62 1.2.10 Intiate Wilmont's Pharmacy Customer Fri 3/23/18 Tue 4/24/18
Database System Modification
63 1.2.11 Conduct Project Status Report Wed 4/25/18 Wed 4/25/18
64 1.2.12 Intiate DroneTech General Interface - Thu 4/26/18 Tue 5/22/18
Wilmont's Side System
65 1.2.13 Conduct Project Status Report Wed 5/23/18 Wed 5/23/18
66 1.2.14 Intiate Website Content Update - Wilmont's Thu 5/24/18 Fri 6/22/18
Side
67 1.2.15 Conduct Project Status Report Mon 6/25/18 Mon 6/25/18
68 1.2.16 Intiate Customer/Management Reporting Tue 6/26/18 Wed 7/18/18

69 1.2.17 Conduct Project Status Report Thu 7/19/18 Thu 7/19/18


70 1.2.18 Intiate Store Management Reporting Fri 7/20/18 Mon 8/13/18
71 1.2.19 Conduct Project Status Report Tue 8/14/18 Tue 8/14/18
72 1.2.20 Intiate Credit Card Processing Wed 8/15/18 Tue 8/28/18
73 1.2.21 Conduct Project Status Report Wed 8/29/18 Wed 8/29/18
74 1.2.22 Intiate Wilmont's Sales Management Thu 8/30/18 Tue 9/25/18
Reporting
75 1.2.23 Conduct Project Status Report Wed 9/26/18 Wed 9/26/18
76 1.3 Conduct Software Testing Thu 9/27/18 Tue 11/6/18
77 1.3.1 Initiate Technical Team Training Thu 9/27/18 Wed 10/3/18
78 1.3.2 Develop Testing Strategy Thu 10/4/18 Mon 10/8/18
79 1.3.3 Develop Order Entry Module Plan Tue 10/9/18 Tue 10/9/18

Page 3
ID Task WBS Task Name Start Finish
Mode
80 1.3.4 Conduct Order Entry Module Evaluation Thu 10/11/18 Fri 10/12/18
81 1.3.5 Evaluate Order Entry Module Log Mon 10/15/18 Mon 10/15/18
82 1.3.6 Conduct Project Status Report Tue 10/16/18 Tue 10/16/18
83 1.3.7 Determine Order Entry Module Approval Tue 10/16/18 Tue 10/16/18
84 1.3.8 Develop confirmation Module Plan Wed 10/17/18 Wed 10/17/18
85 1.3.9 Conduct Delivery confirmation Module Thu 10/18/18 Fri 10/19/18
Evaluation
86 1.3.10 Evaluate Delivery confirmation Module Test Mon 10/22/18 Mon 10/22/18
Log
87 1.3.11 Conduct Project Status Report Tue 10/23/18 Tue 10/23/18
88 1.3.12 Determine Delivery Confirmation Module Tue 10/23/18 Tue 10/23/18
Approval
89 1.3.13 Develop Mobile Application Module Plan Wed 10/24/18 Wed 10/24/18
90 1.3.14 Conduct Mobile Application Module Thu 10/25/18 Fri 10/26/18
Evaluation
91 1.3.15 Evaluate Mobile Application Module Test Log Mon 10/29/18 Mon 10/29/18

92 1.3.16 Conduct Project Status Report Tue 10/30/18 Tue 10/30/18


93 1.3.17 Determine Mobile Application Approval Tue 10/30/18 Tue 10/30/18
94 1.3.18 Develop System integration Plan Wed 10/31/18 Wed 10/31/18
95 1.3.19 Conduct System integration Evaluation Thu 11/1/18 Fri 11/2/18
96 1.3.20 Evaluate System integration Log Mon 11/5/18 Mon 11/5/18
97 1.3.21 Conduct Project Status Report Tue 11/6/18 Tue 11/6/18
98 1.3.22 Determine System Integration Approval Tue 11/6/18 Tue 11/6/18
99 1.4 Implement Modified System Wed 11/7/18 Thu 11/15/18
100 1.4.1 Initiate System Modifications Wed 11/7/18 Tue 11/13/18
101 1.4.2 Conduct Project Status Report Thu 11/15/18 Thu 11/15/18
102 1.4.3 Evaluate Implementation and Signoff Wed 11/14/18 Wed 11/14/18
103 1.5 Conduct End User Training Fri 11/16/18 Fri 11/30/18
104 1.5.1 Establish End User line of communication Fri 11/17/17 Fri 11/17/17
105 1.5.2 Conduct End User Training and Provide Mon 11/19/18 Tue 11/27/18
Manual

Page 4
ID Task WBS Task Name Start Finish
Mode
106 1.5.3 Conduct Project Close-out Report Wed 11/28/18 Thu 11/29/18
107 1.5.4 Initiate First Flight Fri 11/30/18 Fri 11/30/18