1 1 Drone To Home Project Fri 1/5/18 Fri 11/30/18
2 1.1 Create Project Management Plan Fri 1/5/18 Thu 2/1/18
3 1.1.1 Create Project Communication Plan Fri 1/5/18 Fri 1/5/18
4 1.1.1.1 Establish lines of Communication
5 1.1.2 Create Project Charter/Scope Mon 1/8/18 Fri 1/19/18
6 1.1.2.1 Define Business Objective and Case
7 1.1.2.2 Define Project Deliverables
8 1.1.2.2.1 Define Project Management
Deliverables
9 1.1.2.2.2 Define Software Development
Deliverables
10 1.1.2.2.3 Define Software Testing Deliverables
Page 1
ID Task WBS Task Name Start Finish
Mode
28 1.1.2.7.2.1 Conduct Mitigation Approach for
Project Reports
29 1.1.2.8 Estimate Project Plan / Schedule
30 1.1.2.8.1 Create Project Charter/Scope
31 1.1.2.8.2 Create WBS
32 1.1.2.8.3 Conduct Software Development
33 1.1.2.8.4 Conduct Software Testing
34 1.1.2.8.5 Conduct Implementation
35 1.1.2.8.6 Conduct Training
36 1.1.2.9 Create Risk Management Plan
37 1.1.2.9.1 Conduct Risk Analysis for Project
Reports
38 1.1.2.9.2 Conduct Mitigation Approach for
Project Reports
39 1.1.2.10 Develop Status Reports Plan
40 1.1.2.10.1 Determine Date/Time of Status Reports
Page 3
ID Task WBS Task Name Start Finish
Mode
80 1.3.4 Conduct Order Entry Module Evaluation Thu 10/11/18 Fri 10/12/18
81 1.3.5 Evaluate Order Entry Module Log Mon 10/15/18 Mon 10/15/18
82 1.3.6 Conduct Project Status Report Tue 10/16/18 Tue 10/16/18
83 1.3.7 Determine Order Entry Module Approval Tue 10/16/18 Tue 10/16/18
84 1.3.8 Develop confirmation Module Plan Wed 10/17/18 Wed 10/17/18
85 1.3.9 Conduct Delivery confirmation Module Thu 10/18/18 Fri 10/19/18
Evaluation
86 1.3.10 Evaluate Delivery confirmation Module Test Mon 10/22/18 Mon 10/22/18
Log
87 1.3.11 Conduct Project Status Report Tue 10/23/18 Tue 10/23/18
88 1.3.12 Determine Delivery Confirmation Module Tue 10/23/18 Tue 10/23/18
Approval
89 1.3.13 Develop Mobile Application Module Plan Wed 10/24/18 Wed 10/24/18
90 1.3.14 Conduct Mobile Application Module Thu 10/25/18 Fri 10/26/18
Evaluation
91 1.3.15 Evaluate Mobile Application Module Test Log Mon 10/29/18 Mon 10/29/18
Page 4
ID Task WBS Task Name Start Finish
Mode
106 1.5.3 Conduct Project Close-out Report Wed 11/28/18 Thu 11/29/18
107 1.5.4 Initiate First Flight Fri 11/30/18 Fri 11/30/18