Professional Documents
Culture Documents
Abstract: Fly ash and bottom ash are coal combustion by-products 共CCBPs兲 that are generated in large quantities throughout the world.
It is often economical to dispose ash as mixtures rather than separately; that notwithstanding, only a few studies have been performed to
investigate the behavior of fly and bottom ash mixtures, particularly those with high contents of fly ash. Also, there is very limited data
available in the literature on the field performance of structures constructed using ash mixtures. This paper describes the construction and
the instrumentation of a demonstration embankment built with an ash mixture 共60:40 by weight of fly ash:bottom ash兲 on State Road 641,
Terre Haute, Ind. Monitoring of the demonstration embankment was conducted for a period of 1 year from the start of construction of the
embankment. The settlement of the embankment stabilized approximately 5 months after the end of its construction. According to
horizontal inclinometer readings, the differential settlement at the top of the embankment is about 5 mm. Results from field quality control
tests performed during construction of the demonstration embankment and monitoring data from vertical and horizontal inclinometers and
settlement plates indicate that the ash mixture investigated can be considered an acceptable embankment construction material.
DOI: 10.1061/共ASCE兲0899-1561共2009兲21:6共271兲
CE Database subject headings: Fly ash; Bottom ash; Embankment; Field tests; Quality control; Settlement.
are very limited studies on the properties of fly and bottom ash order to better characterize the geotechnical properties of the
mixtures 共Kim et al. 2005兲, as most research studies have focused ashes used in the construction of the demonstration embankment,
on the engineering and environmental behavior of either Indiana the chemical composition of two different ash samples 共both fly
fly ash or bottom ash 共Diamond 1985; Diamond and Olek 1988; ash and bottom ash samples兲 was analyzed. The specific gravity,
Huang 1990; Ke 1990; Alleman et al. 1996兲. grain size distribution and compaction characteristics of the ash
In order to investigate the mechanical behavior of mixtures mixture 共60/ 40 by weight of fly ash:bottom ash兲 used in the con-
with various fly ash contents, a research study consisting of two struction of the embankment were determined.
phases was funded by INDOT. The first phase involved a com-
prehensive laboratory testing program to characterize the behav-
ior of fly and bottom ash mixtures. The second phase of the Chemical Composition
research focused on the construction, instrumentation, and moni- The chemical composition of ash depends on the characteristics
toring of the field performance of a demonstration embankment and composition of the coal burned in power plants. Table 2
constructed using a fly and bottom ash mixture. Kim et al. 共2005兲 shows the oxide composition of the fly ash and bottom ash used
presented the results of the laboratory testing program performed in the construction of the demonstration embankment. The major
on three different ash mixtures 共with fly ash contents of 50, 75, constituents of these ashes are SiO2, Al2O3, and Fe2O3. These
and 100% by weight兲. The laboratory study indicated that fly and three oxides combined constitute about 86 and 70% 共by mass兲 of
bottom ash mixtures exhibit relatively higher peak-friction angle the fly ash and bottom ash, respectively.
共peak values ranging from 30 to 47°兲 and lower dry unit weight
共ranging from 14.1 to 17.7 kN/ m3兲 than typical fill materials of
comparable particle size 共Kim et al. 2005兲. In addition, the hy- Specific Gravity
draulic conductivity of fly and bottom ash mixtures is similar to
The specific gravity Gs of fly ash and bottom ash varies with the
that of a fine sandy silt or silt 共ranging from 2 ⫻ 10−6 to 1
chemical composition of the coal burned in power plants. Higher
⫻ 10−5 cm/ s兲. These laboratory test results showed that fly and
iron contents in the ash lead to higher specific gravity values.
bottom ash mixtures can perform satisfactorily when used as fill
Typical values of Gs range from 2.1 to 2.9 for Class-F fly ash
materials in the construction of embankments and retaining struc-
共McLaren and DiGioia 1987兲 and, from 2.0 to 2.6 for bottom ash
tures 共Kim 2003兲.
共Seals et al. 1972; Moulton 1973; Anderson et al. 1976; Majidza-
Based on the laboratory test results, a demonstration embank-
deh et al. 1977兲. The specific gravity of the fly and bottom ash
ment was designed and constructed in the state of Indiana. The
mixture 共60/ 40 by weight of fly ash:bottom ash兲 that was used in
construction sequence, instrumentation, and performance evalua-
tion of the ash-mixture 共60:40 by weight of fly ash:bottom ash兲
embankment are reported in this paper. The ashes used were gen-
erated at the Wabash River Power Plant located in Central Indiana
and owned by Cinergy Co. 共now known as Duke Energy兲. The
power plant burns bituminous coal using pulverized coal-burning
units. Class-F fly ash and bottom ash generated by the Wabash
River Power Plant are codisposed in a nearby disposal pond using
the wet method 共see Fig. 1兲. The fly and bottom ash mixture
reclaimed from the disposal pond was stored and drained to reach
a moisture content close to its optimum moisture content as de-
termined from laboratory compaction tests.
The geotechnical properties of ash mixtures vary considerably Fig. 1. Disposal pond of fly and bottom ash mixture generated at
based on their source, chemical composition, and gradation. In Wabash River Power Plant
K 2O 2.55 1.79
Na2O 0.38 0.27
SO3 0.07 0.21
Fig. 3. Compaction curve for the fly and bottom ash mixture
P 2O 5 0.14 0.13
SrO 0.05 0.04
Mn3O4 0.04 0.03
Design and Construction of the Demonstration Ash
Embankment
mation of the ash mixture 共there were only minor imprints of the
wheels left behind on the surface of the mixture兲. Fig. 6 shows the
placement and compaction of the fly and bottom ash mixture used
for the embankment construction.
Quality Control
Quality control 共QC兲 of the compacted ash was done for every lift
共150 mm兲 at 15-m intervals along the embankment length. QC
Fig. 4. Location of the settlement plates and piezometers was done in two ways: 共1兲 using the nuclear gauge and
microwave-oven heating tests to determine the in situ density and
in situ water content of the compacted ash mixture; and 共2兲 using
Dynamic Cone Penetration Test the DCPT.
Fig. 7 illustrates the relationship between the DCPT blow
The DCPT consists of upper and lower shafts. The upper shaft, count per 150-mm penetration and the in situ dry unit weight of
which has a 0.078-kN hammer with a 575-mm-drop height, is
attached to the lower shaft through the anvil. The lower shaft
consists of an anvil and a cone attached at its end. The cone has a
60°-apex angle. DCPTs were performed in accordance with
ASTM D 6951 共2003兲 at the same locations in the test pad as the
nuclear gauge and microwave oven tests. The DCPT results on
the compacted ash indicated consistently that 5–7 blow counts
were required for the dynamic cone to penetrate a thickness of
one lift 共150 mm兲. Based on these results, a DCPT blow count of
more than 6 per 150-mm penetration into the compacted ash was
expected to indicate 95% relative compaction or better.
Embankment Compaction
Based on the evaluation of the test pad results, a 150-mm-lift
thickness and three vibratory roller passes per lift using a D-10
vibratory roller manufactured by Caterpillar Inc. 共CAT CS-563D
with 266 kN centrifugal force兲 were recommended in order to
achieve 95% relative compaction. Each layer of ash was uni-
formly placed across the length of the roadway cross section. A
steel track bulldozer 共CAT D7 50兲 was then used to spread out the Fig. 6. Construction of the embankment: 共a兲 placement of fly and
fill material and to provide additional compaction. Passage of the bottom ash-mixture; 共b兲 compaction of fly and bottom ash mixture
heavy construction equipment did not cause any significant defor- layer
section are shown in Fig. 8. The settlement data obtained from the
bottom plates at locations 7.8 and 17.7 m on the southeast side of
the embankment are not shown for the entire 1 year period be-
cause these settlement plates were damaged during construction.
Fig. 7. DCPT blow count versus field dry unit weight of the ash
The maximum settlement, which was more or less the same
mixture
for the two bottom plates, was equal to about 80 mm, and it
stabilized about 8 months after the start of construction. The
the compacted ash. The blow count increases as the dry density settlement at the midheight of the embankment stabilized to a
increases. An empirical correlation for the DCPT blow count maximum value of about 70 mm about 7 months after the instal-
共BC兲, derived in terms of the in situ dry unit weight 共for water lation of the plates. A total settlement of 20 mm was recorded at
contents ranging from 20.4 to 23.8%兲, is as follows: the top of the ash embankment approximately 4 months after the
installation of the settlement plates.
BC = 3␥d − 40.5 共1兲
where BC= blow count per 150-mm penetration and ␥d = dry unit Piezometers
weight 共kN/ m3兲 as obtained from the nuclear gauge tests. Due to
scatter of the data points observed in Fig. 7, caution should be Piezometric elevations were monitored during the construction of
exercised when using the above-mentioned correlation in prac- the embankment to meet the design requirements for staged con-
tice. Note that Eq. 共1兲 relates the DCPT blow count to a single struction. Two piezometers were installed along Section 6 + 250
soil property. Other parameters 共such as the soil water content and within the foundation soil. They are located 9 m from the center-
stiffness兲 affect the DCPT blow count as well. As these param- line of the embankment on both its sides. The piezometric data
eters were not accounted for in the previous correlation, it can collected during construction of the embankment are shown in
only be considered as a general reference for quality control of Table 3. The piezometric levels were maintained below the criti-
compacted densities of ash mixtures. One should also consider cal pore water pressure values at all times.
specific site conditions and characteristics of the materials com-
pacted in the field when establishing quality control procedures. Horizontal Inclinometers
The horizontal inclinometer monitoring system consists of an in-
Environmental Considerations clinometer casing 共outer diameter= 70 mm兲, a portable horizontal
Leaching of trace metals from fly and bottom ash is the main inclinometer probe and control cable, and an inclinometer readout
environmental concern when these materials are used in embank- unit. The horizontal inclinometer was installed on top of the ash
ment construction. Migration of metals from ash into groundwater embankment along Section 6 + 260 in order to monitor differential
has been studied in a number of high-volume ash projects 共Srivas- settlement 共see Fig. 4兲. Monitoring started about three months
tava and Collins 1989; Rehage and Schrab 1995; Alleman et al. after the installation of the horizontal inclinometer due to inac-
1996兲. According to these studies, groundwater contamination cessible site conditions. The horizontal inclinometer data are
due to coal ash usage was minimal. Longer term studies are nec- shown in Fig. 9. A maximum differential settlement of 5 mm was
essary for more definite conclusions on the environmental impact observed in the middle of the embankment after approximately
of ash embankment construction. 5 months of monitoring of the horizontal inclinometer. These re-
sults show that the differential settlements in the embankment
were minimal.
Field Instrumentation Program
Vertical Inclinometers
The performance of the embankment was monitored using settle-
ment plates, piezometers, and horizontal and vertical inclinom- As shown in Fig. 5, two vertical inclinometer casings were in-
eters installed during construction. The results are presented in the stalled: one on the shoulder and one on the toe of the embank-
following sections. ment. The vertical inclinometer on the shoulder can detect lateral
movement of the slope, and the one on the toe, the movement of
the original ground. The vertical inclinometers were installed
Settlement Plates
after completion of the embankment construction. The lateral
A total of ten settlement plates were installed along the midsec- movement of the test embankment was monitored after the end of
tion of the embankment 共Section 6 + 250兲. These settlement plates embankment construction. Fig. 10 shows the lateral movement
were installed at three different depths 共bottom, midheight, and recorded at the shoulder and toe of embankment. A maximum
Fig. 8. Settlement versus number of days after start of construction: 共a兲 7.8 m northwest side; 共b兲 17.7 m northwest side; 共c兲 7.8 m southeast side;
and 共d兲 17.7 m southeast side
lateral movement of about 3 mm was observed at the shoulder of sandy silt 共ML兲 according to the USCS. The height, length
the embankment after about 4 months of monitoring. A lateral and width of the test embankment are equal to 7.6, 60, and
movement of less than 1 mm was observed at the toe of the em- 100 m, respectively.
bankment after about 4 months of monitoring, indicating that 2. The maximum dry unit weight and the optimum moisture
there was basically no movement in the foundation soil. The em- content of the ash mixture were found to be equal to
bankment is stable considering the minimal lateral movements 15.0 kN/ m3 and 19%, respectively. The ash mixture is
recorded. lighter than typical fill materials used in highway construc-
tion.
3. Compaction procedures for the demonstration embankment
Summary and Conclusions were determined based on test pad results. Based on the test
pad results, it was concluded that a DCPT blow count of
The following summarizes the work done and the results of the more than 6 per 150-mm penetration into the compacted ash
laboratory testing and field instrumentation program: would guarantee that 95% of the laboratory ␥d,max would be
1. A high-volume ash-mixture demonstration embankment was achieved in the field. Nuclear gauge, microwave oven, and
constructed at State Rd. 641, in Terre Haute, Ind. The fill DCPT tests were used for compaction quality control.
material consists of a mixture of Class F-fly ash and bottom 4. A preliminary empirical correlation between the DCPT blow
ash 共60:40 by weight兲. The ash mixture was classified as count and ␥d,max was proposed based on the data available.
Acknowledgments
Geotech. Geoenviron. Eng., 131共7兲, 914–924. Seals, R. K., Moulton, L. K., and Ruth, B. E. 共1972兲. “Bottom ash: an
Majidzadeh, K., El-Mitiny, R. N., and Bokowski, G. 共1977兲. “Power engineering material.” J. Soil Mech. and Found. Div., 98共4兲, 311–325.
plant bottom ash in black base and bituminous surfacing.” Vol. 2, Srivastava, L., and Collins, R. J. 共1989兲. “Ash utilization in highways:
User’s manual, publication No. FHWA-RD-78-148, FHWA, U.S. De- Delaware demonstration project.” GS-6481, Research Project No.
partment of Transportation, Washington, D.C. 2422-3, Interim Rep., Electric Power Research Institute, Palo Alto,
Calif.
McLaren, R. J., and DiGioia, A. M. 共1987兲. “The typical engineering
Usmen, M. A., Head, W. J., and Moulton, L. K. 共1983兲. “Use of coal-
properties of fly ash.” Proc., Geotechnical Practice for Waste Dis- associated wastes in low-volume roads.” Transportation Research
posal ’87, Geotechnical Special Publication No. 13, E. Wood, ed., Record. 898, Transportation Research Board, National Research
ASCE, New York, 683–697. Council, Washington, D.C., 268–277.