You are on page 1of 8

Construction of an Embankment with a Fly and Bottom Ash

Mixture: Field Performance Study


Sungmin Yoon, Ph.D.1; Umashankar Balunaini2; Irem Z. Yildirim3; Monica Prezzi, Ph.D.4; and
Nayyar Z. Siddiki5
Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Fly ash and bottom ash are coal combustion by-products 共CCBPs兲 that are generated in large quantities throughout the world.
It is often economical to dispose ash as mixtures rather than separately; that notwithstanding, only a few studies have been performed to
investigate the behavior of fly and bottom ash mixtures, particularly those with high contents of fly ash. Also, there is very limited data
available in the literature on the field performance of structures constructed using ash mixtures. This paper describes the construction and
the instrumentation of a demonstration embankment built with an ash mixture 共60:40 by weight of fly ash:bottom ash兲 on State Road 641,
Terre Haute, Ind. Monitoring of the demonstration embankment was conducted for a period of 1 year from the start of construction of the
embankment. The settlement of the embankment stabilized approximately 5 months after the end of its construction. According to
horizontal inclinometer readings, the differential settlement at the top of the embankment is about 5 mm. Results from field quality control
tests performed during construction of the demonstration embankment and monitoring data from vertical and horizontal inclinometers and
settlement plates indicate that the ash mixture investigated can be considered an acceptable embankment construction material.
DOI: 10.1061/共ASCE兲0899-1561共2009兲21:6共271兲
CE Database subject headings: Fly ash; Bottom ash; Embankment; Field tests; Quality control; Settlement.

Introduction bottom ash in high-volume construction projects, besides allevi-


ating the growing disposal problems, offers a promising way to
According to the American Coal Ash Association 共ACAA兲, about help preserve dwindling naturally available building materials.
123 million t of coal combustion by-products 共CCBPs兲 were pro- Fly ash has been used extensively in embankment construc-
duced in 2005 共ACAA 2005兲. Of this total production, fly ash and tion. Table 1 lists some of the high-volume embankments con-
bottom ash accounted for nearly 71 and 18 million t, respectively; structed throughout the United States using class-F fly ash
about 72% of the total production of CCBPs. However, only 41% 共Patelunas 1986; Srivastava and Collins 1989兲. There are also
of the total production of fly and bottom ash has been recycled. some studies that indicate that bottom ash is an appropriate ma-
Unused fly ash and bottom ash are disposed either in landfills or terial for embankment construction 共Seals et al. 1972; Moulton et
in ponds. They are usually disposed either with the dry method or al. 1973; Huang 1990兲. Whenever fly ash and bottom ash are
the wet method 共Usmen et al. 1983兲. In the dry method, dry ash is codisposed, use of ash mixtures as embankment fill materials is
hauled, placed, and compacted at the disposal sites; whereas in the preferred alternative. However, there is very limited informa-
the wet method, ash is mixed with sufficient amounts of water, tion in the literature on the behavior of fly and bottom ash mix-
and the ash slurry is then transported through pipelines to the tures, and even lesser information on the field performance of
disposal ponds or lagoons. Fly ash and bottom ash are disposed structures constructed using ash mixtures 共Karim 1997; Kim
either separately or together in disposal ponds. Due to increasing 2003兲. This paper reports the monitoring data obtained during a
disposal costs, reduction of landfill space, and need for conserva- period of about 1 year 共from May 2005 to April 2006兲 for a dem-
tion of natural resources, it is essential to identify applications onstration embankment constructed using a fly and bottom ash
that involve the use of large volumes of ash. Use of fly ash and mixture 共60:40 by weight of fly ash:bottom ash兲 and the results of
laboratory tests performed on samples collected from the con-
1
Research Associate, Louisiana Transportation Research Center, struction site.
Baton Rouge, LA 70808. E-mail: syoon@lsu.edu
2
Doctoral Student, School of Civil Engineering, Purdue Univ., West
Lafayette, IN 47907-1284. E-mail: ubalunai@purdue.edu
3
Doctoral Student, School of Civil Engineering, Purdue Univ., West Background
Lafayette, IN 47907-1284. E-mail: iyildiri@purdue.edu
4
Associate Professor, School of Civil Engineering, Purdue Univ., In the state of Indiana, more than 66% of the CCBPs produced are
West Lafayette, IN 47907-1284. E-mail: mprezzi@ecn.purdue.edu
5
disposed as class-F fly ash and bottom ash mixtures 共GAI/
Division of Materials and Tests, Indiana Dept. of Transportation, In- USIFCAU 1993兲. According to the ACAA, fly ash and bottom
dianapolis, IN 46219-038. E-mail: NSIDDIKI@indot.IN.gov ash are typically produced and disposed in the ratio of 80:20 共fly
Note. This manuscript was submitted on December 27, 2007; ap-
ash:bottom ash ratio by weight兲 共ACAA 2005兲. However, current
proved on November 25, 2008; published online on May 15, 2009. Dis-
cussion period open until November 1, 2009; separate discussions must Indiana Department of Transportation 共INDOT兲 specifications for
be submitted for individual papers. This paper is part of the Journal of coal ash utilization in highway construction allow only mixtures
Materials in Civil Engineering, Vol. 21, No. 6, June 1, 2009. ©ASCE, with fly ash content less than 40%. Even though it is advanta-
ISSN 0899-1561/2009/6-271–278/$25.00. geous to use the as-disposed ash mixtures in construction, there

JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009 / 271

J. Mater. Civ. Eng., 2009, 21(6): 271-278


Table 1. List of Projects Using Fly Ash for High-Volume Embankment Construction 共Patelunas 1986; Srivastava and Collins 1989兲
State Year Project description Estimated tonnage or volume
Arizona 1980 I-40, Joseph City 46,300 m3
Delaware 1987 I-495, Wilmington 6,110 m3
Illinois 1972 LR 437, Waukegan 188,700 m3
Massachusetts 1978 John Scott Blvd., Norton 3,820 m3
Minnesota 1979 SR 13, Eagan 267,400 m3
Minnesota 1975 High Bridge Plant, St. Paul 9,932 m3
Ohio 1981 I-480, Avon 30,000 t
Ohio 1983 US 35, Gallia County 27,000 t
145,160 m3
Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

Pennsylvania 1967 Culver Road, Hopewell Township


Virginia 1978 SR 665, Carbo 300 t
Wisconsin 1976–1977 Milwaukee 120,000 t
Wyoming 1976 US 60, Morgantown 40,000 t
Wyoming 1971 US 250, Fairmont 5,000 t

are very limited studies on the properties of fly and bottom ash order to better characterize the geotechnical properties of the
mixtures 共Kim et al. 2005兲, as most research studies have focused ashes used in the construction of the demonstration embankment,
on the engineering and environmental behavior of either Indiana the chemical composition of two different ash samples 共both fly
fly ash or bottom ash 共Diamond 1985; Diamond and Olek 1988; ash and bottom ash samples兲 was analyzed. The specific gravity,
Huang 1990; Ke 1990; Alleman et al. 1996兲. grain size distribution and compaction characteristics of the ash
In order to investigate the mechanical behavior of mixtures mixture 共60/ 40 by weight of fly ash:bottom ash兲 used in the con-
with various fly ash contents, a research study consisting of two struction of the embankment were determined.
phases was funded by INDOT. The first phase involved a com-
prehensive laboratory testing program to characterize the behav-
ior of fly and bottom ash mixtures. The second phase of the Chemical Composition
research focused on the construction, instrumentation, and moni- The chemical composition of ash depends on the characteristics
toring of the field performance of a demonstration embankment and composition of the coal burned in power plants. Table 2
constructed using a fly and bottom ash mixture. Kim et al. 共2005兲 shows the oxide composition of the fly ash and bottom ash used
presented the results of the laboratory testing program performed in the construction of the demonstration embankment. The major
on three different ash mixtures 共with fly ash contents of 50, 75, constituents of these ashes are SiO2, Al2O3, and Fe2O3. These
and 100% by weight兲. The laboratory study indicated that fly and three oxides combined constitute about 86 and 70% 共by mass兲 of
bottom ash mixtures exhibit relatively higher peak-friction angle the fly ash and bottom ash, respectively.
共␾peak values ranging from 30 to 47°兲 and lower dry unit weight
共ranging from 14.1 to 17.7 kN/ m3兲 than typical fill materials of
comparable particle size 共Kim et al. 2005兲. In addition, the hy- Specific Gravity
draulic conductivity of fly and bottom ash mixtures is similar to
The specific gravity Gs of fly ash and bottom ash varies with the
that of a fine sandy silt or silt 共ranging from 2 ⫻ 10−6 to 1
chemical composition of the coal burned in power plants. Higher
⫻ 10−5 cm/ s兲. These laboratory test results showed that fly and
iron contents in the ash lead to higher specific gravity values.
bottom ash mixtures can perform satisfactorily when used as fill
Typical values of Gs range from 2.1 to 2.9 for Class-F fly ash
materials in the construction of embankments and retaining struc-
共McLaren and DiGioia 1987兲 and, from 2.0 to 2.6 for bottom ash
tures 共Kim 2003兲.
共Seals et al. 1972; Moulton 1973; Anderson et al. 1976; Majidza-
Based on the laboratory test results, a demonstration embank-
deh et al. 1977兲. The specific gravity of the fly and bottom ash
ment was designed and constructed in the state of Indiana. The
mixture 共60/ 40 by weight of fly ash:bottom ash兲 that was used in
construction sequence, instrumentation, and performance evalua-
tion of the ash-mixture 共60:40 by weight of fly ash:bottom ash兲
embankment are reported in this paper. The ashes used were gen-
erated at the Wabash River Power Plant located in Central Indiana
and owned by Cinergy Co. 共now known as Duke Energy兲. The
power plant burns bituminous coal using pulverized coal-burning
units. Class-F fly ash and bottom ash generated by the Wabash
River Power Plant are codisposed in a nearby disposal pond using
the wet method 共see Fig. 1兲. The fly and bottom ash mixture
reclaimed from the disposal pond was stored and drained to reach
a moisture content close to its optimum moisture content as de-
termined from laboratory compaction tests.

Fly and Bottom Ash Mixture Characterization

The geotechnical properties of ash mixtures vary considerably Fig. 1. Disposal pond of fly and bottom ash mixture generated at
based on their source, chemical composition, and gradation. In Wabash River Power Plant

272 / JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009

J. Mater. Civ. Eng., 2009, 21(6): 271-278


Table 2. Chemical Composition of Fly and Bottom Ash Produced by the
Wabash River Plant
% by mass

Constituent Fly ash Bottom ash


SiO2 51.13 39.64
Al2O3 22.91 15.08
Fe2O3 12.18 15.02
TiO2 1.01 0.70
CaO 1.54 2.04
MgO 0.73 0.79
Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

K 2O 2.55 1.79
Na2O 0.38 0.27
SO3 0.07 0.21
Fig. 3. Compaction curve for the fly and bottom ash mixture
P 2O 5 0.14 0.13
SrO 0.05 0.04
Mn3O4 0.04 0.03
Design and Construction of the Demonstration Ash
Embankment

In order for the embankment to perform satisfactorily, the ash fill


the construction of the demonstration embankment, determined must satisfy two criteria: 共1兲 it must have adequate strength to
by Method A: ASTM D 854 共2000a兲, was found to be equal to support safely its self weight and that of the traffic loads and 共2兲
2.54. it must be sufficiently stiff to prevent excessive settlement during
the service life of the pavement. Slope stability and settlement
analyses need to be performed to determine the best way to meet
Grain-Size Distribution these design requirements.
Grain-size analysis was performed on fly and bottom ash samples
collected from the construction site in accordance with ASTM Design of the Embankment
D422-63 共2002兲. As can be seen in Fig. 2, 60% of the ash mixture Embankments may become unstable due to excess pore pressure
by weight passed the No. 200 sieve 共0.075 mm兲. The ash mixture development in the foundation soil. Because of the low hydraulic
used in the project, which exhibits nonplastic behavior, is classi- conductivity of a clay loam layer 共about 0.8 m in thickness兲 found
fied as sandy silt 共ML兲 according to the Unified Soil Classifica- at the embankment site location, generation of excessive pore
tion System 共USCS兲. pressure in this layer was a concern. The clay loam classified as
an A-7-6 according to the American Association of State Highway
Compaction Characteristics and Transportation Officials classification system. The pore pres-
sure developed in the foundation soil due to the applied embank-
Standard compaction tests were performed on the fly and bottom ment load must not exceed critical pore pressure values that could
ash mixture in accordance with ASTM D698 共2000c兲. As shown lead to instability. The critical pore pressures were calculated in
in Fig. 3, the maximum dry unit weight ␥d,max is 15.0 kN/ m3, and the center of the clay loam layer during various stages of the
the optimum moisture content wopt is 19%. The zero-air-voids line embankment construction by assuming that the change in pore
for the ash mixture is also shown in Fig. 3. pressure was equal to the stress increment due to the applied
embankment load. When the pore pressure generated in the foun-
dation soil approached these critical values, the embankment con-
struction was stopped until the excess pore pressure dissipated.
The overall stability of the ash embankment was performed using
slope stability analysis software 共STABL兲. A safety factor of 1.3
was used in design of embankment.

Test Pad Construction


Before the construction of the demonstration embankment was
started, a test pad was constructed to establish the specifications
for compaction quality control in the field. The approximate
height, length and width of the test pad were 0.6, 50, and 25 m,
respectively. Nuclear gauge and microwave-oven tests were per-
formed to determine the in situ density and water content of the
compacted ash according to ASTM D2922 共2004兲 and ASTM D
4643 共2000b兲, respectively. Based on the test pad results, the dy-
namic cone penetration test 共DCPT兲 was also selected to be used
Fig. 2. Grain-size distribution of the fly and bottom ash mixture used to ensure the compaction quality control at every stage of the
in the construction of the demonstration embankment embankment construction. DCPT results are discussed next.

JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009 / 273

J. Mater. Civ. Eng., 2009, 21(6): 271-278


Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Schematic cross section of the test embankment at Station


6 + 250

mation of the ash mixture 共there were only minor imprints of the
wheels left behind on the surface of the mixture兲. Fig. 6 shows the
placement and compaction of the fly and bottom ash mixture used
for the embankment construction.

Quality Control
Quality control 共QC兲 of the compacted ash was done for every lift
共150 mm兲 at 15-m intervals along the embankment length. QC
Fig. 4. Location of the settlement plates and piezometers was done in two ways: 共1兲 using the nuclear gauge and
microwave-oven heating tests to determine the in situ density and
in situ water content of the compacted ash mixture; and 共2兲 using
Dynamic Cone Penetration Test the DCPT.
Fig. 7 illustrates the relationship between the DCPT blow
The DCPT consists of upper and lower shafts. The upper shaft, count per 150-mm penetration and the in situ dry unit weight of
which has a 0.078-kN hammer with a 575-mm-drop height, is
attached to the lower shaft through the anvil. The lower shaft
consists of an anvil and a cone attached at its end. The cone has a
60°-apex angle. DCPTs were performed in accordance with
ASTM D 6951 共2003兲 at the same locations in the test pad as the
nuclear gauge and microwave oven tests. The DCPT results on
the compacted ash indicated consistently that 5–7 blow counts
were required for the dynamic cone to penetrate a thickness of
one lift 共150 mm兲. Based on these results, a DCPT blow count of
more than 6 per 150-mm penetration into the compacted ash was
expected to indicate 95% relative compaction or better.

Construction of the Demonstration Embankment


The height, length, and width of the test embankment are equal to
7.6, 60, and 100 m, respectively. Fig. 4 shows a plan view of the
demonstration embankment with the location of the settlement
plates, piezometers, and horizontal and vertical inclinometers.
Stations 6 + 220 and 6 + 280 bound the length of the ash embank-
ment. Fig. 5 shows the cross section of the embankment at Loca-
tion 6 + 250.

Embankment Compaction
Based on the evaluation of the test pad results, a 150-mm-lift
thickness and three vibratory roller passes per lift using a D-10
vibratory roller manufactured by Caterpillar Inc. 共CAT CS-563D
with 266 kN centrifugal force兲 were recommended in order to
achieve 95% relative compaction. Each layer of ash was uni-
formly placed across the length of the roadway cross section. A
steel track bulldozer 共CAT D7 50兲 was then used to spread out the Fig. 6. Construction of the embankment: 共a兲 placement of fly and
fill material and to provide additional compaction. Passage of the bottom ash-mixture; 共b兲 compaction of fly and bottom ash mixture
heavy construction equipment did not cause any significant defor- layer

274 / JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009

J. Mater. Civ. Eng., 2009, 21(6): 271-278


top of the embankment兲. As shown in Fig. 5, eight settlement
plates were installed at the bottom and midheight of the embank-
ment at four different locations 共7.8 and 17.7 m from the center-
line along the southeast and northwest sides of the embankment兲.
The remaining two plates were placed on the top of the ash em-
bankment. Settlement plates were monitored for a period of
1 year from the start of the embankment construction using sur-
veying techniques. The ash fill settled during its construction be-
cause of the load due to the embankment self-weight and the
traffic of construction equipment on top of it. The settlement data
obtained from the settlement plates placed at the bottom and mid-
height of the embankment at various locations along the 6 + 250
Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

section are shown in Fig. 8. The settlement data obtained from the
bottom plates at locations 7.8 and 17.7 m on the southeast side of
the embankment are not shown for the entire 1 year period be-
cause these settlement plates were damaged during construction.
Fig. 7. DCPT blow count versus field dry unit weight of the ash
The maximum settlement, which was more or less the same
mixture
for the two bottom plates, was equal to about 80 mm, and it
stabilized about 8 months after the start of construction. The
the compacted ash. The blow count increases as the dry density settlement at the midheight of the embankment stabilized to a
increases. An empirical correlation for the DCPT blow count maximum value of about 70 mm about 7 months after the instal-
共BC兲, derived in terms of the in situ dry unit weight 共for water lation of the plates. A total settlement of 20 mm was recorded at
contents ranging from 20.4 to 23.8%兲, is as follows: the top of the ash embankment approximately 4 months after the
installation of the settlement plates.
BC = 3␥d − 40.5 共1兲
where BC= blow count per 150-mm penetration and ␥d = dry unit Piezometers
weight 共kN/ m3兲 as obtained from the nuclear gauge tests. Due to
scatter of the data points observed in Fig. 7, caution should be Piezometric elevations were monitored during the construction of
exercised when using the above-mentioned correlation in prac- the embankment to meet the design requirements for staged con-
tice. Note that Eq. 共1兲 relates the DCPT blow count to a single struction. Two piezometers were installed along Section 6 + 250
soil property. Other parameters 共such as the soil water content and within the foundation soil. They are located 9 m from the center-
stiffness兲 affect the DCPT blow count as well. As these param- line of the embankment on both its sides. The piezometric data
eters were not accounted for in the previous correlation, it can collected during construction of the embankment are shown in
only be considered as a general reference for quality control of Table 3. The piezometric levels were maintained below the criti-
compacted densities of ash mixtures. One should also consider cal pore water pressure values at all times.
specific site conditions and characteristics of the materials com-
pacted in the field when establishing quality control procedures. Horizontal Inclinometers
The horizontal inclinometer monitoring system consists of an in-
Environmental Considerations clinometer casing 共outer diameter= 70 mm兲, a portable horizontal
Leaching of trace metals from fly and bottom ash is the main inclinometer probe and control cable, and an inclinometer readout
environmental concern when these materials are used in embank- unit. The horizontal inclinometer was installed on top of the ash
ment construction. Migration of metals from ash into groundwater embankment along Section 6 + 260 in order to monitor differential
has been studied in a number of high-volume ash projects 共Srivas- settlement 共see Fig. 4兲. Monitoring started about three months
tava and Collins 1989; Rehage and Schrab 1995; Alleman et al. after the installation of the horizontal inclinometer due to inac-
1996兲. According to these studies, groundwater contamination cessible site conditions. The horizontal inclinometer data are
due to coal ash usage was minimal. Longer term studies are nec- shown in Fig. 9. A maximum differential settlement of 5 mm was
essary for more definite conclusions on the environmental impact observed in the middle of the embankment after approximately
of ash embankment construction. 5 months of monitoring of the horizontal inclinometer. These re-
sults show that the differential settlements in the embankment
were minimal.
Field Instrumentation Program
Vertical Inclinometers
The performance of the embankment was monitored using settle-
ment plates, piezometers, and horizontal and vertical inclinom- As shown in Fig. 5, two vertical inclinometer casings were in-
eters installed during construction. The results are presented in the stalled: one on the shoulder and one on the toe of the embank-
following sections. ment. The vertical inclinometer on the shoulder can detect lateral
movement of the slope, and the one on the toe, the movement of
the original ground. The vertical inclinometers were installed
Settlement Plates
after completion of the embankment construction. The lateral
A total of ten settlement plates were installed along the midsec- movement of the test embankment was monitored after the end of
tion of the embankment 共Section 6 + 250兲. These settlement plates embankment construction. Fig. 10 shows the lateral movement
were installed at three different depths 共bottom, midheight, and recorded at the shoulder and toe of embankment. A maximum

JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009 / 275

J. Mater. Civ. Eng., 2009, 21(6): 271-278


Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 8. Settlement versus number of days after start of construction: 共a兲 7.8 m northwest side; 共b兲 17.7 m northwest side; 共c兲 7.8 m southeast side;
and 共d兲 17.7 m southeast side

lateral movement of about 3 mm was observed at the shoulder of sandy silt 共ML兲 according to the USCS. The height, length
the embankment after about 4 months of monitoring. A lateral and width of the test embankment are equal to 7.6, 60, and
movement of less than 1 mm was observed at the toe of the em- 100 m, respectively.
bankment after about 4 months of monitoring, indicating that 2. The maximum dry unit weight and the optimum moisture
there was basically no movement in the foundation soil. The em- content of the ash mixture were found to be equal to
bankment is stable considering the minimal lateral movements 15.0 kN/ m3 and 19%, respectively. The ash mixture is
recorded. lighter than typical fill materials used in highway construc-
tion.
3. Compaction procedures for the demonstration embankment
Summary and Conclusions were determined based on test pad results. Based on the test
pad results, it was concluded that a DCPT blow count of
The following summarizes the work done and the results of the more than 6 per 150-mm penetration into the compacted ash
laboratory testing and field instrumentation program: would guarantee that 95% of the laboratory ␥d,max would be
1. A high-volume ash-mixture demonstration embankment was achieved in the field. Nuclear gauge, microwave oven, and
constructed at State Rd. 641, in Terre Haute, Ind. The fill DCPT tests were used for compaction quality control.
material consists of a mixture of Class F-fly ash and bottom 4. A preliminary empirical correlation between the DCPT blow
ash 共60:40 by weight兲. The ash mixture was classified as count and ␥d,max was proposed based on the data available.

Table 3. Piezometer Data Collected during Construction of the Embankment


Northwest 共Station 6 + 250兲 Southeast 共Station 6 + 250兲

Days from Fill Critical Fill Critical


start of height Piezometric piezometric height Piezometeric piezometric
construction 共m兲 head 共m兲 head 共m兲 共m兲 head 共m兲 head 共m兲
12 0.26 166.84 167.56 0.165 166.57 166.72
30 1.70 167.09 169.83 1.567 166.51 168.93
50 2.52 167.16 171.12 2.452 166.55 170.33
69 4.66 167.40 174.49 4.542 166.64 173.62

276 / JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009

J. Mater. Civ. Eng., 2009, 21(6): 271-278


9. The laboratory and field test results show that the fly and
bottom ash mixture used in the construction of the demon-
stration embankment is a viable alternative to conventional
fill materials.

Acknowledgments

This work was supported by the Joint Transportation Research


Program administered by the Indiana Department of Transporta-
Fig. 9. Horizontal inclinometer measurements tion and Purdue University, Cinergy Co., Vectren Co., and the
Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

Indiana Department of Commerce. The contents of this paper


reflect the views of the writers, who are responsible for the facts
and the accuracy of the data presented herein. The contents nei-
5. Monitoring of the demonstration embankment was done for a
ther necessarily reflect the official views or policies of the Federal
period of 1 year from the start of construction of the em-
Highway Administration and the Indiana Department of Transpor-
bankment. The instrumentation program included settlement
tation, nor do the contents constitute a standard, specification, or
plates, and vertical and horizontal inclinometers.
regulation. The writers are thankful to Howard Lewis for his sup-
6. A maximum settlement of 80 mm was observed at the bot-
port during this project. The writers appreciate the help of John
tom of the embankment; the settlement stabilized approxi-
Carpenter and Nelson Brown of INDOT with the field monitoring
mately 5 months after the end of construction of the
work.
embankment.
7. A differential settlement of about 5 mm was observed at the
top of the ash embankment according to the horizontal incli-
nometer readings obtained after approximately 5 months of References
monitoring.
8. Vertical inclinometer monitoring was performed for Alleman, E. J., Fox, P. J., and Battista, D. D. 共1996兲. “Performance evalu-
ation of highway embankment constructed using coal ash.” Joint
4 months after the end of construction of the embankment.
Highway Research Project, Final Rep. No. FHWA/IN/JHRP-96/5,
Negligible lateral movements were observed at the shoulder School of Civil Engineering, Purdue Univ., W. Lafayette, Ind.
and toe of the embankment. American Coal Ash Association 共ACAA兲. 共2005兲. “CCP survey.” 具http://
www.acaa-usa.org/典 共Dec. 11, 2008兲.
American Society for Testing and Materials 共ASTM兲. 共2000a兲. “Standard
test methods for specific gravity of soil solids by water pycnometer.”
Designation D854-00, Philadelphia.
American Society for Testing and Materials 共ASTM兲. 共2000b兲. “Standard
test method for determination of water 共moisture兲 content of soil by
the microwave oven heating.” Designation D4643-00, Philadelphia.
American Society for Testing and Materials 共ASTM兲. 共2000c兲. “Standard
test methods for laboratory compaction characteristics of soil using
standard effort 共12,400 ft-lbf/ ft3共600 kN-m / m3兲兲.” Designation
D698-00a, Philadelphia.
American Society for Testing and Materials 共ASTM兲. 共2002兲. “Standard
test methods for particle size analysis of soils.” Designation D422-63,
Philadelphia.
American Society for Testing and Materials 共ASTM兲. 共2003兲. “Standard
test method for use of the dynamic cone penetrometer in shallow
pavement applications.” Designation D6951-03, Philadelphia.
American Society for Testing and Materials 共ASTM兲. 共2004兲. “Standard
test methods for density of soil and soil-aggregate in place by nuclear
methods 共shallow depth兲.” Designation D2922-04, Philadelphia.
Anderson, D. A., Usme, M., and Moulton, L. K. 共1976兲. “Use of power
plant aggregate in bituminous construction.” Transportation Research
Record. 595, Transportation Research Board, National Research
Council, Washington, D.C., 18–24.
Diamond, S. 共1985兲. “Selection and use of fly ash for highway concrete.”
Joint Highway Research Project, Final Rep. No. FHWA/IN/JHRP-
85/8, Purdue Univ., W. Lafayette, Ind.
Diamond, S., and Olek, J. 共1988兲. “Fly ash concrete for highway use.”
Joint Highway Research Project, Final Rep. No. FHWA/IN/JHRP-
88/8, Purdue Univ., W. Lafayette, Ind.
GAI Consultants, Inc./USIFCAU. 共1993兲. “Use of coal combustion by-
products in highway construction.” Prepared for General Assembly of
Indiana and the Indiana Department of Transportation in response to
Fig. 10. Vertical inclinometer measurements monitored after the end
House Enrolled Act 1056 and Senate Bill 209.
of embankment construction: 共a兲 at the shoulder of the embankment;
Huang, H. W. 共1990兲. “The use of bottom ash in highway embankments,
共b兲 at the toe of the embankment subgrade and subbases.” Joint Highway Research Project, Final Rep.

JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009 / 277

J. Mater. Civ. Eng., 2009, 21(6): 271-278


No. FHWA/IN/JHRP-90/4, Purdue Univ., W. Lafayette, Ind. Moulton, L. K. 共1973兲. “Bottom ash and boiler slag.” Proc., 3rd Int. Ash
Karim, A. M. K. 共1997兲. “Building highway embankments of fly/bottom Utilization Symp., Bureau of Mines, Pittsburgh, Pa., Information Cir-
ash mixtures.” Joint Highway Research Project, Final Rep. No. cular 8640, 148–169.
FHWA/IN/JTRP-97/1, Purdue Univ., W. Lafayette, Ind. Moulton, L. K., Seals, R. K., and Anderson, D. A. 共1973兲. “Utilization of
Ke, T. C. 共1990兲. “The physical durability and electrical resistivity of ash from coal-burning power plants in highway construction.” Highw.
Indiana bottom ash.” Joint Highway Research Project, Final Rep. No. Res. Rec., 430, 26–39.
Patelunas, G. M. 共1986兲. “High volume fly ash utilization projects in the
FHWA/IN/JTRP-90/6, Purdue Univ., W. Lafayette, Ind.
United States and Canada.” Rep. No. CS-4446, Electric Power Re-
Kim, B. 共2003兲. “Properties of coal ash mixtures and their use in highway
search Institute, Palo Alto, Calif.
embankments.” Ph.D. dissertation, School of Civil Engineering, Pur- Rehage, J. A., and Schrab, G. E. 共1995兲. “Environmental performance
due Univ., W. Lafayette, Ind. assessment of coal combustion byproduct use sites: Road construction
Kim, B., Prezzi, M., and Salgado, R. 共2005兲. “Geotechnical properties of applications.” TR-105127, Research Project No. 2796-01, Final Rep.,
fly and bottom ash mixtures for use in highway embankments.” J. Electric Power Research Institute, Palo Alto, Calif.
Downloaded from ascelibrary.org by California State University- Fresno on 09/25/17. Copyright ASCE. For personal use only; all rights reserved.

Geotech. Geoenviron. Eng., 131共7兲, 914–924. Seals, R. K., Moulton, L. K., and Ruth, B. E. 共1972兲. “Bottom ash: an
Majidzadeh, K., El-Mitiny, R. N., and Bokowski, G. 共1977兲. “Power engineering material.” J. Soil Mech. and Found. Div., 98共4兲, 311–325.
plant bottom ash in black base and bituminous surfacing.” Vol. 2, Srivastava, L., and Collins, R. J. 共1989兲. “Ash utilization in highways:
User’s manual, publication No. FHWA-RD-78-148, FHWA, U.S. De- Delaware demonstration project.” GS-6481, Research Project No.
partment of Transportation, Washington, D.C. 2422-3, Interim Rep., Electric Power Research Institute, Palo Alto,
Calif.
McLaren, R. J., and DiGioia, A. M. 共1987兲. “The typical engineering
Usmen, M. A., Head, W. J., and Moulton, L. K. 共1983兲. “Use of coal-
properties of fly ash.” Proc., Geotechnical Practice for Waste Dis- associated wastes in low-volume roads.” Transportation Research
posal ’87, Geotechnical Special Publication No. 13, E. Wood, ed., Record. 898, Transportation Research Board, National Research
ASCE, New York, 683–697. Council, Washington, D.C., 268–277.

278 / JOURNAL OF MATERIALS IN CIVIL ENGINEERING © ASCE / JUNE 2009

J. Mater. Civ. Eng., 2009, 21(6): 271-278

You might also like