April 24

Based on our observations on that day, the workers are too busy. They have different tasks. Others
workers are trying to figure out what to do. They are arranging and preparing the formwork (is the use
of support structures and moulds to create structures out of concrete which is poured into the moulds.
Formwork can be made using moulds out of steel, wood, aluminium and/or prefabricated forms.
Formwork is an ancillary construction, used as a mould for a structure.) they will use for concrete
pouring, for the slab on the second floor. They also operate the formwork for they will be used in
concrete the stirrup (A stirrup is a closed loop of reinforcement bar that is used to hold the main
reinforcement bars together in an RCC structure. In a column, the stirrups provide the lateral support to
the main bars against buckling).