Professional Documents
Culture Documents
AC UPS Sizing
From Open Electrical
Contents
1 Intr
Introd
oducucti
tion
on
1.1 Why do the the calcul
calculatiation?
on?
1.2 When
When to do thethe calcul
calculati
ation?
on?
2 Calcul
Calculati
ation
on Meth
Methodol
odology
ogy
2.1 Step
Step 1: Collec
Collectt the ACAC UPS Loads
Loads
2.2 Step 2: Load
Load Profile,
Profile, Design
Design Load and Design
Design Energy
Energy
2.3 Step
Step 3: Batter
Batteryy Sizin
Sizing g
2.3.1 Nominal
Nominal Battery
Battery (or DC Link)
Link) Voltage
Voltage
2.3.
.3.2
2 Number
Number of of Cells
Cells in Seri
Series
es
2.
2.4
4 Step
Step 4: UPS Sizing
2.
2.4.
4.1
1 Over
Overalalll UPS
UPS Sizing
2.4.
2.4.2
2 Rect
Rectif
ifie
ierr / Charger Sizing
2.
2.4.
4.3
3 Inve
Invert
rteer Sizing
2.4.4
2.4.4 Static
Static Switch
Switch Sizing
Sizing
3 Worked Example
Example
3.1 Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile
3.2 Step 3: Battery Sizing
3.3 Step 4: UPS Sizing
3.
3.3.
3.1
1 Over
Overalalll Sizing
3.3.2
3.3.2 Rectif
Rectifier
ier Sizing
Sizing
3.3.
3.3.3
3 Inver
Inverte
terr and Static Switch Sizing
4 Com puter Software
5 What next?
Introduction
This calculation deals with the sizing of an AC uninterruptible power supply (UPS) system (i.e. rectifier, battery
bank and inverter). In this calculation, it is assumed that the AC UPS is a double conversion type with a basic
system topology as shown in Figure 1.
An external maintenance bypass switch and galvanic isolation transformers are other common additions to the
basic topology, but these
these have been omitted from the system as they are irrelevant for the sizing calculation.
An AC UPS system is used to support critical / sensitive AC loads. It is typically a battery-backed system which
will continue to operate for a specified amount of time (called the autonomy) after a main power supply
interruption. AC UPS systems are also used as stable power supplies that provide a reasonably constant voltage
and frequency output, independent
indepe ndent of voltage input. This is particularly useful for sensitive electrical equipment on
main power supplies that are prone to voltage / frequency fluctuations or instability.
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 1/6
Calculation Methodology
For commercial facilities, UPS loads will mainly be server, data / network and telecommunications hardware.
Refer to the
the Load
Load Profile
Profile Calculation
Calculation for details
details on how to
to construct
construct a load profile,
profile, calcula
calculate
te the
the design
design load
load (
)
and desig
designn energy
energy ( ). The
The "Autonom
"Autonomy
y method
method"" for cons
constru
tructi
cting
ng load
load profil
profiles
es is typi
typical
cally
ly used
used for
for AC UPS
UPS
systems.
The autonomy time is often specified by the Client (i.e. in their standards). Alternatively, IEEE 446, "IEEE
Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications"
has some guidance (particularly Table 3-2) for autonomy times. Sometimes a single autonomy time is used for the
entire AC UPS load, which obviously makes the construction of the load profile easier to compute.
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 2/6
The nominal battery / DC link voltage is often selected by the AC UPS manufacturer. However
However,, if required to be
selected, the following factors need to be considered:
In general, the DC link voltage is usually selected to be close to the nominal output voltage.
The number of battery cells required to be connected in series must be between the two following limits:
( 1 + )
,
(1)
=
( 1 − )
(2)
,
=
where
is the maximum number of battery cells
is the minimum number of battery cells
ce lls
is the nominal battery / DC link voltage (Vdc)
,
is the inverter minimum input voltage tolerance (%)
is the nominal cell float (or boost) voltage (Vdc)
is the cell end of discharge voltage (Vdc)
The limits are based on the input voltage tolerance of the inverter. As a maximum, the battery at float voltage (or
boost if applicable) needs to be within the maximum input voltage range of the inverter.
inverter. Likewise as a minimum,
the battery at its end of discharge voltage must be within the minimum input voltage range of the inverter.
Select the number of cells in between these two limits (more or less arbitrary, though somewhere in the middle of
the min/max values would be appropriate).
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 3/6
Most of the time, all you need to provide is the overall UPS kVA rating and the UPS vendor will do the rest. Given
the design
design load
load ( in VA
VA or kV
kVA) calculate
calculated
d in Step
Step 2, select
select an overall
overall UPS
UPS rating
rating that
that exceeds
exceeds the
the design
design load.
load.
Vendors typically have standard UPS ratings, so it is possible to simply select the first standard rating that exceeds
the design load. For example, if the design load 12kVA,
12kVA, then the next size unit (e.g. 15kVA
15kVA UPS) would be
selected.
The rectifier / charger should be sized to supply the inverter at full load and aalso
lso charge the batteries (at the
maximum charge current). The design DC load current can be calculated by:
=
,
where
,
is the design DC load current (full load) (A)
is the selected UPS rating (kVA)
is the nominal battery / DC link voltage (Vdc)
=
where
is the maximum DC charge current (A)
is the selected battery capacity (Ah)
is the battery recharge efficiency / loss factor (typically 1.1) (pu)
is the minimum battery recharge time (hours)
= +
,
Inverter Sizing
=
–
√ 3
=
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 4/6
where
is the design AC load current (full load) (A)
is the selected UPS rating (kVA)
is the nominal output voltage (line-to-line voltage for a three phase UPS) (V
(Vac)
ac)
Select the next standard inverter rating that exceeds the design AC load current.
Like the inverter, the static switch must be rated to continuously supply the UPS loads. Therefore, the static switch
can be sized using the design AC load current (as above for the inverter sizing).
Worked Example
Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile
VAh
Overall Sizing
Rectifier Sizing
Given a nominal dc link voltage of 120Vdc, the design DC load current is:
=
,
1 , 0 0 0
= = 8 . 3 3
A
1 2 0
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 5/6
Suppose the minimum battery recharge time is 2 hours and a recharge efficiency factor of 1.1 is used. The
maximum battery charging current is:
=
5 0 × 1 . 1
= = 2 7 . 5 A
2
= +
,
= 8 . 3 3 + 2 7 . 5 = 3 5 . 8 3 A
=
–
√ 3
1 , 0 0 0
–
= 2 . 4 0 6 A
√ 3 × 2 4 0
Computer Software
Preliminary sizing is normally done manually. Notwithstanding this, many AC UPS manufacturers provide sizing
tools as part of their service package (for example, see the APC online UPS selector tool (http://www
(http://www.apc.com/tool
.apc.com/tool
s/ups_selector/index.cfm?)).
What next?
Using the results of the UPS sizing calculation, the approximate dimensions of the batteries and UPS cabinet
c abinet can
be estimated based on typical vendor information. This will assist in developing the equipment / room layouts.
Preliminary budget pricing can also be estimated based on the calculation results.
Category: Calculations
https://wiki.openelectrical.org/index.php?title=AC_UPS_Sizing 6/6