Professional Documents
Culture Documents
Project Management-B.Sc-class note-SEC PDF
Project Management-B.Sc-class note-SEC PDF
• Controlling
• Directing
• Organizing
• Planning
• Staffing
Basic Management Principle
• “Strategic planning must complement
strategic thinking and acting
• Strategic Planning –SWOT Analysis
• Strengths
• •Weaknesses
• •Opportunities
• •Threats
Management Information System of
an organization
• Transaction Processing System
• Knowledge and Work Distribution System
• Management Information System
• Decision Distribution System—It help manager
make rapid decision, changeable decision and
not specified in advance
• Executive Level Decision
• Relationship Establishment among sections
Elements of Project management
process
Q: Why project fail?
Benefit/cost ration:
B/C > 1 ok
Choosing a suitable discount rate
The discount rate reflects the opportunity
cost for the organization that will receive the
cash flows.
The analysis can be done with real or nominal
discount rates---
Real rate: dollar conversion rate
Nominal rate: market rate or inflation rate
The discount rate is not same as the interest rate obtained from bank.
Higher risks will require a higher discount rate
Example:
2
(1 2)
)
(1 0
(8
)
1 (1 0) (1 2)
(8) 5 7 8
4
)
(6)
(1 2
)
(6
(6)
3 (5) 6
Conversion from arrow to circle network
0 6 24 10
1-2 2-7
(10 ) (12)
16 10
36 36
2-5
(8)
7-8
12 12 5-7 (12) End
Start (10)
3-4 18 18 48 48
(6) 26 26
4-5
(8) Critical Path
5-6 6-7
1-3 (6)
(6)
(12)
24 18 30 24
0 0
3-6
(5)
25 12
Activity Duration EST EFT LST LFT TF FF
(LST-EST) (LFT-EFT)
1-2 10 0 10 6 166 0 6
1-3 12 0 12 0 12 0 0
3-4 6 12 18 12 18 0 0
2-5 8 10 18 16 24 6 6
4-5 8 18 26 18 26 0 0
5-6 6 18 24 24 30 6 6
3-6 5 12 17 25 30 13 13
6-7 6 24 30 30 36 6 6
5-7 10 26 36 26 36 0 0
2-7 12 10 22 24 36 26 14
7-8 12 36 36 36 48 12 0
PERT
• PERT may be defined by -----
(i) A manager’s tool --- for defining a project and coordinating
various operation among it.
(ii) A direction --- what must be done to successful acoomplish
the objectives of the project
(iii) A profile --- that aids the decision –makers
(iv) A way --- for synchronizing various parts of a project
(v) A technique --- it presents statistical information regarding
uncertainties.
(vi) A method
(vii) A communication facilities
A PROJECT PLANNING TECHNIQUE
PERT CHART
CRITICAL PATH :- (A+B+C+D+DUMMY+H) = 19 DAYS
PATH 1 IS CRITICAL PATH
14
5
14
D
EVENT ID NO. 0
2
TASK ID
ECT
0 A 3 7 13 19
14
B 5 c E H
0 2 3 4 6 8 9
2 2 6 14 5
0 3 3 5 7 14 19
LCT
Expected Time
Dummy TASk
3
10
7
14
(3 + 2 + 2 + 7 + 0 + 5 ) = 19 Person - day2
Schedule Development
From the network diagram, the critical path is identified as 1-4, 4-6, 6-7, with a
project duration of 22 days.
• The probability of completing the project
within 19 days is given by, P (Z< Z0)
To find Z0 ,
we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) =
0.4099)
= 0.5 – 0.4099
= 0.0901
= 9.01%
TIME VARIANCE
BCWS
ACWPt
RESOURCE FLOW VARIANCE
BCWSt COST VARIANCE
SCHEDULE VARIANCE
BCWPt
ACWP
BCWP
Comments: If the twice value is above 1 then the project will satisfactory and
continue ; if the twice value is below 0.8 the project will not satisfactory .our result is
above 0.8 so this project is not satisfactory but still continue.
Resources for Project Control
• Money
• Machinery (Equipment)
• Materials and Supplies
• Manpower (Labor and Supervision)
Elements of Project Control
Resources-related Project-related
3A. Resource-related
• Manpower-related control
• Machinery-related control
• Money-related control
• Material-related control
3A. Resource-related
Options:
- Terminate project?
Planning
• The central research question that this paper
addresses is whether or not cyclone shelters
in Bangladesh are distributed as per the actual
needs
Steps in risk Analysis: