Case Study

Toranomon Hills Mori Tower,


Tokyo (JP)

Vibration suppression for once-in-


a-century construction project in
Japan

Decoupling at the source of the


interference: Providing bedding
for a four-lane underground urban
motorway

Vibration-related internal construction


measures for a 247-m high-rise
complex with tunnelling below
Decoupling of a Four-Lane Urban
Motorway and a 247-m Tall Tower
Standing above it

Project description The Getzner solution


In the centre of Tokyo, on a site Full-surface bedding of a four-lane borne noise from spreading through
covering a total area of about 6,000 urban motorway the building. The building is thus
m2, a prestigious multi-function area effectively protected against
he irst implementation phase unwanted vibrations.
was built; the centrepiece of this
development is the Toranomon Hills
Mori Tower, a high-rise around 247
T of the project involved applying
a resilient bedding to the 200 m
m in height with 52 loors, which is underground length of motorway.
set to become the tallest building in The full width of this section was
Tokyo. bedded on the high-tech Sylomer®.
This has the effect of providing the
irectly beneath this structure structure erected above the road
D the planners designed a four-
lane underground urban motorway –
with effective and long-term
protection against vibration. The
a new main trafic artery for getting solution directly addresses the
across Tokyo. To enable this impres- cause of the vibration, as the four-
sive skyscraper to be built to the lane urban motorway, which is the
required usage standards, a solution source of the disturbing structure-
had to be found for the vibration borne noise, has now been isolated.
produced by the urban motorway, The elastic bedding decouples the
which runs through a tunnel for some source of disturbance from its
200 m. The Tokyo Metropolitan surroundings, and thus also from
Government selected the Japanese the structure erected over it.
property company Mori Building as
its partner for this major public- Protecting outstanding
private sector project. Mori in turn architecture
engaged Getzner as its specialist
partner for vibration isolation. In the second implementation phase
of the project, a variety of internal
Getzner has developed vibration vibration-damping construction
protection for two signiicant measures for decoupling the hotel
subprojects: an elastic solution for that occupies the upper loors of the
the hotel on the uppermost loors tower are being carried out. In order The project goal, which was to
of the high-rise complex and a to protect this sensitive area in the provide the maximum quality
solution for the urban motorway best possible way against vibrations, of life and work by reducing
running directly underneath the Getzner is bedding the hotel loors, vibration and noise, has been
building. the pool areas and the itness and achieved.
machinery rooms of the hotel on
Sylomer®. This prevents structure-
Feedback
Vibration experts on site The advantages of the What do our clients have to say
Getzner solution about the project?
Getzner also assumed responsibility
for overseeing the installation pro- — Sylomer® performs extremely well nstalling Sylomer® mats has the
cess. „On a project of this magnitude
it is not only very important to work
in the long term
— Expert, well-informed contacts
I effect of reducing noise and
vibration. The material has been
closely with our Japanese partners, on site employed successfully for decades –
one really needs to be on site oneself, — Material is easy to handle and Getzner has demonstrated this on
as only then can we constantly to install numerous occasions in the rail
monitor the quality of the work and — Getzner‘s experience spans sector. Another important criterion
ensure that our materials protect this decades and has been gained for future-oriented urban planning
superb architecture in the long term. across all sectors is that the material should be easy
For Getzner, this order is a valuable — Overseeing construction and quick to install.
reference for future projects all over — Comprehensive documentation
the world“, is how Werner Ebster, — Excellent price/performance ratio Toru Tsuchihashi,
project manager at Getzner, Deputy General Manager,
underlines the importance of this Mori Building
major project.
Facts and igures at a glance
Project Toranomon Hills Mori Tower in Tokyo (JP)

Key facts: Tallest building in Tokyo (247 m, 52 loors)


Location: Loop Road No. 2 (trunk road from Shimbashi to Toranomon)
Project coordination
in Japan: Nihon Getzner K.K. und Getzner Werkstoffe Bürs
Owner: Mori Building
Carriageway solution: Full-width elastic bedding of a four-lane carriageway
Hotel solution: Hotel loors, pool complexes plus itness suites and machinery rooms
underlaid with Sylomer® bedding
Elastic bedding: Getzner Werkstoffe GmbH
Execution: 2014

Getzner Werkstoffe GmbH Construction references (extract from Japan)

CS Loop Road K2 en © Copyright by Getzner Werkstoffe GmbH | 09-2016


Foundation: 1969 (as a subsidiary of Getzner, — National Training Center, Tokio (JP)
Mutter & Cie) — Palace Hotel, Tokio (JP)
Chief Executive Oficer: Ing. Jürgen Rainalter — The Peninsula Hotel, Tokio (JP)
Employees: 340 — The St. Regis Hotel, Osaka (JP)
2015 turnover: EUR 77.9 million — Pacifico Yokohama,
Business areas: Railway, construction, industry Conference Center (JP)
Headquarter: Bürs (AT) — Tokyo American Club, Sports Center (JP)
Locations: Berlin (DE), Munich (DE), Stuttgart (DE), — Kabukiza, Tokio (JP)
Lyon (FR), Amman (JO), Tokyo (JP), — QVC Studio, Chiba (JP)
Pune (IN), Beijing (CN), Kunshan (CN), — Toppan Rotary Printing Press, Osaka (JP)
Charlotte (US)
Ratio of exports: 85 %

AUSTRIA — Bürs GERMANY — Berlin — Munich — Stuttgart FRANCE — Lyon JORDAN — Amman
JAPAN — Tokyo INDIA — Pune CHINA — Beijing USA — Charlotte www.getzner.com