You are on page 1of 4

A rticle

Your Contractual Questions Answered

What Are The Obligations Of The Contractor


During Defect Liability Period?
By The Entrusty Group

The Entrusty Group, a multi-disciplinary group of companies, of which, one of their specialisations is in
projects, commercial and contractual management, has been running a regular contractual question-and-
answer section fror MBAM members in Master Builders Journal.

In this instalment of the series, the Entrusty Group will provide the answer to the frequently asked question
above.

D
efect Liability Period (DLP) is ● IEM/JKR Clause 45 – Defects IEM/JKR sub-clause 45(b) is similar
a common feature in all the Liability and Making Good. to the above PAM sub-clause 15.2,
standard form of construction (Please see Flowchart 2) e xcept that it also requires the
contracts in Malaysia, i.e. PAM 98/JKR ● CIDB Clause 27 – Defects Liability Contractor to make good the defects
PWD 203/IEM/CIDB 2000. During the after Completion. no later than three months af ter
DLP, the Contractor is obliged and (Please see Flowchart 3) receipt of the defects Schedule.
liable to rectify defects that appear
between the period the Certificate of Under the PAM contract sub-clause IEM/JKR sub-clause 45(c) allows the
Practical Completion (CPC) is issued 15.3, it allows the Architect to issue Engineer/SO to make good such
and the expiry of the DLP. instructions requiring any defects, defects, shrinkages or other faults if
shrinkages or other faults appearing the Contractor fails to comply and to
Before answering this question, within DLP due to materials or deduct the costs incurred in making
lets def ine defec ts or defec tive workmanship not in accordance with good the defects from the monies
work s. In general terms defec ts the Contract. Such instruction for due or recover from the Performance
or defec tive work s is where the rectifying defects, shrinkages or other Bond or as liquidated demand in
standard and quality of workmanship faults can no longer be issued after 14 money. If the defects, shrinkages
and materials as specified in the days from expiry of the DLP or other faults are impracticable or
contract is deficient. Defects can be inconvenient to the Employer to
classified into two main categories, IEM/JKR sub-clause 45(a) and CIDB sub- have the Contractor make good these
Patent Defects and Latent Defects. clause 27.1 to 3 are similar to the PAM defects and faults, sub-clause 45(d)
Patent defects are defects that can sub-clause 15.3 described above. allows the Engineer to ascertain the
be discovered by normal examination diminution in value of the Works due
or testing whereas Latent Defects PAM sub - clause 15. 2 allows the to the said defective or faulty works
are defects that are not discoverable Architect to specify in a Schedule of and deduct such value in the same
by normal examination or testing Defects any defects, shrinkages or manner.
which manifests itself after a period other faults appearing within the DLP
of time. due to materials or workmanship not CIDB sub-clause 27.4 is similar to
in accordance with the Contract and IEM/JKR sub - clause 45(c) above,
Standard Form of Contracts deliver it to the Contractor within 14 except for the Performance Bond and
days after the said Period expires. Upon liquidated demand of money being
The DLP provisions are found under receipt, the Contractor needs to make excluded.
the following clauses of the standard good such defects, shrinkages or other
forms of construction contracts:- faults within a reasonable time, entirely PAM sub-clause 15.4 requires the
at his own costs, unless otherwise Architect to issue the Certificate of
● PAM 98 Clause 15 – Practical advised by the Architect, in which case Making Good Defects (CMGD) when
Completion & Defects Liability. the Contract Sum is to be adjusted, the defec ts, shrinkages or other
(Please see Flowchart 1) accordingly. faults have been made good.

100

1st Quarter 2007


A rticle

IEM/JKR sub-clause 45(e) and CIDB From the above, it is clear that during advantage of both parties. If the owner
sub-clause 27.6 are similar to PAM the DLP, the Employer via Architect/ have had seek contractors new to the site
sub-clause 15.4. CIDB further provides Engineer/SO is required to issue the to do the remedial work it might well have
that the said Certificate is to be copied necessary notices to the Contractor and had difficulty in finding them. It would
to the Employer and Nominated Sub- he shall be obliged within reasoanble also almost certainly have had to pay
Contractor(s)/Nominated Supplier(s) time to rectify the defects at his own them more and would then have sought
and it shall discharge the Contractor cost. to have recovered from the Contractor
from any physical attendance at the more than the cost to the Contractor of
Works for the purposes of remedying Case Law making good the defects.”
defects. It will not however prejudice
the Employer’s right on latent defects In P & M Kaye Ltd v Hosier & Dickinson As the contracts envisage that the
or other breaches of the Contract. Sub- Ltd (1972), Lord Diplock stated that “….. defects might occur during the DLP, and
clause 27.7 further emphasised that the the contractor is under an obligation to such defects shall not be considered as
provisions of sub-clause 27.1 to 27.6 do remedy the defects in accordance with the a breach of contract. Upon receipt of
not derogate or relieve the Contractor architect’s instructions. If he does not do such notice, the Contractor is obliged
from liability under the Contract or at so, the employer can recover as damages to return to the site to make good
law. the cost of remedying the defects, event and the Owner is obliged to allow the
though this cost is greater than the Contractor to do so. But the failing of
CIDB sub-clause 27.5 is unique as it diminution in value of the works as a the Contractor to rectify the defects
allows the SO to instruct the Contractor result of the unremedied defects.” upon receipt of such notice is clearly
to search for the causes of defects, and a breach of contract and the Employer
if the Contractor is liable for them, the In another case, H.W. Nevill (Sublest) has the right and remedy to recover
Contractor shall bear such search cost v William Press and Son (1981), Judge the cost in the form of damages per
and remedy the defects at his own cost. Newey QC said that “the clause 15(2) and Section 74(3) of Contracts Act 1950 as
If not, the said cost shall be deemed a (3) (the clause relating to DLP) provided an an alternative of recovering the cost of
variation. efficient way of dealing with defects to the the remedying the defective works by

START

Issuance of Certificate of
Practical Completion

Architect issues
Certificate of Practical
Completion

The Contract Sum shall be


The following events
adjusted accordingly unless
take place:
otherwise instructed by
(i) End of Contractor’s
the Architect
contractual liability During DLP, Architect may
except for making (iv) Defects Architect may issue Schedule
good defects; Liability instruct of Defects not
(ii) One moiety of Period Contractor to later than
Retention Fund begins make good 14 days after Contractor makes Employer may Cost shall be
released*; defects expiry of DLP good defects at employ other to recovered
(iii) End of insurance period; his own cost, make good from the
(iv) End of Contractor’s within reasonable defects Contractor
liability for further
Liquidated Damages;
(v) End of Contractor’s
possessions of site
Architect issues
except to make
Certificate of Making Good Defects
good defects.

Architect issues Refer CI 30


Final Certificate within 3 months from DLP/ Certificate and END
Completion of making defects Payment

Release of
second half of Retention Fun

END

Flowchart 1 – PAM 98 Clause 15 – Practical Completion & Defects Liability

101

1st Quarter 2007


A rticle

START

Issuance of Certificate of
Practical Completion
Yes

The following events take place:


(i) End of Contractor’s contractual liability
except for making good defects;
(ii) One moiety of Retention Fund released*;
(iii) End of insurance period;
(iv) End of Contractor’s liability for further
Liquidated Damages;
(v) End of Contractor’s possessions of site
except to make good defects.

Contractor makes good S.O./Engineer Employer may recover cost


No
(vi)) Defects defects at his own cost, ascertains the incurred from the amount
During DLP, S.O./Engineer diminution in the
Liability Period within 3 months due to the Conractor of
S.O./Engineer may issue value of defective
begins after the receipt of the from Performance Bond
may issue Schedule of Works if
written Schedule
Defects not impracticable and
instruction to later than 14 inconvenient for
Contractor to days after Contractor to
make good expiry of DLP rectify
defects Yes

S.O./Engineer issues Certificate of


Making Good Defects

S.O./Engineer issues Final Certificate within 3 Refer CI 48


months from DLP / 3 month after Certificate Final END
of Making Good Defects (whichever is later) Certificate

Release of
Performance Bond

END

Flowchart 2 – IEM/JKR Clause 45 – Defects Liability and Making Good

START

Issuance of Certificate of
Practical Completion
Yes

The following events take place:


(i) End of Contractor’s contractual liability
except for making good defects;
(ii) One moiety of Retention Fund released;
(iii) End of Insurance Period;
(iv) End of Contractor’s liability for further
Liquidated Damages;
(v) End of Contractor’s possessions of site
except to make good defects.
Contractor makes
Yes good at his own S.O. ascertains the
Not later than cost, within time diminution in the value of
If defects Searching
14 days after specified by S.O. No defective works
(vi)) Defects appear work and
the expiry of
Liability Period prior the No remedy shall
Contractor DLP, S.O.
begins expiry of be deemed
is liable for gives Employer may recover
DLP, S.O. as a Yes
such instruction to cost incurred from the
instructs Variation
defects remedy S.O. issues Certificate of amount due to the
Contractor Making Good Defects Contractor or from
to search
the cause
of Defects Within 90 days, S.O. issues
Refer CI 42.7 & END
Final Account and within the
42.8 Final Claim
following 30 days, he shall
Statement & Final
issue Final Certificate
Account and Final
Certificate
Release of 2nd Moiety of
Retention Monies
END

Certificate of Making Good Defects shall discharge the


Contractor from physical attendance but shall not
prejudice Employer’s rights to latent defects or breach
of contracts

END

Flowchart 3 – CIDB Clause 27 – Defects Liability after Completion

102

1st Quarter 2007


A rticle

another contractor within the ambit of However, it was also noted that the The defects listing and rectification
the contract provisions. failing of the Employer/Architect/ management generally cover the
Engineer/SO to issue the required following activities:-
It is noted that the DLP provision notice shall not preclude the Employer
requires such a notice to be given to to employ another contractor to rectify 1. P r e p a r a t i o n o f d e f e c t l i s t s
the Contractor but what would the the defects and recover the remedial identifying deficiencies against
scenario if the Employer/Architect/ cost. As Evan LJ further accepted that standards/requirements (i.e.
Engineer/SO fails to issue the required the Employer’s common law right to snagging list);
notice to the Contractor? Would the recover for damages is not excluded by 2. All remedial works are to be carried
Employer lose its rights and remedies failing to issue such a notice, however, out within the specified time
to recover the cost of remedying the it would limit the damages recoverable under the supervision of qualified
defects? by the principle of the Employer’s duty and experienced contractor’s
to mitigate loss. personnel;
In considering this issue, it is essential 3. Joint inspection, by the Architect/
to appreciate that the requirement of Conclusion Engineer/SO of the rectified works;
such notices impliedly imposes a duty 4. Further defects (if any) identified
to mitigate the loss on the part of the It has to be noted, whether or not by the Architect/Engineer/SO to
Employer. The decision had been held the required notice is given to the be listed on a schedule of defects,
in the Court of Appeal (UK) in the case Contractor, the Contractor is still liable to be rectified within an agreed
Pearce & High Limited v Baxter (1999), to the Employer to rectify the defects period for subsequent inspection,
where Evans LJ said that:- that appear during DLP. It is prudent leading to the issuance of the
for the Contractor to carries out the CPC.
“In my judgment, the contractor is defects rectification works within 5. Upon completion and inspection of
not liable for the full cost of repairs in a reasonable period. It is advisable the rectified works, to be signed off
those circumstances. The employer that the Contractor cater for defects by the Architect/Engineer/SO i.e. to
cannot recover more than the amount rectification management in order “close-out” all rectified works.
which it would have cost the contractor to manage the defects systematically 6. Any further defects occurring/
himself to remedy the defects. Thus, the to avoid potential disputes and/or identified within the DLP, to be
employer’s failure to comply with clause extra costs in fulfilling his contractual rectified periodically, unless those
2.5 (the clause relating to rectification obligation to rectify all the defects. requiring urgent repairs.
of defects), whether by refusing to allow
the contractor to carry out the repair
or by failing to give notice of defects, In the next issue of the MBAM journal the article will answer the question on Can
limits the amount of damages which a Contractor claim for compensation for extra work when there is no SO
he is entitled to recover. The result is instruction?
achieved as a matter of legal analysis
by permitting the contractor to set off
against the employer’s damages the The Entrusty Group includes Entrusty
amount by which he, the contractor, Consultancy Sdn Bhd (formerly known
has been disadvantaged by not being as J.D. Kingsfield (M) Sdn Bhd), BK Burns
able or permitted to carry out the repairs & Ong Sdn Bhd (a member of the Asia wide group BK Asia Pacific), Pro-Value
himself, or more simply, by reference Management, Proforce Management Services Sdn Bhd/Agensi Pekerjaan
to the employer’s duty to mitigate his Proforce Sdn Bhd and International Master Trainers Sdn Bhd. Apart from project,
loss.” commercial and contractual management services, the group also provides risk,
resources, quality and value management, recruitment consultancy services and
Evan LJ accepted that the giving of a corporate training programmes to various industries, particularly in construction
notice with regard to defects should and petrochemical, both locally and internationally.
be regarded as a condition precedent
to the Employer’s right to require Entrusty Group will provide 30 minutes of free consultancy with prior
compliance with the defects liability appointment to MBAM members on their contractual questions. The Group
clause. It was held that the Employer’s also provides both in-house and public seminars/workshops in its various areas
failure in giving the required notice of expertise. For further details, please visit website: www.entrusty.com or
would limit the Employer’s recovery if contact HT Ong or Wing Ho at 22-1& 2 Jalan 2/109E, Desa Business Park, Taman
the rectification cost were more than Desa, 58100 Kuala Lumpur, Malaysia. Tel: 6(03)-7982 2123 Fax: 6(03)-7982 3122
the cost to the original Contractor. Email: enquiry@entrusty.com.my

103

1st Quarter 2007

You might also like