Professional Documents
Culture Documents
Guideline
This guideline is prepared for the following reasons:
1. To assist contractor in application of Loss and Expenses
2. A comprehensive standard format for contractor to follow.
3. To direct contractor on the required evidence needed as a
precedent to assess the Loss and Expenses by the SO
9.0 Conclusion
Where the regular progress of the Works materially affected by any of the matters
expressly in contract, the Contractor has incurred or is likely to incur loss and/or
expense which could not be reimbursed by a payment made under any other
provision in the Contract, provided strictly following the process of claiming L&E in
the provision, the Contractor may make a claim for such loss and/or expense.
Under PAM Contract 2006, Contractor is to give a "written notice" to the Architect
informing him of the Contractor's "intention to claim such loss ad expenses". Such
written notice must contain 3 elements :-
1. an initial estimate of the loss and expenses he may require" duly supported
2. with all necessary calculation and
3. notice must reach the Architect within a stipulated time from the date of the
commencement of the Relevant Event, whichever is the earlier
Thus, the Contractor is to alert the Architect, within the stated time, any likely
additional claim to the completion of the Works.
1. Give the Architect the earliest possible opportunity to discuss with the
Employer on the additional claim
3. The giving of such written notice by the Contractor "a condition precedent" to
an entitlement of loss and expenses
4. If the Contractor fails to give such a notice to the Architect, in the specified
manner, he will not be entitled to any loss and expenses.
Timely Submission of Full Particulars
After having given the Architect the required written notice the Contractor shall send
to the Architect "his final claim for extension of time within stipulated time of the end
of the relevant event.
Such final claim must be "duly supported with initial claim" to enable the Architect to
assess any additional claim to the following procedures:
3. The need for limiting the submission of "final claim" to stipulated time of the
end of the cause of delay is to enable the Architect to assess the claim,
before the facts surrounding the claim become blurred by the passage of
time.
4. "If the Contractor fails to submit such particulars within the stated time (or
within such longer period as may be agreed in writing by the Architect), it shall
be deemed that the Contractor has assessed that such Relevant Event will
not delay the completion of the Works beyond the Completion Date", and that
he no longer requires the loss and expenses he notified the Architect earlier.
2.0
Ref:
Date:
SO address
Attn
In reference to the above, we wish to inform you our intention to claim for L&E under
our contract clause ___. Our intention to claim is base on the following relevant
events:
We shall submit our L&E claim upon completion of the above events for your
assessment.
Thank you
………………
Contractor
CC
4.0
SO address
Attn
In reference to the above, we are pleased to forward our L&E application under the
contract clause ___ for your consideration. The application is base on the following
events:
………………
Contractor
cc
5.0
……………………………………
Name:
Date:
Note :
Application must be made with a cover letter and EOT application report.
Each application of relevant event must use separate checklist to be attach with the evidence.
6.0
Report Format
------------------------------------------------Cover page ------------------------------------------
PROJECT TITLE :
PREPARED BY :
------------------------------------------------Page 1 -------------------------------------------------
CONTENT
------------------------------------------------Page 2 -------------------------------------------------
Justification:
B Reason: Appendix b
Justification:
C Reason: Appendix c
Justification:
Total
Time Start 1st 2nd 3rd 4th 5th 6th 7th 8th
PARTICULAR
Week Week Week Week Week Week Week Week
1. VO work- Boundary fencing & gate
2. VO work- M.S. Grill to windows
3. VO works-Pump House
Delay material from NSC- UAC
4.
Ceiling to Eaves
5. Delay by NSC-Landscaping
6 Compliance to Syabas
------------------------------------------------Page 4 -------------------------------------------------
delay as a result of the execution of work for which a Provisional Quantity is included in the Architect
Contract Bills which in the opinion of the Architect is not a reasonably accurate forecast of the
quantity of work required;
failure of the Employer to give in due time entry to or exit from the Site Employer
suspension by the Contractor of his obligations under Clauses 30.7 and 30.8; Employer
suspension of the whole or part of the Works by order of an Appropriate Authority due to Employer/Arch
negligence or omission on the parts of Employer, Arch or consultant. /Consultant
Note:
Relevant events as describe above applies for PAM contract 2006.
To determine relevant event for other contracts, refer to the conditions of contract.
8.0
Conclusion
Answer
1. NO. There is a misconception in the industry that if given EOT, L&E can be claim.
2. Contractor can only claim loss and expenses for affecting matters that falls under the contract.
3. Any other matters claim not within the clause shall not be within the jurisdiction of architect and QS
and shall be brought to common law and resolve between employer and contractor
Question 2
Will a contractor substantially prejudice its case for additional payment if it fails to keep adequate accurate
records?
Answer
1. The Contractor shall keep contemporaneous records of all his claims for loss and/or expense and
shall submit all particulars to the Architect
2. The time scale shall be in accordance to stipulated time in contract.
3. Therefore failure to comply will result in loss of entitlement.
4. Where record is to be contemporaneous or submitted within time scale, it is crucial for contractor
to made at time required.
Question 3
When a contractor fails to serve a proper claims notice or does not submit details of the claim as required by
the contract, can the architect legitimately reject the claim?
Answer
Yes. There are 2 condition that the contractor loses his entitlement to claim for L&E. The conditions are:
1. Failure to submit notice within a stipulated time under the contract
The Contractor has fail to set a precedent to any entitlement to the loss and expenses claim.
2. Failure to submit claim within a stipulated time under the contract
Contractor waive his right for L&E claim.
Question 4
With a programme shorter than the contract period, can the contractor/subcontractor claim additional
payment if, because of the timing of the issuance of the architect/engineer's drawings, he is prevented from
completing in accordance with the shortened programme?
Answer
No. Architect has no implied obligation as to issue drawing to allow contractor to complete work to meet
early completion programme.
Question 5
Where a contractor submits a programme (which is accepted) showing completion on the completion date
written into the contract, must drawings be issued in good time to enable the contractor to carry out the work
at the time and in the sequence indicated on the programme?
Answer
1. No. Architect has no implied obligation as to issue drawing to allow contractor to complete work
indicated in his programme.
2. It is the contractors obligation to apply in writing to the architect in sufficient time before the
commencement of the affected works to allow architect to give direction or furnish further drawing
within period which would not materially delay the progress of the affected works.
Question 6
Is a contractor/subcontractor entitled to recover the cost of preparing a claim?
Answer
Contractor shall require to follow the procedure for loss and expenses and submit particulars of his claim in
accordance to contract condition expressly stated.
Referring to this clause, it is the contractor obligation to prepare the claims under the terms of the contract
and submit it within time in order to claim for L&E. There for the cost of preparing the claim will be of no
entitlement for reimbursement.
Question 7
Where a delay to completion for late issue of instruction has been recognized, are loss and expense or
additional cost claims in respect of extended preliminaries properly evaluated using the rates and prices in
the bills of quantities?
Answer
Loss and expenses should be evaluated on the real cost and not the rates and prices in bills of quantities.
Question 8
Is a contractor/subcontractor entitled to be paid loss of profit as part of a monetary claim?
Answer
Not covered under the contract and within the jurisdiction of architect and QS. .
Contractor shall have to resolute to common law to be entitle for this claim base on loss of profit
Question 9
If a delay in the early part of a contract caused by the architect/engineer pushes work carried out later in the
contract into a bad weather period causing further delay, can the contractor/subcontractor claim loss and
expense resulting from the bad weather delay?
Answer
Yes. If the bad weather delay is a consequential delay cause by matters affected in L&E relevant event.
Question 10
Where one party to a contract is in breach and the injured party incurs loss, what obligations are there on
the injured party to mitigate the loss?
Answer
Where a breach of contract occurs,
The injured party shall take all necessary steps to keep the losses down to the minimum.
The losses which could have been avoided by taking reasonable steps will not be recoverable.