Cheong Gye Cheon Restoration Project

- a revolution in Seoul -

Dr In-Keun LEE
Director-General / Office of Waterworks
Formerly Cheong Gye Cheon Project
Seoul Metropolitan Government

ICLEI 2006 1
Before After

ICLEI 2006 2
Content
‰ Introduction
ƒ Seoul and Cheong Gye Cheon
‰ Cheong Gye Cheon 2002
‰ The Restoration Project
ƒ Background
ƒ Outline
ƒ Challenges
ƒ Progress
‰ Cheong Gye Cheon 2005
‰ Final Remarks

ICLEI 2006 3
ƒ Introduction
- Seoul and Cheong Gye Cheon

ICLEI 2006 4
Seoul at a glance

ƒ Capital city of Korea for o


ver 600 years
ƒ Area : 605.6 km2
ƒ Population : 10.3 M

City Centre

Han river

ICLEI 2006 5
Cheong Gye Cheon

Cheong Gye Cheon


CBD

ƒ Catchment area: 61 km2


ƒ Length: 13.7 km
ƒ Width: 20~85 m
ICLEI 2006 6
Old map of Seoul

ICLEI 2006 7
Early 20C

ICLEI 2006 8
Problem: sanitation

ICLEI 2006 9
Solution: covering

ICLEI 2006 10
Covering work
(1958~1977)

ICLEI 2006 11
Cheonggye Highway
(1967~1971)

ICLEI 2006 12
Highway in 1990s

ICLEI 2006 13
ƒ Cheong Gye Cheon 2002

ICLEI 2006 14
Cheong Gye Cheon Area

ƒ Building: over 6,000


ƒ over 100,000 small shops
ƒ Nation’s biggest commercial area
ICLEI 2006 15
Cheong Gye Cheon Area

ICLEI 2006 16
Declining old CBD

‰ CBD redevelopment stopped where the Ch


eonggye Expressway started

‰ Population and employment reduced


ƒ Population: 40,000
ƒ Employment: 80,000 in 10 years

‰ Business headquarters moved to Gangnam


(new sub-center)
‰ Industries in CBD lost competitiveness

ICLEI 2006 17
Safety problem

9 Over all “C”, partially “D”or “E”


ICLEI 2006 18
Safety problem

ƒ Only small cars were allowed from 1997


ƒ Maintenance cost soared: US$50M (’94~’99)

ICLEI 2006 19
ƒ The Restoration Project
- Background
- Outline
- Challenges
- Progress

ICLEI 2006 20
Decision to restore: July 2002

ICLEI 2006 21
Why restore?

‰ Paradigm shift of urban management


ƒ Development ÆHigh quality of life
ƒ Environment-friendly city

‰ Fundamental solution to safety problem


‰ Recovery of history and culture
‰ Revitalisation of downtown area
ƒ Balanced regional development

ICLEI 2006 22
ƒ The Restoration Project
- Background
- Outline
- Challenges
- Progress

ICLEI 2006 23
Site location

‰ Total length: 5.84 km

Section 1 (L=2.04km) Section 2 (L=2.1km) Section 3 (L=1.7km)

ICLEI 2006 24
Demolition
‰ Covered structure and highway: 5.4 km
ƒ Waste (concrete+asphalt): 872,400ton (96% recycled)
Step 1 Step 2 Step 3

ICLEI 2006 25
River design
‰ Design Criteria
• Satisfy with the 2nd grade local river standard
• Secure the stream capacity for 200 years frequency rainfall (118mm/hr)
‰ Flood Level: estimated by numerical model and corrected using hydrau
lic model test

HWL (200yrs)

ICLEI 2006 26
Water supply

‰ Waterway plan
• Width: more than 20% of main waterway width
• Depth: more than 40 cm
• Flow velocity: 0.24 m/sec
• Measures to prevent water loss

‰ Water supply plan


• Water from the Han river: 120,000 ton/day
• Underground water from subway stations: 22,000 ton/day

‰ Water quality: better than the 2nd grade


• BOD: 3mg/l or less • Total N: 10 mg/l or less
• SS: 25 mg/l or less • Total P: 1 mg/l or less
• DO: 5 mg/l or less

ICLEI 2006 27
Sewer system
‰ Design Criteria
• Combined sewer system for rainfall and wastewater
• Capacity : 3 times of estimated wastewater

‰ Combined Sewer System

ICLEI 2006 28
Bridge design
‰ Design Criteria
• Minimize flow resistance
• Create as cultural places
- artistic landmark
‰ Number of bridges: 22
‰ International concept design
competition

ICLEI 2006 29
Landscape design

‰ Concepts
• New green belt with waterfront: West to East
• Gradual transformation from urban landscape to natural environment
• Create ecological biotop and environment
• Thematic places: waterfall and fountains

Upstream Downstream
B C
A
Nature
Culture + Urban
History

ICLEI 2006 30
Historic relics restoration

‰ Basis
ƒ Preserve or restore historic relics
ƒ Consider current situation: flood, traffic, merchants
ƒ Involve specialists
‰ Site survey: Feb 2003 to June 2004
ƒ Restore 600 year old bridge: Gwangtong gyo
ƒ 150 m upstream from the original site
ƒ Restore Supyo gyo and Ogansu gyo: future plan

ICLEI 2006 31
ƒ The Restoration Project
- Background
- Outline
- Challenges
- Progress

ICLEI 2006 32
Challenge 1: Transport

‰Cheonggye road & hwy


ƒ Urban backbone corridor
ƒ 170,000 vehicles/day

‰Traffic disaster warned


ƒMedia, interest group
ƒTraffic simulation
ƒProject delay

ICLEI 2006 33
Solutions to transport

‰ Discourage driving cars in the city centre


‰ Improve traffic system
ƒ Cheong Gye Cheon area
ƒ Metropolitan area

‰ Improve public transport system


ƒ subway system
ƒ bus only lane

ICLEI 2006 34
Challenge 2: Neighboring merchants
ƒ Traffic congestion : access difficulty
ƒ Noise & dust due to construction
Ö Business decline

ICLEI 2006 35
Solutions to merchants
‰ Detailed survey on the markets and continu
ous interviews
ƒ consultation offices at the markets
ƒ regular meeting on the project

‰ Minimize inconvenience f
or business activity
ƒ state-of-the-art technolog
y
ƒ provide parking space nea
rby

ICLEI 2006 36
Solutions to merchants

‰ Stimulate business activity


ƒ Reduce parking fee
ƒ Improve parking system for loading & unloading
ƒ Promote Cheong Gye Cheon stores
‰ Financial support and subsidies
ƒ Low-interest loans
ƒ Grants for the market remodeling
‰ Special arrangement for street vendors
‰ Special business centre in a outer area

ICLEI 2006 37
ƒ The Restoration Project
- Background
- Outline
- Challenges
- Progress

ICLEI 2006 38
Project delivery

‰ Targets
ƒ Keeping the schedule
ƒ Best value for money
‰ Details of contract: Design-build contract
ƒ invitation for bid: Feb 2003
ƒ bidding: June 2003
ƒ starting work: 1 July 2003
À three construction sections
‰ Original project budget (’03): US$357M
ƒ Final adjusted amount (’05): US$386M (+8%)
‰ Original project period:
ƒ 1 July 03 ~ 30 Sep 05 (27 months)

ICLEI 2006 39
Construction progress
Started on 1 July 2003

ICLEI 2006 40
Construction progress

Stage 1: Scaffolding (July 2003)

ICLEI 2006 41
Construction progress
Stage 2: Highway demolition (Aug 2003)

ICLEI 2006 42
Construction progress
Stage 3: Covered road demolition (Jan 2004)

ICLEI 2006 43
Construction progress
Stage 4: Sewer, road & bridge construction (Sep 2004)

ICLEI 2006 44
Construction progress
Stage 5: Landscaping for the recovered area (May 2005)

ICLEI 2006 45
First water supply
1 June 2005

ICLEI 2006 46
Test running & Final touch
June ~ September 2005

ICLEI 2006 47
Grand opening

1 October 2005

ICLEI 2006 48
ƒ Cheong Gye Cheon 2005

ICLEI 2006 49
Monitoring
Changes

‰ Monitor the changes due to the project


ƒ from Jan 2003~Mar 2006
ƒ before, during and after the project

‰ Monitoring areas
ƒ Land use
ƒ CBD Industry
ƒ Environment
ƒ Ecology
ƒ Traffic
ƒ Real estate

ICLEI 2006 50
Traffic
Changes

‰ Speed in CBD
ƒ Morning peak: 17~18 km/hr
ƒ Evening peak: 12 km/hr
ƒ not very much worsened
‰ Car in/out flow
ƒ 1.56M Ö 1.27M (-18.6%)
‰ Subway ridership
ƒ Central area: +13.7%

ICLEI 2006 51
Environment
Changes

‰ Air
ƒ No2: 69.7 Ö 46.0 ppb (-34%)
ƒ PM10: 74.0 Ö 60.0 μg/m3 (-19%)
‰ Water quality
ƒ BOD: 100~250 Ö 1~2 ppm
‰ Noise level reduced
‰ Heat island effect relieved
‰ Wind corrider created

ICLEI 2006 52
Cooling effect
Changes

Thermal image
27 July 2005

37o 36o

28o 36o

Average 32.7oC -3.6oC Average 36.3oC


Cheong Gye Cheon Nearby street

ICLEI 2006 53
Environmental improvement
Changes

Public survey (Nov 2005)

Air

Water

Noise V improved
Improved
Odour Unchanged

Daylight

Wind

0% 25% 50% 75% 100%

ICLEI 2006 54
Ecology: Fishes
Changes

‰ 3 Ö 14 species

ICLEI 2006 55
Ecology: Birds
Changes

‰ 18 species

ICLEI 2006 56
Ecology: Insects
Changes

‰ 7 Ö 41 species

ICLEI 2006 57
ƒ Final Remarks

ICLEI 2006 58
Most preferred destination

ICLEI 2006 59
Future of Cheong Gye Cheon

‰ Identity as the 600 yr old Ca


pital
ƒ Harmony between preservati
on & development
‰ Economic vitality
‰ Pedestrian oriented street s
ystem
‰ International standard busin
ess district

ICLEI 2006 60
Effects of the Project

‰ Changes in the urban management


paradigm
‰ Historic restoration
‰ Nature & ecological restoration
‰ CBD regeneration
‰ Good example of
ƒ solving conflicts over a public project
ƒ successful project management

ICLEI 2006 61
Virtual Tour

ICLEI 2006 62
Further information
http://english.seoul.go.kr/cheonggye/
iklee@seoul.go.kr

Thank you for your attention!

ICLEI 2006 63