Test Validation

No Site ID type status Validator Scenario Date

111108 Fail Kedir 6/26/2020

123 Nemo

111440 Fail Kedir 6/26/2020

124 Nemo

111599 Fail Kedir 6/26/2020

125 Nemo
Validation date after Signature
Snag clearance status Type

4T4R

2T2R

2T2R
Remark

The lat long is not right,so it sis diffcult to check mobility test
SHC sec3 is not locked
Detach time and erab setup time for all sectors are above
target for all sectors
ping32 sec1 and sec3 and ping1460 sec1 are not locked
ping test is done 20 times for all sectors
DL all sectors test is not done in the right methodology

SHC sec2 is done 4 times


UL sec2 is not done
Detach time and erab setup time for all sectors are above
target for all sectors
DL all sectors test is not done in the right methodology

The site azimuth needs to be checked


DL mob average throughput failed
SHC sec1 and sec3 are not done 5 times
ping32 sec1 done 8 times and ping32 sec3 done 9 times
There is transfer failure in UL all sectors
attach failure in sec1 and attach duration is above target for all
sectors
Detach time is above target for all sectors
DL sec2 is not done
there is transfer failure in DL all sectors
SSV Validation Summary_Kedir
Tool Failed Passed Retest Signed Total
Nemo 61 0 0 0 61
PHU 16 48 47 48 64