In Case of Currency Exchange Case, Price Adjustment Factor is taken as Unity for all year in count; only multiplied by
Exchange Rate (28 days before the deadline of bid submission)
Annual Price
Adjusted Annual A in Value of B, in Bid Capacity in
SN Fiscal Year Turnover in Adjustment
Turnover in Millions Millions Millions Millions
Millions Factor
Col ID -> a b c d e f g
1 2074 2075 5000 1 5000
2 2073 2074 4500 1.1 4950
3 2072 2073 4700 1.2 5640
4 2071 2072 5500 1.3 7150
5 2070 2071 3500 1.4 4900
6338 3825 40543
6 2069 2070 4000 1.5 6000
7 2068 2069 3300 1.6 5280
8 2067 2068 3450 1.7 5865
9 2066 2067 2500 1.8 4500
10 2065 2066 2100 1.9 3990
Annual Price
Adjusted Annual A in Value of B, in Bid Capacity in
SN Fiscal Year Turnover in Adjustment
Turnover in Millions Millions Millions Millions
Millions Factor
Col ID -> a b c d e f g
1 2074 2075 3500 1 3500
2 2073 2074 3150 1.1 3465
3 2072 2073 3290 1.2 3948
4 2071 2072 3850 1.3 5005
5 2070 2071 2450 1.4 3430
4437 2425 28633
6 2069 2070 2800 1.5 4200
7 2068 2069 2310 1.6 3696
8 2067 2068 2415 1.7 4105.5
9 2066 2067 1750 1.8 3150
10 2065 2066 1470 1.9 2793
Annual Price
Adjusted Annual A in Value of B, in Bid Capacity in
SN Fiscal Year Turnover in Adjustment
Turnover in Millions Millions Millions Millions
Millions Factor
Col ID -> a b c d e f g
1 2074 2075 1750 1 1750
2 2073 2074 1575 1.1 1732.5
3 2072 2073 1645 1.2 1974
4 2071 2072 200 1.3 260
5 2070 2071 1.4 0
6 2069 2070 1.5 0 1819 4175 8557
7 2068 2069 1.6 0
8 2067 2068 1.7 0
9 2066 2067 1.8 0
Current Contract Commitments Form( For Calculation of B with reference of FIN-4) for Individual Contractor
Col ID -> a b c d e f g
1 Rap-1 35 8000 2073 10 10 4500 12 131
2 DIT-2 50 5000 2072 9 36 2500 4 104
3 DOR/73/74-20 100 4500 2073 5 28 1000 4 83
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Current Contract Commitments Form( For Calculation of B with reference of FIN-4) for Individual Contractor
Col ID -> a b c d e f g
1 DPR/900 100 6000 2071 10 42 1500 9 125
2 DRODH/03 25 4500 2073 10 36 1300 9 27
3 DOR/LT-99 25 4000 2074 12 28 3000 15 50
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Current Contract Commitments Form( For Calculation of B with reference of FIN-4) for Individual Contractor
Col ID -> a b c d e f g
1 Gap-4 45 3500 2074 8 15 1500 2 56
2 LLT-076 100 4500 2074 12 24 3000 11 250
3 POK_45 100 2500 2075 9 16 500 12 42
4
5
6
7
8
9
10
11
12
13
14
15
16
17
# The Outstanding Works means Contract Price (excluding Vat) minus Work Evaluated by Employer till the reference date.
Note 1: “B” shall be calculated as : ( e) ( a ) , If (f) is less than 12, then value of (f) shall be taken as 12.
B x12
(f)
Note 2: If Initial or Revised Contract Date is run out with respect to Date of Invitation of Bid, the Estimated Time in Month to Complete the outstanding works shall be taken equal to 12 months.