Check list for integrating third party Equipment to BSNL Network

1. Site Inspection Report


 Install the equipment in the allocated Premise
 Power ON
 Product Specification
 End to end connectivity details
 Requirement for testing
 Share the report duly signed by Node In Charge/DGM( attached as Annexure 1)

2. Testing Committee
Testing Committee include the following officers from the below modules
 BNG
 RPR
 FTTH
 MPLS
 Node In Charge
 Circle/SSA Co-ordinator
3. Testing of connected elements
 Conducting of testing as per requirement
 Validation of testing
 Completion of testing
4. Preparation of Report
 Report needs to be prepared as per the testing procedure
 Sharing of report with concerned SSA
5. Commissioning of Tested Equipment

5th Floor, Bangalore East Telephone Exchange, Lazar Road, Bangalore East, Bangalore 560005.
Tel. No: 080- 2580 8890, Fax: 080 – 2580 8880, Mob: + 91 94480 10361. Email: buddhan@bsnl.co.in