Professional Documents
Culture Documents
Abstract -- As part of the energy transition and the transformers a DGA is not applicable. Therefore, partial
associated development of renewable energies, the number of discharge diagnosis by means of a single-phase induced
installed dry-type transformers is increasing on the medium- voltage test is discussed below. In contrast to a three-phase
voltage power grid. Therefore, the paper at hand focuses on on-
excitation in the factory, the transformer under test is
site condition assessment of dry-type power transformers which
are often installed in wind turbine nacelles, industrial sites as energized with a single-phase source. Thus, the power intake
well as in marine and civil applications. The assessment of the is reduced, and a more compact and lightweight source can
insulation condition is based on an induced voltage test in be used on-site. This way, measurements in confined spaces
combination with a partial discharge measurement. In contrast can be conducted rendering a bulky trailer mounted source
to laboratory tests under controlled conditions, an increased unnecessary. A portable test system of 30 kg [2] is used to
level of interference from rotating machinery, power electronics
energize transformers with power ratings up to 4 – 5 MVA.
and other consumers is to be expected on site. The approach of
energizing transformers of power ratings up to 15 - 20 MVA For power ratings up 15 – 20 MVA to two additional
with a portable, scalable single-phase voltage source is amplifiers can be installed. Combining this approach with a
presented. Due to the single-phase injection the power intake is PD measurement offers the possibility to analyse the
reduced, and an individual evaluation of each coil becomes insulation system of each coil individually, resulting in a
possible. Practical examples show how partial discharge signals powerful tool for reliable on-site insulation diagnostics of
can be separated from these interferences using a synchronous medium-voltage transformers.
multi-frequency PD measurement.
are suitable. In the following, the main characteristics of the reduced compared to a three-phase excitation. Fig. 3 depicts
FAT and the on-site, offline PD diagnostics are discussed. the power intake in “kVA” at nominal voltage of three
distribution transformers with power ratings between
A. Factory Acceptance Test
800 kVA and 1600 kVA. It can be seen that in case of a
After finalizing all voltage withstand tests during the single-phase excitation the power intake is reduced by
factory acceptance test (FAT), the partial discharge approx. 50 %.
measurement is carried out on each individual unit. For a
three-phase transformer a three-phase voltage source is
connected to the low-voltage winding to energize the device
under test. On the high-voltage winding a coupling capacitor
and a measurement impedance (“coupling device”, “CD”)
are connected to each phase terminal. A PD measurement
system is then installed which is switched between the phases
during the test cycle to record the PD activity. Alternatively,
a three-channel PD measurement system can be used to
simultaneously analyse all three phases. Using the latter
approach, identifying possible cross-talk between the phases
and separating multiple PD sources can be realized. A
schematic overview of the common measurement setup is
given in Fig. 1.
Fig. 3. Comparison of power intake between a three-phase (blue) and a
single-phase (green) excitation.
Fig. 12. PRPD of the isolated internal PD. Fig. 14. Frequency spectrum of noise and calibrator impulse, filter
frequencies marked in red.
B. 19 kV / 3 kV / 9.5 MVA Transformer
While there are no signs of PD activity on phase A, phase
The second case study deals with the on-site testing of a
B clearly shows the inception of partial discharges at 15 kV.
19 kV / 9.5 MVA / Dyn11 dry-type transformer. The unit is
After visual inspection of the coil it was is found that the top
installed in a cavern power plant and part of the excitation
part of the winding body is polluted with dirt. Since a
system of a 400 MVA asynchronous generator. As one sister
comprehensive cleaning of the winding surface is not
transformer showed PD activity the operator decided to
feasible, it is decided to change the setup of the
check all remaining units for partial discharges. Since the
measurement. While the excitation of the transformer
transformers are all installed in the cavern, it became
remains unchanged, one side of the tested HV winding is
necessary to perform the requested measurements with a
connected directly to ground. First the coupling capacitor
portable test system. The single-phase excitation of the
stays connected to the terminal on top of the winding where
transformer is realized by using two synchronized test
the pollution is the heaviest, Fig. 15-a). Afterwards, the
systems [2] to provide the needed power. In addition, a 0.4
connection of the coupling capacitor and the ground
kV / 3 kV transformer stepped up the output voltage U of the
connection are exchanged. This way the main insulation of
test system to the LV rating of the transformer under test.
the winding is electrically stressed in the same way while
The complete connection diagram can be seen in Fig. 13. As
there is no electrical stress on the terminal next to the
a PD measurement system, a MPD600 [11] from OMICRON
polluted winding surface, Fig. 15-b).
is installed on the HV.
VI. CONCLUSION
The article at hand focuses on the insulation assessment of
dry-type medium voltage transformers. A comparison is
drawn between the three-phase induced voltage test of the
factory acceptance test and a single-phase approach for on-
site testing purposes. Due to expected interferences, the
3CFRD-method is introduced. This synchronous multi-
frequency measurement allows the operator to separate
electromagnetic noise from PD signals. Besides, individual
PD sources can be distinguished and analysed independently.
Two case studies are presented which show that a single-
phase induced voltage test on three-phase transformers can
be utilized to identify insulation defects. Due to a defined
voltage distribution, each coil can be examined individually.
Finally, all obtained information during the PD measurement
Fig. 16. PRPD for polluted side on a) high voltage and b) on ground.
such as the type of the PD source and the inception voltage
are factored in the evaluation of the criticality of the defect.
Finally, phase C is energized and checked for any PD
activity. Again, partial discharges occur below nominal
voltage, at 14 kV, in both haft-waves of the test voltage. VII. REFERENCES
Discharge levels of up to 800 pC are recorded. The pattern [1] Mineral oil-filled electrical equipment in service - Guidance on the
interpretation of dissolved and free gases analysis, IEC 60599,
evaluation shows comparable results compared to phase V, Sept. 2015.
Fig. 17-a). However, the symmetrical patterns in both half- [2] CPC100 – Technical Data Sheet, OMICRON electronics, 2016.
waves show a tendency to follow the shape of the voltage [3] Martin J. Heathcote, "J&P Transformer Book", 13th edition, Elsevier
sine-wave. Typically, those characteristics point towards Ltd., 2007.
[4] Power transformers – Part 11: Dry-type transformers, IEC 60076-
internal discharges in the solid insulation system [8]-[10]. 11:2004, Jun. 2005.
Again, the same approach as discussed above is applied, Fig. [5] High-voltage test techniques – Partial discharge measurements,
15. In contrast to the previous phase, changing the IEC 60270, Ed. 3.1, Nov. 2015.
connection setup does not have any influence on the partial [6] A. Carlsson, F. Wegschneider, G. Schemel, J. Fuhr, "Testing of power
discharge activity, Fig. 17-b). As the voltage stress across the transformers and shunt reactors", ABB, 2nd ed., Chapter 8.5.4,
May 2010.
turn-to-turn insulation of the winding remains unchanged this [7] M. Krüger, A. Kraetge, K. Rethmeier, “Improved Partial Discharge
emphasizes the assumption that PD impulses are caused by Measurements by Real-time Impulse Waveform Analysis”, CIGRÉ
gaseous voids inside the main insulation. Workshop on Power Transformers, Iguacú, Apr. 2010.
[8] Partial Discharges in Transformers – Working Group D1.29,
CIGRÉ, Brochure 676, Feb. 2017.
[9] Recognition of Discharges – Working Group 21.03, CIGRÉ, 1969
[10] J. Fuhr, "Procedure for Identification and Localization of Dangerous
PD Sources in Power Transformers", IEEE Transactions on
Dielectrics and Electrical Insulation, Vol. 12, No. 5, Oct. 2005.
[11] MPD 600 – Technical Data Sheet, OMICRON electronics, 2015.
VIII. BIOGRAPHIES
Victor Lozano was born in Madrid, Spain, in 1976. He received his high
technical degree in electronic product development in 1999. He was
working for 15 years in Unitronic electric as technician in the calibration
laboratory and specialized in Power transformers and rotating machines
testing. In 2014 he joined OMICRON Technologies España as Sales &
Application Engineer. He is concerned with sales, technical support and
training regarding substation assets and rotating machines diagnostics.
Fig. 17. PRPD for top of the winding on a) high voltage and b) on ground.