Professional Documents
Culture Documents
The ongoing discharge ads further gases, which allow the gasfilled cavities to persist. Further, there is also so-called corona
discharge at bushings and external high voltage Icads.
Thus, for most of the stable partial discharge in transformers
the rules of gas discharge apply. For the occurrence of gas
discharge two conditions must be met. Firstly, the local
electrical field must have reached the streamer inception field
and, secondly, a free electron must be available. This 'first'
electron is then accelerated in the electrical field strong
enough to cause secondary electrons to build the electron
avalanche, when it hits a gas molecule (Figure 1). The
ongoing partial discharge is then 'supplied' by electrons
derived from de-trapping of electrons kept in flat traps on the
surfaces of the cavity.
Photon
INTRODUCTION
Among high voltage generation,.transmission,and distribution
equipment, large power 'transformers have an insulation
system with the highest complexity. Other than with rotating
machines, for instance, the inner components of a transformer
are not accessible. Thus, besides the time and cost-consuming
opening of a transformer, any testing is limited to the
terminals and the tank wall.
El
Figure 1 - Partial discharge in a spherical gas inclusion (void)
0-7803-8447-4/04/$20.0002004IEEE.
186
In the test room, the supply is *ically provided by a motorgenerator set. The test frequency is usually chosen three to
five times the line frequency. Induced voltage tests on-site are
mostly performed using Diesel engine generator sets [l I].
*17.6
IPCl
0.c
.171
I80
Ide0 I
360
TEST CONFIGURATIONS
Various test configurations are possible for a large power
transformer. Firstly, with the applied voltage configuration, a
test transformer is used to energize the transformer under test
on one bushing of the high voltage winding. In the test room,
this is often a single-phase standard transformer. Alternatively,
and especially under field conditions, resonant test sets are
used for the applied voltage test. More commonly, the induced
voltage configuration is used to energize the transformer.
Normally, a single-phase or three-phase step-up transformer is
connected to the low voltage winding. With machine
transformers energizing from the tertiary winding is a
commonly applied option.
187
.
.
.
.
.
.
188
In time domain (Figure 6), firstly the travel time from the
point of injection to the point of acquisition is seen. Secondly,
the graph shows the resonant behavior when injecting at a
high voltage bushing and measuring at a tertiary terminal. The
frequency domain (Figure 7) shows the coupled signal for
IOOOpC (upper trace), IOOpC (mid trace), and noise floor
(lower trace) for the same connection. This graph shows that
during this test for frequencies below 2MHz the sensitivity is
reduced by ambient noise signals. It further shows that the
cross coupling has an increasing efficiency above 6MHz.
REf
PEAK
LO6
.e
*n
dB,
R T IS 4 8
darn
.
.
I .
........................................................................................
.
.
. . . . . . . . . . . . . ... . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
;;:!,;;I
.
.
.
.
........................................................................
00 I
iao
IdWl
I
350
............................................................
.
.
I
-.
I
Figure 10 -Discharge activity shown with Fig. 9 in time domain.
180
I de0 I
S T R R T 188 L H I
I R E S BW 3 0 k l l r
""BW
30 XHI
S T O P iB.iB PI".
.*UP
18.8
'.C
..~.'
..
,. ,.
180 .-
Iaeg I
360
190
3.
Fmth, B., Gross, D. "Partial Discharge Signal
Generation Transmission and Acquisition," IEE Proc.-Sci.
Meas. Technol., Vol. 142, No. 1,January 1995, pp. 22-28.
4.
Niemeyer, L. "A Generalized Approach to Partial
Discharge Modeling", IEEE Trans DEI, Vol. 2, No. 4, August
1995, pp. 519-528.
5.
Heitz, C. "A Generalized Model for Partial Discharge
Processes Based on a Stochastic Process Approach", J. Phys.
D, September 1999, pp. 1012-1023.
6.
Gross, D., Soeller, M., "Partial Discharge Acceptance
Testing and Monitoring on Power. Transformers,'' ETG
Fachtagung, Diagnostik el. Betriebsmittel, Berlin, Germany,
February 26-27,2002, ISBN 3-8007-2671-8, pp. 213-216.
7.
Sundermann, U,, Fmth, B:; and Gross, D. "On-Line
Partial Discharge Testing of Power Transformers". EPRI
Substation Equipment Diagnostics Conference, New Orleans,
USA, February 16-18,1998.
8.
Gross, D. "On-site partial discharge diagnosis and
monitoring on I
N power cables", Conf. Proc. of Jicable, June,
1999, Versailles, France, pp. 509-514.
Figure IS - ICMmonilor unit installed on a power transformer
CONCLUSION
Large power transformers are valuable and important
components of the grid. Partial discharge testing on power
transformers is a demanding and challenging task because of
their intemal complexity. However, in-depth analysis using
well-adapted instruments can greatly reduce the efforts of the
time-consuming and costly opening and re-testing of power
transformers.
9.
Diessner, A., Gorahlenkow, J., Hashoff, I., and
Schreieder, A. "Experience with Diagnostic Techniques for
Electrical Insulation in G I s . CIGRE Symp:, Berlin, 1993,
Report 130-10.
10.
Gross, D., "Partial Discharge Measurement and
Monitoring on Rotating Machines," ISEI 2002 Conference,
Boston, MA, April 7-10,2002,02CH37316, pp. 570.574.
11.
Braunlich, R., Hassig, M., Fuhr, J., and Aschwanden,
T. "Assessment of Insulation Condition of Large Power
Transformers by On-Site Electrical Diagnostic Methods", ISEI
International Symposium on Electrical Insulation, Anaheim,
CA, U.S.A., April 2-5,2000.
12.
Carlson, A., Fuhr, J., Schemel, G., and Wegscheider,
F. Testing Power Transformers. ABB Business Area Power
Transformers, 2003, ISBN 3-00-010400-3.
- Partial
REFERENCES
13.
IEC60270, High-voltage test techniques
discharge measurements, CEILEC 60270:2000.
1.
Bean, R. L., Chackan, N., Moore, H. R., and Wentz,
E. C. Transformers for the Electric Power Zndustry. MsGrawHill Book Company, Inc., 1959, pp. 341-346.
14.
IEEE C57.113-1991 'WEE Recommended Practice
for Partial Discharge Measurement in Liquid-Filled Power
Transformers and Shunt Reactors".
2.
Fruth, B., Gross, D. "Phase Resolving Partial
Discharge Pattem Acquisition and Spectrum Analysis", Proc.
of the ICPDAM, July 1994, Brisbane NSW, Australia,
94CH3311-8, pp. 578-581.
15.
Bengtsson, T, Kols, H., Jonsson,. B., "Transformer
PD Diagnosis using Acoustic Emission Technique," Conf.
Proc. of ISH, August 25-29, 1997, Montreal, Canada, Vol 4,
pp. 115-119.
191