You are on page 1of 1

Tanahun District

DPR of Rising Kot and Durbar

COST ESTIMATE CONSTRUCTION : RATE ANALYSIS

Description Unit Unit Rate Unit


Quantity Cost
311 Structural Steel
Material Structural Steel kg 1.05 98.00 102.90
Labour Skilled Md 0.02 1,030.00 20.60
Unskilled Md 0.03 750.00 22.50
Subtotal 146.00
Tools and Plants (7%) 10.22
Total 156.22
Cost per kg with 15 % overhead 179.65
411 Material and Equipment
Transportation by Truck
From : Kathmandu Metalled Road, km 25.00 1.000 276.00 6.90
To: Bridge site Non Metalled Road, km 1.000 7.71
Transportation by Porter (Rate=Daily wage/38) 1.000 8.55
Transportation by Air
Subtotal 6.90
Total per kg 6.90
Cost per kg with 15 % overhead 7.94
572 Erection of Truss Bridge
Material Bamboo P 6.00 210.00 1,260.00
Dori kg 2.00 60.00 120.00
Labour Skilled Md 1.90 325.00 617.50
Unskilled Md 15.00 325.00 4,875.00
Subtotal 6,872.50
Cost per m with 15 % overhead 7,903.38
351 Hot Dip Galvanisation
Material Zinc kg 0.095 295.00 28.03
HydrocloricnAcid Ltr 0.065 39.00 2.54
Chemical for pre-fluxing Kg 0.025 577.00 14.43
Fuel Ltr 0.056 96.50 5.40

Labour Skilled Md 0.001 1,030.00 0.72


Unskilled Md 0.005 750.00 3.94
Subtotal 55.05
Tools and Plants 5% 2.75
57.80
Cost per m³ with 15 % overhead 66.47