You are on page 1of 3

SparkEnergy Communication System

TEST REPORT
PUTTING INTO OPERATION

Code: 425.200.500.023
Version: 1.05

Customer

Customer:
Order No:

Device

Device type:
Serial No:
Device address:
Facility:
Connected
devices:

No of
Project:
pages:
Date:

Contractor: (signature)

Attachment:
CONFIGURATION PRINTOUT YES NO (tick appropriate)

CTR_CSSE_a_v105.doc
Page _____
SPARKENERGY COMMUNICATION SYSTEM

SYSTEM PART
1. SW versions
CMS:
PEGASUS:
See: Pegasus -> Supervision -> Operational data

2. Connection status
IP adress Subnet mask Default gateway

3. Power Supply
Power supply unit type PS1 PS2
PS
(Universal Power supply unit)
PS48/60
(48VDC - 60VDC Power supply unit)
 = built-in; x = not built-in

4. Built-in applications
1 2 3 4 5 6 7 8
Application
x = not built-in

CTR_CSSE_a_v105.doc
Page _____
SPARKENERGY COMMUNICATION SYSTEM

DZ9 APPLICATION Application no: #1 #2 (encircle suitable)

1. SW versions
TLI: Primary Secondary
o o
CSR (N 1) CSR (N 2) CSR (No3) CSR (No4)
See: Pegasus -> Supervision -> Operational data

2. Line interface
Primary line Secondary line

3. CSR unit - Command input test


CSR (No1) CSR (No2) CSR (No3) CSR (No4)
CMD_IN
1 2 1 2 1 2 1 2
Checked
 = checked; x = not built-in

4. CSR unit – Command output test


CSR (No1) CSR (No2) CSR (No3) CSR (No4)
CMD_OUT
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Checked
 = checked; x = not built-in

5. CSR unit - Relay signalling test


CSR (No1) CSR (No2) CSR (No3) CSR (No4)
SGN_OUT
1 2 1 2 1 2 1 2
Checked
 = checked; x = not built-in

6. Measurement of Test command nominal transmission time


Primary line (ms) Secondary line (ms)
Test command
See: Pegasus -> Supervision -> Operational data

7. CSR unit – Setting of command input jumpers


CSR (No1 ) CSR (No2) CSR (No3) CSR (No4)
JP1 JP2 JP1 JP2 JP1 JP2 JP1 JP2
Setting
24V, 48V, 110V, 220V

8. CSR unit – Setting of command output soldering connections


CMD_OUT CSR (No1) CSR (No2) CSR (No3) CSR (No4)
Soldering connection
P1, P2, P3, P4, x = not built-in

9. CSR unit - Setting of signalling output soldering connections


SGN_OUT CSR (No1) CSR (No2) CSR (No3) CSR (No4)
Soldering connection
P5, P6, P7, P8, x = not built-in

10. E1-75/120 line interface – Setting of jumpers and connector selection


Connector Jumpers Primary line Secondary line
position JP1, JP2, JP3, JP4, JP5 JP1, JP2, JP3, JP4, JP5
BNC 1-2
RJ45 2-3
 = built-in; x = not built in

11. LFI interface – Choosing the soldering connection for impedance setting on the analog
input/output
Primary line Secondary line
P1 P2 P1 P2
Soldering connection
 = built-in; x = not built-in

CTR_CSSE_a_v105.doc
Page _____