COST OF QUALITY

Project Cost Estimate $ 745,979.75 100%


CURRENT FUTURE COST
CONFORMANCE COST PERCENT PERCENT
COST
PREVENTIONS COST

SECURITY SYSTEM DEVELOPMET $ 10,000.00 1.34% $ - 0.00%


SUPERVISION OF PROJECT $ 9,000.00 1.21% $ - 0.00%
DOCUMENTS
QUALITY TRAINING $ 12,000.00 1.61% $ - 0.00%
TOTAL PREVENTION COST $ 31,000.00 4.16% $ - 0.00%
APPRAISAL COST

DELAYED RENTAL EQUIPMENTS $ 17,500.00 2.35% $ - 0.00%


SUPERVISION OF TESTING $ 8,000.00 1.07% $ - 0.00%
RELIABILITY TESTING $ 4,500.00 0.60% $ - 0.00%
TOTAL APPRAISAL COST $ 30,000.00 4.02% $ - 0.00%

TOTAL COST OF CONFORMANCE $ 61,000.00 8.18% $ - 0.00%

COST OF FUTURE COST


COST OF NON-CONFORMANCE PERCENT PERCENT
QUALITY OF QUALITY
INTERNAL FAILURE COST
DRONE REPLACEMENT 0.00% $ 22,000.00 2.95%
$
-
LACK OF QUALITY DOWNTIME 0.00% $ 12,500.00 1.68%
$
-
REWORK AND OVERHEAD LABOR 0.00% $ 12,500.00 1.68%
$
-
TOTAL INTERNAL FAILURE COST 0.00% $ 47,000.00 6.30%
$
-
EXTERNAL FAILURE COST
WARRANTY REPLACEMENTS 0.00% $ 7,500.00 1.01%
$
-
LOST OF BUSINESS 0.00% $ 30,000.00 4.02%
$
-
TERRITORIAL BIRD ATTACKS 0.00% $ 22,000.00 2.95%
$
-
TOTAL EXTERNAL FAILURE COST 0.00% $ 59,500.00 7.98%
$
-

NON-CONFORMANCE TOTAL COST $ 0.00% $ 106,500.00 14.28%


-

$ 106,500.00 14.28%
$ (61,000.00) -8.18%

$ 45,500.00 6.10%