Professional Documents
Culture Documents
Abstract. During the design phase of the reconstruction of the existing mooring facility “EBS Biohub” at the port of Rotterdam,
the Netherlands, a high risk profile was recognized in the proximity of four new dolphins next to the existing jetty. The risk
originated from the greater installation depth of the dolphins related to the limited foundation depth of the existing foundations
and from the structural analysis which indicated that the superstructure could only withstand limited settlement differences. Risk
management aspects were incorporated in the contract by defining an observational approach involving monitoring of the
structure and the subsoil. The contractor Geka offered a pile test at dolphins to be installed at a safe distance from the jetty. A
number of test piles were installed at varying distances from the dolphins in order to detect settlements. The induced settlements
were compared with a contractually defined criterion. Based on the test, two installation methods were in place. Two dolphins
were installed under a slope in order to create a minimum of 5 m distance between the installation trajectory and adjacent piles.
Two dolphins at shorter distance were placed while two adjacent piles per dolphin were cut from the jetty platform with an
alternative support by a reaction frame with active hydraulic compensation at service load. All criterion on bearing capacity,
vibration levels, settlements, deformations and cone resistance were met. No damage on nor deformation of the existing structure
was encountered resulting in a success in terms of budget, planning and risk management.
Pile tip
Dolphin
-10
dolphin installation depth (NAP -35 m), marked 1% volume loss
in Figure 4. Based on previous projects involving -15
(sheet)pile driving in granulair soils (de Nijs -20
2003, de Nijs 2015) an estimated lower boundary
on compaction was used in a settlement analysis. -25
The main elements form the superstructure, the 3.1. Contractual Approach on Risks
longitudinal loader beams, had a rigid behavior.
The connection with the cross beams and piles The analysis indicated a high risk on damage to
acted as hinges. The limited thickness, 8 cm, of the jetty as a result of pile settlements induced by
the in situ casted deck implied it couldn’t dolphin installation by means of hammering.
redistribute alternative loading caused by From a clients point of view The Port of
deformations. At pile settlement, the 4 to 1 slope Rotterdam perceived an uncertain outcome if
of the piles would cause a movement in only the requirement of a maximum settlement
horizontal direction or would require a reaction of 10 mm would be contracted. The specification
force, see the red marked pile in Figure 6. itself could not guarantee that the requirement
The horizontal displacement would initiate a would be met by the contractor. Exceeding the
tension load in the cross beam, since the criterion was a most unfavorable outcome for the
unaffected surrounding piles outside the active client as well as the contractor, introducing new
wedge would not respond to the deformations. uncertainties on repair and future usability of the
The connections with the loader beams could not jetty.
withstand this additional load. As a result the The alternative however, a reliable and cost
deck would be damaged and the crane rail effective design or procedure on pile installation
distance would exceed the horizontal tolerance. to mitigate this risk, proved to be very difficult to
From the structural analysis in FEM it was found design and define in a contract. Especially the
that the jetty could only withstand limited practical aspects of pile installation or structural
settlement differences between piles to a mitigation were difficult to estimate or to define.
maximum of 10mm. In response to this uncertainty the client
adopted the strategy to invite contractors to offer
a risk management procedure. In the selection
procedure the contractor would benefit from the
offered quality regarding settlement control and
preservation of structural integrity. The offered
risk management was therefore incorporated in
the bid and ultimately in the contract between
client and contractor.
In order to allow the contractor to optimize
and demonstrate its risk management procedure,
the observational method was in place. Since
three dolphins could be installed prior to the four
critical ones, a learning curve on site was
Sand layer possible. The contractor was also allowed to
reduce pile driving energy by means of flushing
wedge the dolphin internally up to 2 m above tip level.
P1 -23 unloaded
-30
P2 -23 unloaded
-40 P3 -23 pile load
-50 P4 -23 pile load
-60 P5 -23 pile load
P6 -25.8 unloaded
-70
P7 -25 unloaded
-80 P8 -23 unloaded vibratory
-90 P9 -23 unloaded vibratory
postdiction -3% and -2% Figure 12. Dolphin installation with slope 7 to 1.
-100
5. Resume
References
Figure 13. Dolphin positions M1 and M2, vertically installed
Nijs, R.E.P. de (2003). Installation of sheetpiles in granulair
Per dolphin the adjacent piles with a slope soil, Geotechniek, october 2003, 46-54. (in Dutch)
towards the dolphin were cut and hydraulically
Nijs, R.E.P de, Kaalberg, F.J, Osselaer, G, Couck, J. van
compensated, see the marked piles in Figure 13. Royen, K. (2015). Full scale field test (sheet)pile
Before cutting the piles, a reaction frame was drivability in Antwerp (Belgium), Proceedings of XVI
installed, see Figure 14. The piles were loaded up ECSMGE 2015, Edinburgh, 13-17 September 2015.
to service load. During installation of the
dolphins the system was kept at its original load
by hydraulics. During driving of the dolphins
approximately 40 mm settlement occurred.