Professional Documents
Culture Documents
Operations Management - I
Authors:
Somitra Baldua
Akanshu Verma
Abhin Ketan Kakkad
Sounak Bhadra
Chinmay Dharap
Danish S Mehta
Section: E
August 2019
To: Hugo Schaeffer
From: Group_E13
RE: RP#1 processing
Memo
NCC is one of the largest cranberry cooperative in North America.Company’s strategic objective
is to improve its production operations in terms of overtime costs and truck waiting times before
the onset of 1971 crop. NCC has been facing extremely high overtime costs despite investing
$75,000 for a fifth Kiwanee dumper at their receiving plant 1 (RP1). Moreover, high waiting
times for truck unloading has led to wide resentment amongst the growers because of the
significant cost. To solve this problem, we analysed the process flow diagram for RP1 breaking
down each individual unit separately for wet and dry berries. Implied utilization for each
workstation was used to evaluate the bottleneck. It was observed that drying process for wet
berries with an implied utilization of 180% was the bottleneck resource significantly limiting the
capacity of entire cranberry production process. Since demand at the bottleneck (1080 bbl/hr)
was significantly higher than capacity (600 bbl/hr), this led to inventory build-up at the bins.
Since bins designated for wet berries had a limited capacity of 3200 bbl, this led to queuing up of
trucks waiting to get unloaded once bins capacity was exhausted.
In order to analyse the inventory build-up and resultant overtime and waiting costs, inventory
build-up rate (480 bbl/hr) and inventory draw down rates (600bbl/hr) were used to plot inventory
build-up profile. The bottleneck resulted in an overtime of ~9.5 hours and 163 truck hours of
waiting time worth $16,300 cost. Thus the total costs including overtime labor cost and truck
waiting time is ~$70,300.
In order to solve the problem, option to purchase either 1 dryer or 2 dryer was evaluated.
To analyse, bottleneck resource of the entire process was analysed and subsequent inventory
build-up graphs were evaluated basis new inventory drawdown rate and inventory build-up rate.
These were used to compute the impact on overtime costs as well as truck waiting hours and
cost.
1 new dryer reduced overtime by 56%, savings of $30,240 in overtime costs with $81 as truck
waiting cost at an investment of $25k. Thus total costs including investment is $54,835.
2 new dryer reduced overtime by 83%, savings of $44,820 in overtime costs with no waiting of
trucks at an investment of $50,000. The total cost including investment is $59,180.
1-16
Temporary holding bins
Dry Berries
250 bbls /each
Total Capacity: 4000 bbls
Dry
berries
Kiwanee Dumpers 17-24
Trucks 5 dumpers Temporary holding bins
Capacity: 5-10 min/truck Wet berries Destoning, 3 units
75 bbls/truck (average: 7.5minutes) 250 bbls /each 1500 bbls/hour/unit
600 bbls/dumper Total Capacity: 2000 bbls Total Capacity: 4500 bbls/hr
Total capacity: 3000 bbls
25-27
Temporary holding bins Wet
Wet berries berries
400 bbls /each
Total Capacity: 1200 bbls
Dechaffing
3 units
1500 bbls/hour/unit
Total Capacity: 4500 bbls/hour
Drying
3 units
200 bbls/hour/unit
(Max.)
Wet berries Total Capacity: 600 bbls/hour
Dry berries
9 Jumper Separators
3 separators lines
400 bbls/hour/line
Total Capacity: 1200 bbls/hour
Resource bottleneck
The below table gives the utilization of each of the individual workstation.
Please refer to Exhibit 1 for detailed calculations.
Since drying process has the highest implied utilization it is the bottleneck in cranberry
processing which needs to be resolved.
Its utilization is 50% higher than the next highest utilization implying a high degree of mismatch
between the capacity and demand in the entire process.
Since drying is the only process where demand is greater than capacity, inventory builds up at
the drying unit.
Demand for wet berries = 1080 bbl/hr
Capacity = 600 bbl/hr
Thus, inventory buildup rate = Demand – Capacity = 480 bbl/hr.
Time to reach maximum capacity = Max capacity/buildup rate = 3200/480 = 6.67 hours
Since time to reach maximum capacity will be before 7 PM, this will result in build-up of
significant truck inventory
Since berries arrive over a 12-hour window from 7 AM to 7 PM, 35 trucks with 2560 bbl of wet
berries will be waiting outside the plant at 7 PM. Post 7 PM, inventory will first reduce from the
waiting trucks at an inventory drawdown rate of 600 bbl/hr (Figure 1). (Exhibit 2)
Post 11:16 PM, when all the waiting trucks have been unloaded, drawdown of bin inventory will
begin at the same inventory drawdown rate of 600 bbl/hr (Figure 2). This will result in an
overtime of 9 hours 36 mins. (Exhibit 2)
Also area under the graph of truck inventory buildup = total waiting time = 163 truck hours
Hourly rate for leasing trucks = $100
Hence, cost due to additional wait time = $16,300
2000
1500
1000
500
0 11:00 AM
10:00 AM
12:16 AM
4:00 PM
1:00 PM
1:40 PM
3:00 PM
5:00 PM
6:00 PM
7:00 PM
8:00 PM
9:00 PM
3:16 AM
10:00 PM
7:00 AM
8:00 AM
9:00 AM
1:16 AM
2:16 AM
4:16 AM
4:36 AM
12:00 PM
11:16 PM
Inventory buildup bin
Truck inventory
3000
2500
2000
1500
1000
500
0
1:40 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 11:16
PM PM PM PM PM PM PM PM PM PM PM PM
Figure 2: Inventory build up in the trucks
ANALYSIS OF INVESTMENTS
1. Kiwanee dumper
Cost per dumper is $75,000. Each dumper has a capacity of 600 bbl/hr however with demand on
a peak day is only 1440 bbl/hr which can be easily fulfilled using 3 dumpers instead of 5. Since
one extra dumper can be used for breakdowns, adding an extra dumper was not a profitable
decision.
2. 1 or 2 new dryers
Also area under the graph of truck inventory buildup = total waiting time = 0.81 truck hours
Hourly rate for leasing trucks = $100
Hence, cost due to additional wait time = $81.09; Reduction of cost by 99.5%
3:00 PM
7:12 PM
1:00 PM
1:40 PM
4:00 PM
5:00 PM
6:00 PM
6:26 PM
8:12 PM
9:12 PM
7:00 AM
8:00 AM
9:00 AM
12:00 PM
10:12 PM
11:12 PM
0
6:26 PM 7:00 PM 7:12 PM
New overtime hours = Earlier overtime hours * Change = 12000 * 0.17 = 2040 hrs
Per hour overtime rate = $4.5/hr
New overtime cost = $4.5 * 2040 = $9180; Savings = $44,820
Inventory buildup bin
3000
2000
1000
0
Evaluation summary
Original State 1 new dryer 2 new dryer
Labour overtime cost 54,000 $23,760 $9180
Truck waiting cost $16,300 $81 0
Investment 0 $25,000 $50,000
Total cost $70,300 $54,835* $59,180
*Assuming truck waiting is incurred for 90 days of peak demand from Sept to December
NCC currently pays a premium of $0.5 per bbl for No. 3 berries. However, because of human
interventions, half of the berries marked as No. 3 were No. 2B in reality.
Introduction of light meter system will reduce the false positives and improve the yield.
Economic impact
Volume of No. 3 rated berries in 1970 = 450,000 bbl
Proportion of 2B berries in the above = 50%
Number of 2B rated berries = 225,000
Savings with installation of color grading = Savings per unit * Total number of units = 125,000
System cost = -$10,000
Since operator will replace chief berry receiver at the same pay grade, no change in wage cost.
Net savings = $125,000 -$10,000 = $115,000
CONCLUSION
Under the given conditions, NCC is incurring significant overtime costs as well as truck waiting
cost. The major bottleneck in the operation process is the drying process which has an implied
utilization of 180%. Truck waiting costs are also aggravated by the limited capacity of wet
berries storage bins (3200 bbl/hr), which is only 44% of overall bins storage capacity, despite
wet berries contributing to 75% of the demand.
Thus basis the analysis of multiple option, our recommendation is to to move ahead with
installation of 1 dryer which will reduce the overtime during peak hours by ~ 7 hours at an
additional investment of $25,000. Truck waiting cost will also be only $81/day during peak
months of September to December. Total cost is also minimized as compared to initial construct
and purchase of 2 new dryers.
Moreover, since demand will be highly variable during rest of the season, buying only 1 machine
will keep overall fixed costs in check and will ensure higher plant utilization
EXHIBIT 1
Utilization calculations
1. Kiwanee Dumpers
Using Little’s Law:
Capacity = 60* (1/average time to dump a truck) * # of dumpers * capacity of single truck
= 60 * 1/7.5 * 5 * 75
= 3000 bbl/hr
2. Bins
Dry Berries:
Wet Berries:
3. Destoning
4. Dechaffing
Dechaffing is done for both the dry berries as well as wet berries
Capacity of each dechaffing unit = 1500 bbl/hr
Total capacity = capacity/unit * # of bins = 1500 * 3 = 4500 bbl/hr
Demand for berries = 1440 bbl/hr
Thus Implied utilization = 1440/4500 = 32%
5. Drying
6. Separation
Separation is done for both the dry berries as well as wet berries
Capacity of each separation unit = 400 bbl/hr
Total capacity = capacity/unit * # of bins = 400 * 3 = 1200 bbl/hr
Demand for berries = 1440 bbl/hr
Thus Implied utilization = 1440/1200 = 120%
EXHIBIT 2
Truck
Time
inventory
1:40 PM 0
2:00 PM 160
3:00 PM 640
4:00 PM 1120
5:00 PM 1600
6:00 PM 2080
7:00 PM 2560
8:00 PM 1960
9:00 PM 1360
10:00 PM 760
11:00 PM 160
11:16 PM 0
EXHIBIT 3
Inventory build up rate = 280 bbl/hr
Inventory drawdown rate = 800 bbl/hr
Inventory buildup
Time bin
7:00 AM 0
8:00 AM 280
9:00 AM 560
10:00 AM 840
11:00 AM 1120
12:00 PM 1400
1:00 PM 1680
1:40 PM 1960
3:00 PM 2240
4:00 PM 2520
5:00 PM 2800
6:00 PM 3080
6:26 PM 3200
7:12 PM 3200
8:12 PM 2400
9:12 PM 1600
10:12 PM 800
11:12 PM 0
Truck
Time
inventory
6:26 PM 0
7:00 PM 159
7:12 PM 0
EXHIBIT 4
Inventory build up rate = 240 bbl/hr
Inventory drawdown rate = 1200 bbl/hr
Inventory buildup
Time bin
7:00 AM 0
8:00 AM 160
9:00 AM 320
10:00 AM 480
11:00 AM 640
12:00 PM 800
1:00 PM 960
1:40 PM 1120
3:00 PM 1280
4:00 PM 1440
5:00 PM 1600
6:00 PM 1760
7:00 PM 1920
8:00 PM 720
8:36 PM 0