demand? The demand for a finished product, such as laptop, car, table, or chair is known as Independent demand. On the other hand, the demand for a unit assembled separately or component parts that is used for designed to be incorporated with other units into a finished product is called Dependent demand. MRP or material requirements planning is used to compute dependent demand. MRP is important in dependent demand because it considers three questions that helps in computing the dependent demand, the what is needed, when is it needed, and how much is needed. Not only the quantities of each component parts needed but it also considers the lead times needed to produce and receive the items.
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 40 Material Requirements Planning