Professional Documents
Culture Documents
CUT-IN NOTE
ABSTRACT
In the oil and gas industry, the foundations of offshore platforms have, for decades, used the
grouted technique. This technology has now been transferred into the offshore wind turbine
industry. This paper gives details of the use of the technology in some of the first offshore
windfarms in Europe and considers future design possibilities.
1. INTRODUCTION
Offshore windfarms using the grouted junction technique, as a new and efficient method for wind
turbine foundations, include Bockstigen, Utgrunden, Blyth, Yttre Stengrund, Horns Rev, Samsoe,
North Hoyle, Arklow Bank, Kentish Flats and Barrow. At Utgrunden, Horns Rev, Samsoe, North
Hoyle, Arklow Bank, Kentish Flats and Barrow, grouted solutions have been used to connect the
wind turbine towers to the monopile foundation. At Bockstigen, Blyth and Yttre Stengrund the
technique is also used for connecting monopiles to the drilled rock socket at the seabed. Each
type of foundation has its own advantages, dependent upon location, soil condition and loading.
Fig 1 shows a range of foundation designs where grouting techniques have been used.
(a) (b)
Transition piece
with tower flange
Grout seal
Monopile
Figure 2: Connecting a wind turbine tower to a driven monopole with a grouted transition piece.
3. GROUT MATERIAL
The Ducorit® grout is based on the revolutionary concept DSP (Densified Systems with ultra-
fine Particles). DSP was optimized by Densit a/s as a result of many years of intense research
WE_29(5)_07-Moller 2/2/06 12:31 pm Page 465
Concrete
20 mm Concrete Concrete
313 g/m3 26×10–3 Densit
m2/sec 20
Densit Concrete Densit Concrete k ohm m
114 g/m3
Densit 5 mm 0.6×10–3 <0.1
Densit
1 mm 0 mm m2/sec k ohm m
in cement technology and fine particle packing. Today, it forms the basis of the unique
properties of all Ducorit materials which have been used successfully to install approximately
199 wind turbines offshore.
Among the properties which make the material ideal for such connections are:
4. DESIGN CONSIDERATIONS
(a) Practical Sizing and Installation
• Minimum grout gap: 25 mm.
• Maximum grout gap: due to low heat of hydration; generally there is no limit.
WE_29(5)_07-Moller 2/2/06 12:31 pm Page 466
• Transition piece overlap length on existing projects (1.33 to 1.5) x (pile Outer
Diameter).
Until now the transition pieces have been centred in the top and the full adjustment have been
done by tilting the transition piece around the top of the Monopile. Thereby the grout gap
increases with increasing pile diameter if an adjustment of 0.5 to 1.0 degree is maintained.
Increasing the grout gap increases both the demand on grout-seal performance, and the cost,
since the grout volume increases with (diameter)2. The sketches in Fig 3.1 demonstrate ways
of reducing grout volume.
1 2 3
1 2 3a 3b
Ground
D Load beam
Figure 4: Plan of the deck-assembly for the offshore wind farm ship, A2SEA to carry 10 transition
pieces.
Figure 5: Possible MP1 Resolution deck layout for 6 monopiles and transition pieces.
3101 5951
1311
4611
6162
3511
2251
3211
4726
2111
A A
9453
14179
Snit A-A
510
5810
4801
111
510
8648
2111
10.00
0000-
Figure 6: Design for a multiple-pile structure in concrete, made by the Danish Utility ENERHI E2.
6. CONCLUSIONS
The installation of offshore windfarms is progressing at an accelerating rate, with experience
being gained in several European countries. Obviously, the foundations are distinctive
features compared with onshore installations. This paper has reviewed the properties and
experience of grouted joints enabling such foundations. The methods have been successful,
and there is every indication of continued use as the industry expands.
REFERENCES
Morten S. Andersen and Petter Petersen, Structural Design of Grouted Connection in Offshore
Steel Monopile Foundations., Det Norske Veritas (DNV).
Det Norske Veritas, DNV-OS-J101, offshore Standard: “Design of Offshore Wind Turbine
Structures Draft, February 2004, DNV.
Tech-wise A/S (now Elsam Engineering A/S Model Tests of Grouted Transition Piece for the
Horns Rev Turbines,), 2001-08-22.
Strengthening of Offshore Steel Components Using High-Strength Grout: Component Testing
and Analytical Methods. OTC paper OTC 13192.
Fatigue characteristics, Technical Report, European Union EUREKA-Project, Contract
EU264–COMPRESIT, Sub-task 1.9.