Professional Documents
Culture Documents
m
er as
Cost
Category
1987
Estimate
1994
Actual
%
co
(£
million)
(£
million)
Change
eH w
Tunneling
(Target
costing
works)
1,329
2,110
59%
o.
Terminals
and
fixed
equipment
(lump
sum
works)
1,136
1,753
54%
rs e
Rolling
stock
(procurement
items)
245
705
188%
ou urc
Bonuses
and
contingency
46
-‐
Direct
and
additional
works
230
-‐
Total
construction
costs
2,719
4,844
79%
o
aC s
ar stu
The
Eurotunnel
was
unable
to
make
a
profit.
No
profit
was
generated
from
the
start
of
operations
in
1994
-‐
2007.
The
costs
of
the
tunnel
were
simply
too
high.
sh is
• Schedule
Construction
began
in
December
1987
with
operations
targeted
to
begin
in
May
1993.
Although
freight
services
started
in
June
1994,
passenger
service
didn’t
Th
begin
until
December
1994.
Delays
in
obtaining
operations
certificates
for
all
four
kinds
of
services
resulted
in
19
months
of
delay,
29%
longer
than
the
original
project
schedule
of
66
months.
• Quality
Several
specifications
were
weakened
to
a
lower
level
of
performance
during
construction.
The
maximum
speed
in
the
tunnel
was
reduced
with
a
resulting
increase
in
travel
time;
the
capacity
of
the
tunnel
was
reduced
as
well
(p.
8
of
the
case).
There
were
many
“optimization”
compromises
that
caused
the
Eurotunnel’s
operating
costs
to
go
up
(p.
9
of
the
case).
These
are
indications
that
the
original
specifications
were
not
all
met,
meaning
that
quality
was
compromised.
https://www.coursehero.com/file/26992649/Eurotunnel-Eyes-Wide-Shut-HW-answerspdf/
1
2. What
were
the
reasons
for
the
Eurotunnel
project's
performance?
In
particular,
what
roles
did
technical
and
market
uncertainty
play?
Technical
uncertainty:
Technical
uncertainty
was
considered
to
be
insignificant
–
a
point
made
in
the
CTG-‐FM
proposal
–
due
to
the
belief
that
ground
conditions
-‐
the
geology
and
water
conditions
through
which
the
Eurotunnel
had
to
be
bored
-‐
were
favorable
and
well
understood.
CTG-‐FM
believed
that
it
had
proven,
dependable
tunneling
methods
and
would
not
be
challenged
by
the
straight-‐
forward
design
of
the
Eurolink.
It
turned
out
that
there
were
technical
risks
–
e.g.,
cleft
rock
that
enabled
water
to
flow
into
the
area
that
was
being
bored,
causing
wet
ground
on
the
UK
side.
This
required
changes
to
the
technology
of
the
tunnel
boring
machines,
resulting
in
unexpected
increases
in
specifications
and
costs.
The
technology
of
the
French
boring
m
er as
machines
was
inappropriate
for
boring
through
water,
resulting
in
start-‐up
delays
and
co
unnecessary
expenses.
Both
sets
of
technical
risks
could
have
been
better
managed
using
risk
eH w
management
methods,
which
would
have
led
to
fewer
delays
and
lower
unforeseen
expenses.
o.
Market
uncertainty:
rs e
ou urc
Eurotunnel’s
continued
inability
to
turn
a
profit
also
could
have
been
caused
by
market
uncertainty.
When
Eurotunnel
started
operations,
the
channel
ferry
contractors
merged
and
o
started
much
more
aggressive
pricing.
In
addition,
low-‐fare
airlines
started
flying
between
the
aC s
UK
and
continental
Europe
during
the
1990s.
Also,
the
high-‐speed
link
from
Dover
to
London
vi y re
million
(in
1987
prices)
for
2003,
which
was
pretty
close
to
the
1987
revenue
estimate
with
ar stu
inflation
figured
in.
(The
UK
consumer
price
index
from
1987
to
2003
was
~
25%
per
year.)
So
it
appears
that
market
uncertainty
didn’t
cause
the
Eurotunnel’s
inability
to
achieve
a
profit.
sh is
3. What
else
could
affect
the
Eurotunnel's
ability
to
turn
a
profit?
Th
Debt.
The
source
of
the
Eurotunnel’s
inability
to
turn
a
profit
was
its
disproportionate
debt
load.
The
original
plan
predicted
that
debt
servicing
would
represent
79%
of
total
cost
(see
the
top
of
page
5
in
the
case).
Supporting
this
level
of
debt
servicing
would
require
an
operating
margin
of
44.1%
-‐
somewhat
unrealistic
in
the
transportation
industry.
The
profitability
problem
was
due
to
competing
interests
of
the
various
parties
involved
in
the
original
1985
bid.
Exhibit
5
in
the
case
shows
the
interests
and
contractual
obligations
that
https://www.coursehero.com/file/26992649/Eurotunnel-Eyes-Wide-Shut-HW-answerspdf/
2
controlled
the
relationships
of
the
most
important
players
in
the
Eurotunnel
project.
These
different
relations
caused
the
parties
to
compete
rather
than
cooperate
with
each
other:
banks
wanted
to
get
their
money
back
(from
their
loans)
with
interest;
shareholders
wanted
operating
profit
and
a
high
share
price;
the
Trans
Manche
Link
(TML)
that
constructed
the
tunnel
wanted
to
make
a
profit
on
its
construction;
and
the
Eurotunnel
itself
wants
to
make
money
owning
and
operating
the
tunnel
for
the
next
50
years.
Given
the
enormous
amount
of
debt
the
Eurotunnel
had
incurred,
not
all
of
these
goals
could
be
satisfied.
4. Describe
the
interests
and
obligations
(i.e.,
contract
structures)
between
the
Eurotunnel
and
the
banks
and
the
Eurotunnel
and
TML.
Eurotunnel
and
the
Banks
m
er as
The
banks
were
initially
reluctant
to
invest
in
the
financing
of
the
Eurotunnel,
realizing
that
the
co
project
had
many
risks.
As
a
result,
the
banks
were
determined
to
structure
the
equity
and
loan
eH w
agreements
in
order
to
secure
maximum
protection.
This
had
direct
and
measurable
effects
on
o.
the
project
and
on
Eurotunnel’s
later
operations.
Loans
were
structured
so
that
Eurotunnel
rs e
bore
all
interest
risk
and
had
to
pay
fees
each
time
changes
were
negotiated.
As
a
result,
ou urc
financing
fees
and
costs
exploded,
adding
to
the
Eurotunnel’s
debt
load
directly
and
exacerbating
its
formidable
challenge
of
achieving
profitability.
o
Facing
a
total
accumulated
financing
need
of
about
₤10
billion
by
mid-‐1994,
the
Eurotunnel
had
aC s
to
raise
cash
both
from
shareholders
and
banks,
and
then
completely
restructure
its
debts
in
vi y re
July
1997.
Even
after
this
financial
restructuring,
the
Eurotunnel’s
debt
was
too
high
to
allow
the
firm
operating
it
to
recover.
Banks
maneuvered
to
retain
their
bargaining
power
in
subsequent
restructuring
negotiations
so
that
they
could
exact
as
many
of
the
tunnel’s
future
operating
revenues
as
possible.
The
banks
did
this
to
avoid
a
costly
(for
them)
bankruptcy.
ed d
ar stu
Eurotunnel
and
TML
sh is
The
building
contractors’
priority
was
to
derive
a
profit
from
the
construction
contract
and
to
shed
as
much
risk
as
possible.
The
investment
made
by
the
building
contracting
companies
in
Th
TML
were
negligible
compared
to
the
revenues
they
could
derive
from
the
construction
work.
Losing
their
stake
in
TML
was
thus
a
relatively
minor
risk.
There
are
two
types
of
cost
reimbursement
contracts:
one
with
a
fixed
“management
fee”
and
one
with
“cost-‐plus-‐effort
percent”
reimbursement.
The
logic
behind
both
is
that
the
contractor
doesn’t
influence
key
design
decisions
but
only
coordinates
them
and
should
be
protected
from
cost
risks.
A
cost-‐plus
contract
was
used
for
rolling
stock
in
the
Eurotunnel
project.
Cost-‐plus
contracts
are
appropriate
only
if
the
client
(in
this
case
Eurotunnel)
is
very
familiar
with
the
work
to
be
done
and
can
judge
the
appropriateness
of
every
step,
since
the
contractor
receives
a
“volume
fee”.
Eurotunnel
wasn’t
knowledgeable
about
rolling
stock
and
https://www.coursehero.com/file/26992649/Eurotunnel-Eyes-Wide-Shut-HW-answerspdf/
3
this
handicapped
its
supervisory
ability.
Trans
Manche
Link
(TML)
was
reluctant
to
get
involved
in
this
kind
of
work
since
they
had
the
least
expertise
in
this
particular
facet.
However,
the
banks
wanted
one
party
(TML)
to
take
overall
responsibility
for
delivering
the
entire
project.
The
procurement
contract
was
a
compromise,
which
enabled
TML
to
avoid
cost
risks
on
the
procurement
of
the
rolling
stock.
A
combination
of
TML’s
lack
of
expertise
and
discharge
from
responsibility
inevitably
led
to
uncontrolled
cost
increases.
A
cost-‐plus
contract
was
not
the
right
type
of
procurement
contract
for
the
rolling
stock.
5. What
kind
of
support
did
the
British
&
French
governments
and
IGC
give
the
Eurotunnel?
In
1987,
just
after
its
formation,
the
Eurotunnel
claimed
that
the
schedule
imposed
by
the
British
Government,
from
its
inception
to
the
granting
of
Royal
Assent
to
the
Bill,
was
ridiculously
tight
for
a
project
of
its
enormity
and
importance.
The
tunnel
project
was
politically
m
er as
driven;
it
was
supported
by
two
governments
with
very
different
philosophies
on
infrastructure
co
projects.
Both
governments
wanted
the
project
to
succeed
and
did
support
the
initial
eH w
financing,
but
the
commitment
of
the
French
government
was
stronger.
While
the
French
o.
government
built
a
high-‐speed
rail
link
between
Paris
and
Calais,
the
British
government
rs e
cancelled
its
planned
link
(which
lengthened
the
travel
time
from
Paris
to
London
by
one
hour),
ou urc
and
did
not
build
it
until
November
2007.
Again,
the
respective
interests
of
the
key
drivers
of
the
project
were
not
fully
aligned
with
the
success
of
the
project.
o
The
supervising
body,
IGC,
did
not
unambiguously
support
the
project
either—slow
decision-‐
aC s
making
and
opaque
project
requirements
added
to
the
project’s
costs.
vi y re
6. Would
it
have
made
sense
to
stop
the
project?
What
could
have
been
done
differently?
ed d
It
might
have
made
sense
to
stop
the
project
but
it
would
have
been
necessary
for
the
ar stu
Eurotunnel
managers
to
have
recognized
the
constant
escalation
in
project
costs
early
on.
Also,
there
was
probably
too
much
at
stake
for
the
governments
involved
to
stop
the
project.
The
Eurotunnel
had
a
strong
political
objective
and
perhaps
for
different
reasons,
neither
the
sh is
British
nor
the
French
would
accept
the
loss
of
face
from
pulling
out
of
the
project.
The
ideal
of
Th
European
unification
promoted
the
project
and
contributed
to
the
Eurotunnel’s
continuation.
What
Could
Have
Ben
Done
Differently?
The
need
for
an
initial
win-‐win
deal
and
the
ability
to
work
through
unexpected
(but
inevitable)
changes
in
long-‐term
projects
requires
that
the
contracts
be
rooted
in
an
overarching
business
approach
and
business
relationship
that
includes
transparency
and
a
fair
process
for
managing
changes
that
will
inevitably
occur
in
a
project
of
this
magnitude.
The
process
begins
with
the
choice
of
contracting
partners.
Traditionally,
the
norm
in
the
construction
industry
has
been
to
https://www.coursehero.com/file/26992649/Eurotunnel-Eyes-Wide-Shut-HW-answerspdf/
4
select
the
contractor
on
price
alone.
But
choosing
a
contractor
based
on
track
record,
reputation
and
previous
working
relationships
is
a
much
better
predictor
of
project
success.
The
second
step
is
to
draw
up
a
contract
as
a
business
deal,
which
specifies
value
for
both
parties,
explicitly
allocates
risks
(neither
hiding
them
nor
politically
ignoring
them),
and
leaves
flexibility
for
changes,
according
to
an
agreed-‐upon
governance
structure
and
an
attitude
of
collaboration.
Third,
the
process
must
address
the
inevitable
changes
that
characterize
uncertain,
complex
and
long-‐term
projects.
If
changes
are
made
transparently,
with
the
possibility
for
all
sides
to
be
heard
and
explicitly
discuss
trade-‐offs,
the
changes
have
a
higher
chance
of
succeeding
and
keeping
all
parties
on
board.
This
includes
early
warning
systems,
which
make
potential
changes
visible
earlier
(allowing
more
time
to
react)
and
also
make
the
changes
equally
visible
to
everyone
involved.
Ultimately,
this
process
helps
to
build
relationships,
which
are
the
first
m
er as
safeguard
against
opportunistic
behavior.
co
eH w
The
Eurotunnel
project
blatantly
failed
to
build
these
kind
of
working
relationships
and
trust.
o.
TML
and
Eurotunnel
detested
each
other.
The
lack
of
trust
was
made
worse
by
the
two
very
rs e
different
management
cultures
present
in
the
project:
the
French
and
British
managers
did
not
ou urc
see
eye
to
eye
on
many
operational
decisions.
A
lesson
of
this
case
is
that
not
only
do
you
need
to
understand
your
customer’s
requirements
but
you
need
to
understand
your
business
partners
as
well.
Relationships
matter!
o
aC s
vi y re
ed d
ar stu
sh is
Th
https://www.coursehero.com/file/26992649/Eurotunnel-Eyes-Wide-Shut-HW-answerspdf/
5