Application Lifecycle Management

Prelim Q2

20/20

This cycle tests the new features with existing features that might have been impacted
by the changes.

Cycle 2-Integrated System Testing

_______are checkpoints on a release timeline used to verify that the release and its
interim deliverables are progressing as planned.

Milestones

Tests the performance of the application for criteria such as number of concurrent users
that the application supports and the response time of the application.

Cycle 3-Performance Testing

The Detailed tab enables you to select content to include in the release scope item.

False

If an application flaw is detected while running a test set, you can submit a defect. 

True

In the definition phase, the QA/project manager defines the scope, milestones, and
KPIs for the project in ALM.

False

When you assign a requirement to a cycle, the requirement is not automatically


assigned to the release.

False

A test set folder in the Test Lab module contains tests that are covered by your
requirements.

True

Tests the new features of the application implemented in the release.


Cycle 1-New Features

This cycle ensures that the new features meet the expectations of the business.

Cycle 4-User Acceptance Testing 

The testing process begins with defining defect in the Management module.

False

The Release Scope tab enables you to define and update release scope items.

True

You can not customize each KPI to reflect your needs

False

Displays the progress of a release in a Gantt chart.

Master Plan tab

______ are the means for setting objectives on Project Planning and Tracking releases
and for planning and tracking release progress towards these objectives throughout its
duration.

Thresholds

Cycle 2 can start before the end of cycle 1.

True

Displays KPI calculations that enable you to determine the status of your release.

Scorecard tab

Indicates whether the scheduled calculation is currently running

Active/Inactive

Milestones are used to measure progress in project planning and tracking.

True

After adding a cycle to a release, you specify the details for the cycle using the _____.

Details tab