GENERAL CONDITIONS OF CONTRACT

NOTE: Following Clause No. 72.0 and 73.0 shall not be applicable for
tender valuing upto ` 500 Crore (Rupees Five Hundred Crores)

72.0 CLAIMS

72.1 Monthly Statement of Claims:

The contractor shall prepare and furnish to the


Engineer once in every month an account giving full
and detailed particulars of all claims for any
additional expenses to which the Contractor may
consider himself entitled to and of all extra or
additional works ordered by the Engineer which he
has executed during the preceding month and no claim
for payment for and such works will be considered
which has not been included in such particulars.

Non-receipt of statement of claims shall be


construed that contractor has 'no claim'.

72.2 Signing of “No Claim” Certificate:

The contractor shall not be entitled to make any


claim whatsoever against IRCON under or by virtue of
or arising out of this contract, nor shall IRCON
entertain or consider any such claim, if made by the
Contractor, after he shall have signed a “No Claim”
Certificate in favour of IRCON in such form as shall
be required by IRCON after the works are finally
measured up. The Contractor shall be debarred from
disputing the correctness of the item covered by “No
Claim” Certificate.
The “No Claim Certificate” furnished by the
contractor shall be treated as the “Discharge
Certificate” by the contractor, which discharges the
Employer from all liabilities under the contract.
73.0 SETTLEMENT OF DISPUTES

All disputes and differences of any kind whatsoever


arising between the parties (Employer/ Engineer and
the Contractor) out of or in connection with the
contract, whether during the progress of the work or
after its completion and whether before or after the
determination of the contract, shall be settled as
under, provided that matters for which provision has
been made in clauses 20.3, 36.5, 40.1, 40.2, 49.7,
50.0, 51.0, 59.0, 61.0 and 72.0 of General
- 61 -