Successfully Implementing SAP S/4HANA – Part 4

Transition Road Maps for Upgrade of SAP S/4HANA and embedded products
Dr. Christoph Nake, SAP
Dr. Astrid Tschense, SAP
July, 2019
PUBLIC
Disclaimer

The information in this presentation is confidential and proprietary to SAP and may not be disclosed without the permission of SAP.
Except for your obligation to protect confidential information, this presentation is not subject to your license agreement or any other service
or subscription agreement with SAP. SAP has no obligation to pursue any course of business outlined in this presentation or any related
document, or to develop or release any functionality mentioned therein.
This presentation, or any related document and SAP's strategy and possible future developments, products and or platforms directions and
functionality are all subject to change and may be changed by SAP at any time for any reason without notice. The information in this
presentation is not a commitment, promise or legal obligation to deliver any material, code or functionality. This presentation is provided
without a warranty of any kind, either express or implied, including but not limited to, the implied warranties of merchantability, fitness for a
particular purpose, or non-infringement. This presentation is for informational purposes and may not be incorporated into a contract. SAP
assumes no responsibility for errors or omissions in this presentation, except if such damages were caused by SAP’s intentional or gross
negligence.
All forward-looking statements are subject to various risks and uncertainties that could cause actual results to differ materially from
expectations. Readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of their dates,
and they should not be relied upon in making purchasing decisions.

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 2


Webinar Series

July
CW27 CW28 CW29 CW30
July 3rd July 10th July 17th July 24th

1hr Webinar 2: 1hr Webinar 3: 1hr Webinar 4: 1hr


Webinar 1: Transition Road Maps
Working with Transition to SAP
Introduction to for Upgrade of SAP
Transition Road Maps S/4HANA – Service
Transition Road Maps S/4HANA and
Offerings
embedded products
Get an introduction on Get a deeper insight how Learn about the service After a transition to SAP
transition road maps and to create a service plan, offerings from SAP and S/4HANA, you may
how they can support an work with the road map understand the linkage consider to move to
implementation or graphic and adapt the between road map and S/4HANA embedded
transition project from project file template in SAP services. products like from LE-
first considerations until SAP Solution Manager or Get answers to the WM to SAP EWM, or LE-
realization MS Project following questions: TRA to SAP TM, or SAP
What are the service CRM to S/4HANA
Focus: Find information using offerings for Standard Customer Management.
SAP S/4HANA on prem the accelerators, filters Support customers? Learn which road maps
and search functionality What about Enterprise and services are already
Focus: Support Customers? available.
Target Group: SAP S/4HANA on prem What is premium
IT Management, CoE engagement? What Focus:
Leads, Project Managers Target Group: can I get with my type SAP S/4HANA on prem
Project Managers, of contract? Target Group:
Project Team, TQMs
IT Management, CoE
Target Group: Leads, Project
IT Management, Managers
Project Managers

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 3


Transition Road Map for SAP S/4HANA Upgrade and embedded Products

Agenda

▪ Upgrade of SAP S/4HANA – Road Map and Services

▪ Product Integration in SAP S/4HANA – Example: SAP EWM embedded in SAP S/4HANA

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 4


Available Transition Road Maps (excerpt)
Road Map Scenarios embedded products
• New implementation
Transition to SAP S/4HANA • System Conversion
• Selective Data Transition
On prem

• Upgrade
• New implementation of embedded product • SAP EWM
SAP S/4HANA Upgrade and Product Integration
• Transition to embedded product • SAP TM
• SAP S4CM
• New implementation
• System Conversion (in-place/shell/remote)
Transition to SAP BW/4HANA
• New implementation of embedded product • SAP BPC 11.0
• Transition to embedded product
SAP Activate Methodology for Business Suite and On- • methodology
Premise- Agile and Waterfall
SAP Activate Methodology for New Cloud • methodology
Implementations (Public Cloud-General)
SAP Activate Methodology for SAP S/4HANA Cloud • transition
Cloud

SAP Activate Methodology for SAP S/4HANA Cloud • transition


(single tenant edition)
SAP Activate Methodology for Success Factors • transition

Implementation of SAP Analytics Cloud • transition

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 5


Upgrade of SAP S/4HANA
Run a pure technical upgrade, or implement new features or embedded products?

SAP S/4HANA is currently available on release 1809 FPS02


Check the help.sap.com landing page for SAP S/4HANA

For every release/FPS, a Feature Scope Description is


available, explaining which features are provided up to this
release of SAP S/4HANA

SAP and Partner Solutions (on


Premise and Cloud) with
integration to SAP S/4HANA

SAP S/4HANA LoB Products


embedded in SAP S/4HANA,
add. license required

Core processes in SAP S/4HANA

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 6


Upgrading SAP S/4HANA
Transition Paths Overview

System conversion from SAP S/4HANA Finance to SAP S/4HANA

Upgrade within the SAP S/4HANA product family

SAP S/4HANA upgrade to release 1709 and 1809 with upgrade


from SAP HANA 1.0 to SAP HANA 2.0 :

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 7


Upgrading SAP S/4HANA - Road Map Structure Picture

For a pure technical upgrade, only a sub-set of


the S/4HANA implementation road map
activities are relevant.
The activation of new features may require
additional activities!
➢ Adapt the structure slide to your project
requirements
➢ Consider:
➢ Which activities are required for the planned
scenario?
➢ Which activities are missing for the activation of
new features? Check against the picture from
the "Transition to SAP S/4HANA" road map
➢ Adapt activity sequence, if required

The road map structure picture ppt is available for download in the Road Map Viewer „Download Project Plan“

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 8


Roadmap Viewer: Tasks and Tools

SAP Transformation Navigator


SAP Innovation Discovery Finder
S/4HANA – What’s New Viewer

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 9


Roadmap Viewer: Tasks and Tools

Simplification Item Catalog

SAP Note 2399707 - Simplification Item Check

The Simplification Items Check can be used as of target


SAP S/4HANA 1709 and needs to be run on the source system
(SAP Notes 2399707 and 2502552)
SAP Blog: SAP S/4HANA Simplification Item Check – How to do it right
The Simplification Item Catalog provides a description of all relevant changes
from a source product/release to a target product/release

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 10


Tasks and Tools

Software Logistics Toolset Landing Page


Maintenance Planner

SAP Note 693168 - Minimized Downtime Service (MDS)


Upgrade Guide for SAP S/4HANA 1809

ABAP Test Cockpit (ATC)


Custom Code Migration Guide

SAP Note 2469025 – How-To: Upgrading to SAP HANA 2.0

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 11


Services for Upgrade of SAP S/4HANA

▪ Learn how SAP services are mapped to road map


activities
Consider:
➢ Should SAP support in the planning and design?
➢ Is the execution done by customer/partner or by an SAP
service?
➢ Should the Safeguarding be done by SAP?
➢ Transfer the decision on services to a
service plan

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 12


Upgrade of SAP S/4HANA with enhancements – Service Components

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 13


Transition Road Map for SAP S/4HANA Upgrade and embedded Products

Agenda

▪ Upgrade of SAP S/4HANA – Road Map and Services

▪ Product Integration in SAP S/4HANA – Example: SAP EWM embedded in SAP S/4HANA

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 14


Product Integration in SAP S/4HANA – Example: SAP EWM

SAP Extended Warehouse Management Product Road Map


SAP S/4HANA Suite 1809 and planned new /changed functionality for SAP EWM in release 1909

EWM
standalone

embedded
EWM with
license

Basic Warehousing or
Stock room management,
no EWM license required

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 15


Product Integration in SAP S/4HANA – Road Map
Example: SAP Extended Warehouse Management embedded in S/4HANA

Create an Innovation Strategy and a high-level Road Map for


SAP EWM → Advisory Service transition WM to SAP EWM

Identify the Impact of the implementation of SAP EWM on


existing processes → Business Assessment Service for
SAP EWM

Define the Implementation Strategy for SAP EWM → Value


and Implementation Strategy Workshop (VIS) with special
focus on EWM

https://go.support.sap.com/roadmapviewer → SAP S/4HANA Upgrade and Product Integration Roadmap


Filter for the Product you want to integrate in SAP S/4HANA (SAP EWM, SAP TM,SAP S4CM, more to come)
© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 16
Product Integration in SAP S/4HANA
SAP EWM embedded in S/4HANA – Service Components

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 17


Project File Template for Upgrade and Product Integration
Download the Project In the Flavors Check which tasks
Add activities, tasks Assign resources to
Plan zip file, open the column, open the /subtasks are not
and planned all subtasks
Project Plan for MS column header menu relevant for your project.
services.
Project and add the and select all Select the line of the All tasks/subtasks
planned project start checkboxes respectice task/subtask Adapt the durations are explained with
date under containing your and open the context of the tasks, where the roadmap texts in
File>Info>Project planned transition menu. Choose appropriate. the notes section
Information scenario „Inactivate Task“. (column 1)

Result: Result: Result: Result: Result:


The project end date is Only the tasks and The selected tasks/subtasks You align th project plan You can check the
calculated automatically subtasks required for your are inactivated and the with the service plan and availability of the required
and earliest start dates scenario are displayed dependencies are re- add reasonable timelines resources, resource
of all tasks and subtasks and all dependencies are arranged. and check the service flow usage and assignment
are set re-arranged. Note: This inactivation can be conflicts
reverted, if necessary

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 18


Summary

➢ The Upgrade of SAP S/4HANA is decribed in the Road Map „SAP S/4HANA Upgrade and
Product Integration“

➢ The transition to SAP S/4HANA-integrated products is currently described for:


SAP EWM, SAP TM, SAP S4CM (tbc.)

© 2019 SAP SE or an SAP affiliate company. All rights reserved. ǀ PUBLIC 19


Thank you.
Contact information:
Dr. Christoph Nake
Chief Support Engineer
christoph.nake@sap.com

Dr. Astrid Tschense


Expert Support Engineer
astrid.tschense@sap.com
Follow us

www.sap.com/contactsap

© 2018 SAP SE or an SAP affiliate company. All rights reserved.


No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of
SAP SE or an SAP affiliate company.
The information contained herein may be changed without prior notice. Some software products marketed by SAP SE and its
distributors contain proprietary software components of other software vendors. National product specifications may vary.
These materials are provided by SAP SE or an SAP affiliate company for informational purposes only, without representation or
warranty of any kind, and SAP or its affiliated companies shall not be liable for errors or omissions with respect to the materials.
The only warranties for SAP or SAP affiliate company products and services are those that are set forth in the express warranty
statements accompanying such products and services, if any. Nothing herein should be construed as constituting an additional
warranty.
In particular, SAP SE or its affiliated companies have no obligation to pursue any course of business outlined in this document or
any related presentation, or to develop or release any functionality mentioned therein. This document, or any related presentation,
and SAP SE’s or its affiliated companies’ strategy and possible future developments, products, and/or platforms, directions, and
functionality are all subject to change and may be changed by SAP SE or its affiliated companies at any time for any reason
without notice. The information in this document is not a commitment, promise, or legal obligation to deliver any material, code, or
functionality. All forward-looking statements are subject to various risks and uncertainties that could cause actual results to differ
materially from expectations. Readers are cautioned not to place undue reliance on these forward-looking statements, and they
should not be relied upon in making purchasing decisions.
SAP and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered
trademarks of SAP SE (or an SAP affiliate company) in Germany and other countries. All other product and service names
mentioned are the trademarks of their respective companies.
See www.sap.com/copyright for additional trademark information and notices.