Professional Documents
Culture Documents
INSTITUTE OF ENGINEERING
PULCHOWK CAMPUS
Assignment Report
On
Procurement Management
Termination of Contract
(5) Where a procurement contract has been terminated pursuant to Sub-section (4), the Public
Entity shall have to pay the value for the following work that has been completed prior to the
termination of the said contract: -
(a) Payment due under clause (a) of Sub-section (2),
(b) Where expenditure is to be paid on reimbursement basis, such expenditure as
actually incurred.
(c) The price of the goods specially manufactured for the Public
Entity under the procurement contract,
(d) Excluding the lost profit and the amount under clause (c) of
Sub-section (3), the expenditure incurred for termination of the procurement contract,
and
(e) Other expenditure as prescribed.
The Section (59) of the act, hence defines and addresses all the possibilities of contract
termination that shall have to be specified in the procurement contract, and also in some
special grounds, provides ways to terminate the contract, arising in special situations.
It is clear from the Section of the act that the termination of the contract can only get legality
when so is justified under various occurrence of events. It could be either when the parties get
freed from their responsibility to deliver the required goods and services that the Public
Entity recognizes and verifies and completes the payment, as mentioned in the contract.
The termination could be from one of the sides best suited for their interests as within the
limitation provided by the act. It could also be due to the occurrence of disaster like
landslides, earthquakes or engagement in war, and is within the clause (d) of the Sub-section
(2) as force majeure.
The outcome of such terminations, when the works are not completed, may raise disputes
between the parties, in financial issue, due to loss incurred on either side. The loss should be
compensated well to the respective party. When the works are completed, the required
payment is to be made to the procured party. This is defined as per the Sub-section(3).
Sub-section (4) gives rights to the Public Entity to terminate, even if the cause of termination
is not mentioned in the contract agreement, if the works is causing against the best interest of
the public, and subsequently, Sub-section(5) makes the Public Entity responsible for the
value of the completed work to the other party.
References:
Public Procurement Act, 2063
Purchasing Principles and Management, Peter JH Baily
Consequences of termination of public procurement contracts, Kesikli Law Firm, Turkey.