PROJECT UPDATE

AUGUST 14TH, 2020

IML LABELS
COLOMBIA
The installation of the mezzanine
equipment has begun.
All the plumbing (drains) of 2nd floor (mezzanine level)
are completed.
Panel wall that
divides loading
zone from
warehouse
Fire Sprinkler Progress
Window installation of main Façade
Last layer of granular base with cement mix
for the area that won’t have a concrete finish
Planting the green surface that eventually will cover
up the retaining wall
That is how the granular base will be by the
dirt compaction wall of the west façade
North Façade, you can
see the extra width of
the road access as well
as the electrical vaults
for sub-station hook ups
SUMMARY

• The Industrial Park people, have started to work on the main road access and MEP around
the entrance and IML lot, their goal is to be ready with all at the same time that IML
warehouse be completed.

• Adolfo has greatly coordinated the installation of the mezzanine equipment to have it ready
at required time frame.