You are on page 1of 7

Ammonium Nitrate

by the
Stengel Process
J. J. DORSEY, JR.l
Contnrerdol S d m b C-, SMIngtOn, Lo

I N THE summer of 1951, Commercial Solvents Corp. decided


to embark on a $ZO,Mhl,Mhl expansion of its Sterlington, La.,
plant. This expansion was to include increased production of
an important factor in the design of a solid ammonium nitrate
plant, since many of them are located in the Sonth where humid
weather conditions may seriously deet the output from the
ammonia and methanol and new facilities for producing solid dryers of a conventional plant. A brief comparison of the major
ammonium nitrate. Since a preliminary cost survey indicated components of the several processes is given in Table I.
that the Commercial Solvents ammonium nitrate process (8)
should result in the lowest investment and production cost, it was
necessary to obtain detailed design data from 8 pilot plant for
a large plant. Tentatively, June 1952 was the deadline for ob- Table I. Comparison of Ammonium Nitrate Processes
taining enough information on the process to allow a detailed en- commercis1
s01venta corp.
gineering comparison of the Commercial Solvents process with 0Lleration (stengel) Prilling OslolKryatal(6)
competitive processes and for at least a preliminary evaluation Preheatkg YeS NO NO
of the pilot plant product. Neutralization YeS YW Yea
The building, reaction equipment, and wster-cwled conveyor
installation were completed hy January 1952 By March 1952,
b$$E;
EvapO?StiOn

,sation
NO
NO
NO
Yes
Yes
NO
YB.
NO
YW
NO
NO
YeS
Flaking and aooling Ye. NO NO
it was apparent that additiond handling equipment would be Grinding Yea NO NO
necessary. Accordingly, two small dryers, product screens, Dniw NO YW Yea
Cwling NO Yea NO
and several conveyors were procured. A coating drum waa c1aasifioatlon Ye* YeS Ye*
Costing and bagging Yea Yea Ye8
fabricated, and a sewing machine for sewing filled bags was ob-
tained. Throughout April, May, and June of 1952, the complete
pilot plant wm operatad on a threeahift basis a t a production
rate of about 300 pounds per hour. The pilot plant waa operated In conventional prilling ammonium nitrate processes (7), the
in order to obtain additional information and to train production control of the particle size from the prilling tower is a function
personnel through May 1953. The required design information of the properties of the solution of ammonium nitrate such m
was obtained during 1952, to allow the construction of the plant concentration and temperature, the type of spraying equipment,
to proceed during 1953. The production plant waa completed and the characteristics of the tower. The final product moisture
in August, 1953, and has been operating since that time (3). level depends on the operation of two or three rotary vessels
functioning &B dryers and/or a cooler. The atmospheric condi-
In Stengel Process, Control of Producl tions, temperature, and humidity affect the capacity of the prill-
Moisture Is Independent of Climate ing tower and the dryers.
In the Commeroial Solvents process the control of the product
In this process, preheated ammonia and nitric acid react in a moisture o m be by the conditions maintained in the reaction sys-
packet reactor, as described for the patented Stengel reaction tem. This is a function of the preheating of the reactants and
system (8). The reactants are preheated ta a sufliciently higb
the operation of the stripper, which uses air to reduce further the
temperature that the molten ammonium nitrate leaving the reac- product moisture to the d&d level. This operation readily
tion system will be at the desired moisture level. This may be lends i h l f to automatic control. Since the moisture content of
as low as 0.1%. From the reactor, the mixture of steam and the ammonium nitrate is established in the reaction system, the
ammonium nitrate passes to a cyclone-type separator where a outside weather conditions have no effect on the product moisture.
separation of the molten ammonium nitrate and steam results.
The steam is taken to a total condenser and sewered. The molten
Pilot Plant Components A m
ammonium nitrate p " to ~ the stainless steel, water-bed con- Equipped for Automatic Control
veyor where it solid3ies aa a continuous sheet. This sheet of am-
monium nitrate is broken into about 5-mesh particles. This The pilot plant waa located about one-half mile from the am-
product is dried, cooled, and classilied into a -5 to +20 mesh monia plant, the nearest major production unit. Steam, water,
mixture before paesing on to coatmg and bagging equipment. power, and air were brought to the area from the plant supplies.
Provisions are incorporated for recovering fines from the screen Ammonia and nitric acid were brought to the pilot plant by
and other possible loasea in the process. portable trailers which were filled a t available facilities in the
The Commercial Solvents solid ammonium nitrate process production plant.
offem a simple method of producing a dry product without a The pilot plant building waa of prefabricated steel construction
prilling tower, crystalher, or dryers and coolers, thus d o r d i n g a placed on a concrete slab. No special Boor was supplied and
process that is essentially independent of the weather. This is attack on the concrete was negligible except where hot nitrate
frequently drained. The building was 20 feet wide by 48 feet
L h n t addrar. O h Mathiason Chemical Corp., New Haven. Conn. long, and the reaction equipment was housed in a special barricade.

I a n m 1955 INDUSTRIAL AND ENGINEERING CHEMISTRY u


ENGINEERING, DESIGN, AND PROCESS DEVELOPMENT

n
REACTOR SECTION Non
-Condensables
I
I
I I I -
G o ndenser
Vapor
R e a c t or Scrubber
Ammoniq
Heater NI-lqN03- 18.2 Ib./hr.
H20-274.51b./hr.

-0
i am

7-

Ammonia
- From T r a i l e r
' '-
NH NO
-
7
616.2 Ib./hr.
H20-2755 ib/hr. Separator
S c r u b b e r Pum

Nitric A c i d
-
P r e-
heater

FINISHING SECTION

90lb./hr. O v e r s i z e R e c y c l e
C o a t i n g Agent S c r e w F e e d e r

H 2 0 % 0.1- 0.4
A c i d i t y , 0.04 0.06-
S c r e e n Analysis %

-5, i - 2 0 72.0
N q N 0 3 - 6.18 tons/doy
- 20 , 14.2
-
T e m p e r a t u r e -OF.

-0 Pressure - inches H2 0

a pressure Pounds per. sq.ini

Figure 1. Process Flow Sheet for Pilot Plant Production of Ammonium N i t r a t e

12 I N D U S T R I A L A N D E N G I N E E R I N G CHEMISTRY Vol. 47, No. 1


PILOT PLANT

Ammonia Storage, Metering, and Preheating. The ammonia stainless steel pipe about 5 feet long. This stripper was packed
from a 1000-gallon trailer passed successively through a vapor- with various types of packing t o various levels. The piping a t
izer, pressure controller, temperature controller, direct indicating the bottom of the stripper allowed for entry of the heated strip-
Flowrator, superheating equipment, and into the reactor (Figure ping air, and the discharge of the molten ammonium nitrate to
1). the Eastern Model D-11 centrifugal pump which pumped the
The ammonia vaporizing and superheating equipment were of molten ammonium nitrate to the water-cooled conveyor where it
standard carbon steel construction and were designed to use solidified.
available plant steam pressure of up t o 250 pounds per square inch The vapor scrubber was fabricated from a section of 8-inch
gage. While some tests were conducted utilizing ammonia stainless steel pipe. The scrubber was designed to recover the
superheated to over 450' F. with electric heaters, this proved t o ammonium nitrate and ammonia which escaped from the separa-
be unnecessary, and for most of the operation preheating to tor and t o cool the steam leaving the scrubber. Normally a
300" F. was adequate. packed height of 25 inches was employed. The scrubber a5-
Nitric Acid Storage, Metering, and Preheating. The nitric sembly consisted of a circulating pump, a hot well controlled to a
acid from a 2000-gallon stainless steel trailer passed either directly constant level by condensate addition, and a flowmeter in the
t o the Ingersoll Rand Type s/4 MCS centrifugal pump or first pump discharge system. A side stream was taken off t o the acid
through a scale tank. From the pump the nitric acid flowed charge tank for recovery.
through a direct indicating Flowrator and two acid heaters in Also in the pilot plant reaction assembly was a surface con-
series t o the reactor. denser used t o condense all the steam from the vapor scrubber.
Several types of nitric acid heaters were employed during the This condensate was weighed and analyzed to provide a measure
pilot plant operation. Generally, two heaters were employed in of the efficiency of the process.
series, The first heater contained a number of coils of stainless Water-cooled Conveyor. From the bottom of the stripper,
steel tubing within a carbon steel jacket. This heater was the molten ammonium nitrate was pumped to the water-cooled
operated a t less than 50 pounds per square inch gage steam pres- conveyor where solidification and cooling ocurred. The water-
sure and preheated the nitric acid to 250" F., if necessary. Prac- cooled, stainless steel conveyor was a standard 20-inch-wide belt
tically no corrosion of the tubing inside the heater resulted, but with a cooling section 18 feet long. This conveyor belt was modi-
corrosion of the welds joining the two heaters was a continuing fied t o allow belt speed variations from 0 to 85 feet per minute.
problem, although not serious enough to prevent operation of the For maximum water economy and heat transfer, water was cir-
pilot plant. culated through the two sections by a recycle pump until tht
The second heater initially employed to preheat the nitric acid water temperature reached a specified maximum. The cooled
above 260" F. was a Durco Series D4HF which is a standard sheet of ammonium nitrate was removed from the belt by a
Duriron heater. I t s principal disadvantages were its small size scraper and fed t o the product breaker and grinder which were
and low operating steam pressure limit of 75 pounds per square located at the discharge end of the water-cooled conveyor.
inch gage. This heatcr was replaced with a straight, jacketed Drying, Cooling, and Product Coating. It was initially thought
section of 1-inch, Schedule 40, Type 304 stainless steel pipe. t h a t it might be necessary to have a t least one dryer and a cooler,
This type of heater lasted over 1800 hours. In this equipment as in most conventional ammonium nitrate plants. I n this phase
corrosion also occurred primarily a t the zone adjacent to the weld- of the pilot plant study, a General American Transportation
of the top and bottom flanges. With this heater, acid preheat flight-type dryer, 12 inches in diameter by 9 feet long, and a
temperatures as high as 320' F. were used for short periods. Link-Belt Model 207, Roto-louvre dryer were both evaluated.
Except for brief periods during the experimental program, it was The installation was so designed that the product passed first
not necessary to have an acid preheat temperature much over through the flight-type dryer, and then into the Roto-louvre
290" F. It is entirely probable that some vaporization of nitric dryer, or into either dryer separately. The Roto-louvre dryer
acid occurred at times. could be operated as a cooler, but generally sufficient cooling de-
Control of the nitric acid preheat temperature was by manual veloped through the screens, and coating drum.
adjustment of a steam pressure regulator for each acid heater to The product coating was accomplished by adding coating agent
give the desired reactor gradient or temperature. and the classified ammonium nitrate to a rotating drum where
Reactor, Separator, Stripper, and Scrubber. Two different the tumbling coated the product. The coating agent was fed t o
types of operation of the pilot plant were explored-the operation the coating drum by a vibrating feeder or a screw feeder. The
leading t o the production of a n ammonium nitrate solution of 2 feeder was adjusted to discharge continuously a t a fixed rate to
t o 3% water content which required a dryer and cooler for subse- correspond to the known production rate. The product was
quent processing and, next, the operation to produce directly a bagged in conventional six-ply, moisture resistant bags for stor-
product of 0.2 to 0.4% water, thus eliminating the need for a dryer age and field trials. All bags were sewn and overtaped.
or cooler. The major differences between these two types of Grinding to Size and Product Classification. The grinding of
operation were the nitric acid preheat level and the use of a strip- ammonium nitrate to a product passed through 5 mesh and re-
ping gas to dehydrate further the ammonium nitrate. tained on 20 mesh screen with a minimum of fines was extensively
The reactor was fabricated from a 16-gage stainless steel tube, studied. Many factors influence the characteristics of the am-
2.5 inches in outside diameter by 8 feet long. Provisions were monium nitrate with regard to the production of fines. Among
made for entrance of the ammonia a t the side and nitric acid these are temperature, sheet thickness, aging time, and moisture
directly at the top. The reactor was packed with various sized content.
packing to a packed height of up to 7 feet. A thermocouple well As part of this study of grinding ammonium nitrate the follow-
extended through the center of the packing from the bottom. ing types of grinders were considered:
Reactor temperatures were measured in this center thermowell.
The separator, of conventional cyclone-type design, was fab- Corrugated roll, roller mill
ricated at CSC's Sterlington shops. The separator was 8 inches Several types of hammer mills
Several types of granulators
in outside diameter by 24 inches high. The steam-ammonium Several types of so-called choppers
nitrate mixture entered tangentially and the ammonium nitrate
flowed by gravity to the stripper below. The steam and non- Generally, the best results were obtained with a hammer mill
condensables left from the center discharge pipe and passed out or granulator, both of which are used in the production plant.
to the scrubber. A vibrating screen was employed for classifying the product.
The stripper was fabricated from a piece of 3-inch, Schedule 40 The screen was 2 feet wide by 3 feet long. This screen was modi-

January 1955 INDUSTRIAL AND ENGINEERING CHEMISTRY 13


ENGINEERING, DESIGN, AND PROCESS DEVELOPMENT

fied during later operation to incorporate an oversize w e e n , and In addition, the condensate from the total condenser located
the oversize mas recycled to the primary grinder. The screens after the vapor scrubber was passed through a pH cell, thus al-
were continuously blanketed with dry air to minimize blinding of lowing the continuous measurement of the p H of the condensate
the 20-mesh product screen. The fines from the screening opera- after the recovery system In operation the fine control of a
tion were returned with the acid to the reaction system RS shown slight excess of ammonia could best be done by referring to the
in Figure 1. pIS recorder.
Start-up of Reaction Section. Normally, the finishing section
Development Program Includes Investigation was started first since there was no point in Lhe process stream
of Process Variables, Alternative Equipment where the product collected until i t reached the bag. The coat-
ing drum, screene, conveyors, grinder, and water-cooled conveyor
The program for pilot plant work was planned to obtain design were started in that order. The reactant preheaters were ad-
information for those components of the plant for which the justed to the desired steam pressure. The reactor, separator,
longest delivery time was indicated. Since it appeared that the stripper, and connecting lines were steamed a t atmospheric
major item in t,his regard was the number, type, and size of pressure.
dryers and cooler, t,liisphase of the work was esplored first. Xext The ammonia flow n-as started first and then the acid flow
in importance n - ~ the
s stainless steel, water-bed conveyors since was begun at a low rate until a rise in temperature in the reactor
the length and number of t,hese, and the rotary diyer and cooler, as observed. M t c r this, the acid flow could be brought, rapidly
would dictate t o 3 large degree the size of the process building. to the desired level. I s soon as the ternperat,ures of the molten
Concurrent with these studies, n.ork was ammonium nitrate leached certain values, it mas possible t o
reaction system, grinding, coating, classification, bagging, and switch the flow froni the vapor scrubber sump t o the water-
recovering of fines from the grinding system. cooled conveyor. 'rhe temperature at which this switch was
Test8s on the small quantit>ieso i product available from the made depended on whet~lieror not a dryer was used.
laboratory studie? hnvc indicated that the product should store After start,-up, a level T T ~ Sdeveloped in the scrubber sump and
and handle satisfactorily. Early in April and May of 1952 the the recovered ammonium nitrate soluthri was cireulat>edthrough
first product from t,he pilot piant was set aside under controlled the scrubber. When t,he concentration of the solution in the
conditions for stomge stabilit vapor scrubber reached a definite value, the solution was con-
Aftel all of the above phase e well along, the possi- tinuously removed to the acid charge tank for return through the
bility of eliniinat ing rotary clryirig equipment came under inten- reactor. The level was maintained constant in the vapor scrub-
sive study, and it was deterniined that the dryer and cooler ber sump to control the concentration. To reduce entrainment
could be omitted in the commercial installation. During hIay losses from the vapor scrubber, a,n entrainm.ent separator was in-
and June of 1953 the pilot plant as operated to train production stalled. This proved highly beneficial since at times the scrubber
supervisors and operat,ors. tended to carry over and this aininonium nitrate solution was re-
Operation of the reactor system t o produce molten a,mnionium moved from the gas strrain and retnrned to the vapor xruhher
nitrate of about 0.3% moist'ure content resulted in a higher sump.
ammonium nitrate temperature to the water-cooled conveyor. %'hen stripping air vtis ured, the stripper rvas started as soon
The addition of ammonium nitrate fines to the moiten ammonium as the molten ammonium nitrate temperature reached about
nitrate was found desirable, since otherwise the higher t,empera- 400" F. The stripping air also passed through the separator
tures put additional coo!ing loa,d on the stainless steel, water- and vapor scrubber.
cooled conveyor. If necessary, the belt could be operated to Water-Cooled Conveyor Operation. Depcnding on the pro-
compensate for t,lie higher temperature, although the uniformity duction rate and manner of operation, the make-up cold \-rater
of t.he sheet leaving the conveyor was not as good. Also, Kith was sent to the circulating -xater system of t'he water-bed con-
low moisture it was desirable to cool the product leaving the veyor, or added only io the first section. It is important to
water-cooled convpgor to a. lo-xer tempemtiire sirice the product, solidify the molten ammonium nitrate as rapidly as possible to
passed very quickly LO t'he screens, the co:tting d r ~ i mand
, the bag. keep the sheet of ammonium nit,rate as uniform as possible.
When the tIyo dryere were eliminated from the pilot plant When the complete pilot plant was operated over extended
building, t.he scrmis vere modified t,o allow the installation of an periods without shutdon-ns, the fines from below the vibrating
oversize screen and t,lie recycle of the oversize material to the pri- screens were continuously returned to a fines dissolving pot d i i c h
mary grinder. The pilot plant was operaied during most of the cont,ained an agitator. A thermocouple was located in the exit
first 6 months of 1953 without a dryer or cooler. During this line overflowing from the dissolving pot to the water-lxd con-
period it was possible t o obtain product moisture contents oon- veyor. The amount of fines returned to the dissolving pot was
sistently less than 0.3%. regulated to control the temperature of the molten ammonium
Any amount of fines greater than the quantity that could be nitrate to t,he vater-bed conveyor to perhaps 30" F. above the
returned to the fines-dissolving system could be proportioned to solidifying point of the ammonium nitrate. Returning the fines
the nitric acid by means of anot>herscrew conveyor and passed to the production system in this manner resulted in cooling of the
again through the reaction system. At the same time, the vapor ammonium nitrate and disposing of the fines. This reduc'ed the
scrubber operation concentrated any fog loss from the system water requirements to the mater-bed conveyor.
to between 50 and 90% animonium nitrate; this concentrated The control of the cooling through the water-bed convog'or was
materia! was continually returned to the nitric acid for recycle based on the temperature of the solidified ammonium nitrate
through the reaction system. pabesing over a Weston thermometer. TVhiIe this temperature
A stainless steeI suyface condenser condensed the water Irav- was not necessarily the true ieniperature of the ammonium ni-
ing the vapor scrubber. The weight and analysis of this water trate, it did give a sufficiently reliable tempcrature for coiltrolling
gave an accurate picture of the losses and these data were neces- belt operation.
sary for material balance calculatisns. Grinding, Drying, Cooling, Coating, and Bagging. From the
The molten amnionium nitrate was sampled as soon as it water-bed conveyor t h e product passed to the grinder which was
reached the Sandvik belts. Changes based on the acidity and located directlyat theend of the belt. For most of the pilot platlt
moisture content of t,hese samples could be made t o bring this work a n Art.hur Coltoii single rotor granulator was used. Vari-
phase of the operation t o the desired conditions. ous screen sizes were tried as various sized products were made in
A calibration was availahle for each reactant flowmeter as a order to determine the ei7e most suitable. When the pilot plant
general means of controlling the ratio of ammonia t o nitric acid. was operated with the two dryers, the material was conveged t o

14 INDUSTRIAL AND ENGINEERING CHEMISTRY Vol. 47, No. 1


PILOT PLANT

January 1955 INDUSTRIAL A N D ENGINEERING CHEMISTRY 15


ENGINEERING, DESIGN, AND PROCESS DEVELOPMENT

the top of the flight-type dryer. After passing through this flight- ment agencies ( 1 , 2, 4, 6). l l a n y equations can be written for
type dryer, the product discharged into a Koto-louvre dryer
direct'ly below. From the Roto-louvre dryer the product dis-
charged onto another conveyor which carried the product to the XH&Os -
decomposition of ammonium nitrate-for example,

- KHS + HSOj
NzO + 2x20
(1)

-
screen. The screen cooled and also classified the product to a SHaS03 (2)
plus 20 mesh size. From the screen the product, passed into the
coating drum where the proper amount of coating agent was ap- PIIHIXOB N?$. ' / z 02 + 2H20 (3)
plied. The product discharged directly from the coat,ing drum In the Stengel reactor equilibrium in Equation 1 is approached
into the bag, which was brought to the sewing machine and from the right. At t,he normal operating temperatures of the
sewed. Commercial Solvents pilot plant, equilibrium is such that the
The operation of the flight-type dryer was tried with both
exit gases from the reactor contain comparatively small a,niounts
counter-current and concurrent flow of air and product. The of ammonia and acid vapor, and these combine as the gases are
counter-current flow of air and product resulted in the best dry- cooled and are largely recovered in the vapor scrubber. Under
ing, although some difficulty was experienced with a carry-over normal operating conditions there should be even less decom-
of the fines from the product into the air discharge duct from the position according to the reaction of Equation 2. Since the re-
dryer. action of Equation 3 proceeds at still higher temperatures, there
In general, the drying conditions for the predryer were con-
can be litt'le ammonium nitrate decomposition by t'his mechanism.
trolled to keep the ammonium nitrate at about the same tem- Based on operation of the pilot plant and commercial plant to
perature as it entered. Since it, was simple to control the amount date, normal operat,ing temperatures after the separation of the
of cooling on the water-bed conveyor, it was possible for t h e prod- ammonium nitrate and st,eamwill be less than 400" F., and it is be-
uct to reach the predryer at a t,emperature anywhere between lieved unnecessary t,oexceed a temperature of 430" F. Considering
130" and 190" F. The temperature of the inlet air and the quan- that about a minute elapses between the time t,he ammonium
tity of air were varied to give t,he desired product moisture con- nit,rate leaves the separator until it reaches the individual water
tent and product temperature at the discharge. Drying condi- cooled belts where cooling is very rapid, it is apparent that, there
t,ions and, of course, capacities vere different when the t,wo can be little decomposition of the molten ammonium nitrate
dryers Lvere used in series and when either dryer was used alone. beyond the reactor.
In general, if the temperature of the ammonium nitrat,e was in- Khile temperatures higher than 460" F. may occur at times in
creased as it' went through the drycr, very little moisture reduc- the reactor itself, the rcsidence time is normally only a small
tion resulted. Most of the loss of moisture resulted if the tem-
fraction of a second and thus too short for significant deconi-
perature of the ammonium nitrate was decreased in passing
position. Under normal conditions of operation, Bemperaturea
through the dryer. in the reactor above 460' F. r$.ould not occur. During the
The Roto-louvre dryer employed \vas one of the smaller size laboratory and pilot plant stages of this investigation, abnormal
production dryers. Again it was possible to control the exit prod- reactor operating conditions were intentionally included on occa-
uct temperature and to sdme est,ent t'he moisture content, by sion; for example, temperatures well above 600" F., extreme ratios
varying the air rate, air inlet temperatiire, speed of rotation of the of reactants, and reactants contaminated v,-ith oil and other mate-
dryer, bed level, and retention time.
rials known to sensitize ammonium nitrate were studied. How-
I t was found early in the course of the investigat,ion that under ever, during all of the laboratory and pilot plant operat,ions no
humid conditions there was a t,enclency for thc vibrating screens uncontrollable conditions developed.
to blind. To minimize this blinding it was necessary to intro- Yields €ram this process depend primarily on the mechanical
duce a small amount of conditioned air below the screens. This operation beyond the reaction system and on the efficiency of
air passed up through the screens and out through the top where the vapor scrubber recovery system. Yields across the reaction
the product entered. Very little difficulty was experienced with system of 98% and better have been realized. Essentially the
screen operation while conditioned air \vas employed, and the air only nonrecoverable material is that which decomposes.
helped to cool the product. A thermodynamic analysis of this process will be presented in
It was difficult to obtain a uniformly coated product in the a subsequent papcr.
pilot plant. A screw-type feeder arid a vibrating feeder were
tried for feeding coating agent to the coating drum at a steady
rate. Both of these types of feeders tended to stop feeding or to Pilot Plant Production Is Sufficient
feed erratically, primarily because t,he coating agent Tyould not, to Allow Product Evaluation
flow steadily dawn to the feeder mechanisms. Since the amount During the pilot plant development of the process it was also
of coating agent used was only a few pounds per hour, it was pos- necessary to obtain information about desirable product char-
sible to install the feeder on platform scales; thus the amount of acteristics. It was known that a low product moisture was
coating agent fed could be watched and recorded on an hourly desirable. It was expect,ed t,hat ahout, 3yo coating agent would
basis. 11-hilethis served to indicate the amount of coat,ing agent required. The major difference bet,ween the new product and
used, it did not necessarily ensure that, the discharge of coating available fertilizer-grade ammonium nitrate was the shape and
agent was continuous. For selected storage stability tests, ma- size of the particles. Prills and crystal ammonium nitrate are
terial was prepared by charging 97 pounds of ammonium nitrate smooth of surface and rounded in shape.
a,nd 3 pounds of coating agent to a drum and rolling the drum The Commercial Solvents process product is irregular in shape
across the floor until thorough mixing resulted. In this manner tending toward cubic, and can be sized as desired. Products of
it was possible t o obtain data regarding the effect,ivenese of several sizes were prepared for storage, field spreading, and mixing
vm.ious types of coating agents and various concentration levels tests in comparisons with existing products. The larger sized Coni-
of coating agent. mercial Solvents process particles showed the least tendency to
clog conventional-type spreaders, but smaller particles wcre
Abnormal Reactor Operating Conditions more readily distributed in mixed fertilizers. A - 5 to +20
Are Intenlionally Included in Study mesh product T ~ selectedS as the most satisfact,ory product for
all users.
The decomposition of ammonium nitrate has been studied In April and hlay of 1952 some of the first pilot plant produc-
extensively by many investigators. These investigations have tion was put aside for storage stabi1it)y evaluation. Some of
been sunimarized in many excellent bulletins issued by govern- this mRt,erial is still in storage and is still satisfactory. Some of

16 INDUSTRIAL AND ENGINEERING CHEMISTRY Vol. 47, No. 1


ENGINEERING, DESIGN, AND PROCESS DEVELOPMENT

this early pilot plant production and later production was also with this project, in particular t o W. 0. Bell, Jr., J. D. Kramer,
tested by Mississippi State College, and Louisiana State Univer- A. P. Miller, L. A. Stengel, and R. S. Egly.
sity. Satisfactory storage stability has been demonstrated with
products made with all of the process variables discussed. Literature Cited
Burns, J. J., and associates, U. S. Bur. Mines, Rept. Invest.
Summary 4944.
Elliot, Martin A , Ibid., 4244.
Extensive pilot plant work preceeded the commercial develop- Hester, A. S., Dorsey, J. J., and Kaufman, J. T., IND.ENG.
ment of a new process (the Stengel process) for manufacturing CHEM.,46,622(1954).
ammonium nitrate. This process is now in commercial operation Grant, It. L., and Scott, G. S., U. S.Bur. Mines, Infor. Ciro.
at Commercial Solvents Corp., Sterlington, La. The process 7463,June 1948.
offers significant investment savings and lower operating costs AIiller, Phillip, and Saeman, W. C., Chcm. Eng. Progr., 43, 667
through reduced personnel and utilities requirements. Since (1947).
Rous, W.H., and associatee, U. S.Dept. Agr., Tech. Bull. 912,
the control of the product moisture is in the reaction equipment, J u n e 1946.
the process is essentially independent of climatic conditions. Shearon, W.H.,Jr., and Dmwoody, W. B., IND. ENG.CHEM.,
45,496 (1953).
Acknowledgment Stengel, L. A. (to Commercial Solvents Corp.), U. S. Patent
2,568,901 (September 25, 1951).
The author wishes to express sincere appreciation to Commer- RscBIvEn for review July 30, 1954. ACCEPTED October 29, 1964.
cia1 Solvents for permission to present this information. Credit presented at the Regional Meeting of the American Institute of Chemical
is due t o all Commercial Solvents personnel who were associated Engineers, Washington, D. C., March 1954.

Thermal Calculations for


Sugar Process Engineers
HOWARD E. HIGBIE'
Deparfmenf of Chemirfry, University o f Piffsburgh, Piffsburgh, Pa.

T HERMAL properties of gas mixtures have been frequently


tabulated as the enthalpies of the individual components (9).
Then the total enthalpy or heat content of the mixture is com-
tions. In the following sections a method of preparing these
tables is outlined and methods of using the tables for the calcula-
tion of the heat effects attending several types of changes are
puted by summing, for all components, the product of the described.
enthalpy of the pure component times the fraction of the com- The justification for presenting the thermal properties of
ponent present. This procedure is justified x h e n the heat of sucrose solutions as two tables of partial enthalpies rather than aa
mixing is negligible; otherwise, the heat contents of the mixtures a single table of the total enthalpy or of the apparent enthalpy can
are not additive. be seen in the relationships between the heat effects and solution
The volume, enthalpy, and free energy changes on forming changes. The thermal equations can be stated by inspection and
liquid solutions from their components are not negligible in the calculations are straightforward. The solution partial
general, hence workers in the field of theory of solutions have enthalpies can be used in conjunction with existing enthalpy
expressed the solution properties in terms of partial quantities tabulations-e.g., the steam tables.
(6)-for example, partial molal volume, relative partial molal A recent communication from Lyle points out that he derived
heat content, and chemical potential. These quantities are de- an empirical equation for the enthalpy of sucrose solutions in
fined to be additive so that the specific volume of a solution, for terms of concentration and temperature (6). Although it wm
example, is the sum of the products of the mole fractions times the written without the benefit of more recent heat of dilution and
partial molal volumes of the components. The partial quantities solution data, the equation agrees well with the present tabula-
are intensive properties of the solution and depend on the tion. The Lyle equation does not express the partial enthalpies
composition of the solution as well as on the other variables which explicitly so that the calculation of the heat effects accompanying
determine the value of the total property. solution, precipitation, and vaporization processes is less con-
The partial enthalpies of water and sucrose in solution provide venient than with t h e present tabluation.
a convenient basis for engineering calculations of the thermal
effects attending changes in these solutions. These changes, Development Is Based on Relationships between
which occur in the sugar refining and processing industries, may Partial Quantities and Measurable Quantities
involve the gain or loss of either component from the solution.
A tabulation of the partial enthalpies of water and sucrose is The partial enthalpies of Tables I and I1 as well as the partial
presented in Tables I and 11, for the concentration range from 0 specific heats used in their evaluation are defined similarly to the
t o 65 weight % sucrose and the temperature range from 32" to well-known partial molal properties of solutions (6, page 33)
200" F. An enthalpy table for crystalline sucrose has been pre- except that they have been put on a unit weight rather than a
pared to cover the same temperature range (Table IV) and an unit mole basis. Thus, the partial enthalpies of water and
enthalpy table for water vapor over this temperature range sucrose in solution are defined by
(Table 111) has been included for convenience in making computa-
1 Present address, 7813 Maple Ridge Rd , Bethesda 14, Md.

January 1955 INDUSTRIAL AND ENGINEERING CHEMISTRY 17

You might also like