Professional Documents
Culture Documents
Heat Integration in A Crude Distillation PDF
Heat Integration in A Crude Distillation PDF
Design procedure:
– Location of pumparounds (PA)
– Analyse Pumparound Duty concerning the
Fractionation constraints
– Evaluate alternatives to improve Heat
Recovery: global costs (Pinch Design Method)
• Evaluate PA heat duty distribution at
atmospheric tower (vacuum constant)
• Evaluate changing pinch stream possibilities by
process modifications (modify vacuum tower
configuration, considering atmospheric tower
best result fixed)
• Evaluate modifying pinch stream return
temperature (if PA)
Pumparound Section
LVGO
NAPHTHA
TPA
KEROSENE
MVGO
MPA
LIGHT DIESEL
HVGO
REDUCED CRUDE
VACUUM
RESIDUE
Pumparound Section - Example
0 500 1000 1500 2000 2500 3000 3500 4000 4500 100 150 200 250 300 350 400
0 0
Flow rate (kmol/h) Temperature (°C)
5 5
10 10
Theoretical stage
Theoretical stage
15 15
20 20
25 25
35 35
These graphics compare both liquid internal reflux and temperature profile at
atmospheric column, considering BPA is already defined. Data refering to Max
PA are at near zero liquid reflux, while the other data refer to maximum liquid
internal reflux above Mid PA section.
Simulation Basis
19o API Brazilian Crude
Kept Constant:
– Atm Furnace Outlet Temperature
– Vacuum Furnace Outlet Temperature
– Atm Ovhd Drum Temperature
– Overflash Rate
– Number of stages
HVGO / LVGO ~ 1
Pumparound Withdraw at Product Drawoff Pans
Fractionation Constraints:
– Naphtha – Kerosene: 0 oC min gap
– Kerosene – Light Diesel: 5 oC min gap
– Light Diesel – Heavy Diesel: 30 oC max overlap
Cost basis:
– Brent: US$ 30.00 / bbl
– Fuel oil: US$ 20.60 / 106 kcal
– Cooling water: US$ 0.066 / m3
– Equipment Cycle Life: 10 years
Fractionation vs Heat Recovery
10
-10
-50
-60
-70
0 -5 -10 -15 -20 -25
Bottom Pum paround Duty (106 kcal/h)
Fractionation vs Heat Recovery
10
0
5 C gap at 18x106 kcal/h
-30
Inf lection Point at Duty = 14x106 kcal/h
10
0
GAP5-95 Kerosene vs Naphtha
GAP5-95 Light Diesel vs Kerosene
-20
-40
0 -5 -10 -15 -20 -25
Top Pum paround Duty (106 kcal/h)
Case Study 1
Case Study 1 – max heat recovery
Evaluate PA heat duty distribution in atmospheric tower
(vacuum configuration constant)
Ovhd
58.8 22.7 23.0
Condenser
Top PA 0 16 16
Mid PA 0 20 14
Bottom PA 0 0 6
¨ Hot Utility
0 + 0.22 - 4.05
(Base)
Case 16,14,6:
– Bottom PA: 6x106 kcal/h; Tout = 338°C; Treturn = 303°C
– Pinch: HVGO; Tpinch = 312°C
– Bottom PA: Above the Pinch = 338 – 312 = 26°C (74,3%)
6 x 0,743 = 4,45x106 kcal/h ~ 4,27x106 kcal/h (4.05 + 0.22)
Results – Case Study 1
Atmospheric Tower
Base 16,20,0 16,14,6
¨T optimum
26.2 14.9 19.2
(ºC)
Utility Cost
8.504 7.014 6.644
(106 US$/yr)
Capital Cost
6.016 6.126 5.789
(106 US$/yr)
Overall Cost
14.520 13.140 12.432
(106 US$/yr)
Savings
0 1.380 2.088
(106 US$/yr)
16,14,6 MVGO
Results – Case Study 2
MVGO
16,14,6
(pinch – Mid PA)
Hot Utility at pinch
5.74 0.16
(106 kcal/h)
Cold Utility at pinch (106
60.4 54.1
kcal/h)
¨ Hot Utility (Base)
- 4.05 -9.63
(106 kcal/h)
¨T optimum (ºC) 19.2 13.2
Utility Cost
6.644 4.565
(106 US$/yr)
Capital Cost
5.789 8.555
(106 US$/yr)
Overall Cost
12.432 13.120
(106 US$/yr)
Savings
2.088 1.400
(106 US$/yr)
As pinch is occurring at MVGO (much higher flow rate than HVGO), there is a
large portion of Hot Composite Curve with few variation in flow above the
pinch, resulting expressive increment on Capital Cost (penalty too high).
Results – Case Study 2
Utility Cost
6.644 4.565 5.784
(106 US$/yr)
Capital Cost
5.789 8.555 5.728
(106 US$/yr)
Overall Cost
12.432 13.120 11.512
(106 US$/yr)
Savings
2.088 1.400 3.008
(106 US$/yr)
If we keep pinch at HVGO, heat recovery is the same than Case “16,14,6”,
however the HEN approach is much higher, allowing more heat recovery.
Case Study 3
Pinch Stream Pumparound ¨T
¨T optimum
19.0 17.2 14.1 13.3
(ºC)
Utility Cost
6.181 5.994 5.685 5.784
(106 US$/yr)
Capital Cost
6.028 5.977 5.954 5.728
(106 US$/yr)
Overall Cost
12.209 11.971 11.639 11.512
(106 US$/yr)
Savings
2.311 2.549 2.881 3.008
(106 US$/yr)
Procedure constraints
– Pinch analysis assumes direct heat
exchange
– Cost of new sections inside the tower
need to be evaluated appart
– Modification on vacuum and
atmospheric collumn simultaneously are
not easily evaluated
– Non optimal design (but close to
optimum)
Conclusion