Name of Project
Location
Name of the Owner
NO. OF
Item No. DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
DAYS
1.0 Mobilization/ Demobilization 1.00 lot 8,500.00 8,500.00
NO. OF
Item No. DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
DAYS
d.) Labor
Foreman 1.00 man-day 15.00 450.00 6,750.00
Skilled Worker 2.00 man-day 15.00 400.00 12,000.00
Laborer 5.00 man-day 15.00 250.00 18,750.00
Sub Total 37,500.00
D5- ( .8m x 2.15m) H, D3, Hollow Core (CR) 1.00 set 3,071.00 3,071.00
Door Locksets
Locksets - Lever Type 2.0 set 682.00 1,364.00
Locksets - Cylindrical knob 8.0 set 306.00 2,448.00
NO. OF
Item No. DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
DAYS
d.) Labor
Foreman 1.00 man-day 7.00 450.00 3,150.00
Skilled Worker 2.00 man-day 7.00 400.00 5,600.00
Laborer 2.00 man-day 7.00 250.00 3,500.00
Sub Total 12,250.00
b.) Labor
Foreman 1.00 man-day 8.00 450.00 3,600.00
Skilled Worker/ Carpenter 2.00 man-day 8.00 400.00 6,400.00
Laborer 4.00 man-day 8.00 250.00 8,000.00
Sub Total 18,000.00
NO. OF
Item No. DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
DAYS
10.0 Electrical Works
a.) Lighting Fixtures 1.0 lot 26,000.00 26,000.00
b.) Wires and Wiring Devices 1.0 lot 16,000.00 16,000.00
c.) Panelboard, Conduits, Boxes, Fittings and
Miscellaneous 1.0 lot 25,000.00 25,000.00
Sub Total 67,000.00
d.) Labor
Foreman 1.00 man-day 5.00 450.00 2,250.00
Skilled Worker / Electician 1.00 man-day 5.00 400.00 2,000.00
Laborer 1.00 man-day 5.00 250.00 1,250.00
Sub Total 5,500.00
DETAILED ESTIMATES
Item No. DESCRIPTION COST AMOUNT
A. DIRECT COST 2,993,558.00
1.)Mobilization/ Demobilization 8,500.00
2.)General Requirements and Temfacil 10,000.00
3.) Materials 2,851,208.00
4.) Labor 123,850.00
16,412.50
Prepared by: