Professional Documents
Culture Documents
capital expenditure projects- M and N. The relevant cash flows for each project are shown in the
following table. The firm’s cost of capital is 14%
Project M Project N
Initial Investment (CF0): $28,500 $27,000
b.) Calculate the net present value (NPV) for each project.
Project N:
PV = CFt *
Year CFt PVIF (14%) PVIF
1 $11,000 0.877 $9,647
2 10,000 0.769 $7,690
3 9,000 0.675 $6,075
4 8,000 0.592 $4,736
c.) Calculate the internal rate of return (IRR) and (MIRR) for each project.
Project M:
IRR 15.086%
Project N:
IRR 16.1935%
d.) Summarize the preferences dictated by each measure you calculated, and indicate which
project you would recommend. Explain why.
M N
Payback Period 2.85 yrs. 2.67 yrs.
NPV $637 $1,155
IRR 15.1% 16.2%
e.) Draw the net present value profiles for these projects on the same set of axes, and explain
the circumstances under which a conflict in rankings might exist.