Professional Documents
Culture Documents
iree peat, = : :
é oe
= aaa \a= = SS EE i
(100
— X)%
Loss -V Gain
VaR-Example
“VaR is the maximum loss calculated for a given time
period at a certain confidence level.
“¢On the other hand, when the distribution of losses is used,
VaR is equal to the loss at the Xth percentile of the
distribution.
“eo Figure 2: Calculation of VaR from the Probability Distribution of the Loss in
the Portfolio Value [Gains are negative losses; confidence level is X%; VaR level is
Vi.
(100
— X)%
Gain V Loss
VaR-Example
“Example: <A 3% VaR of $50 over the next 1
week would mean that a minimum loss that would
occur within the next 1 week is $50 and the probability
of this loss is 3%.
“*In other words, there is 97% chance that our loss will
not exceed $50 within the next 1 week.
~* Example: The average return u=1.23%, and the
standard deviation 0=4.3%. °
“Figure 3: Monthly returns |
of a global portfolio p°
s
>
6
VaR-Example
“* Example: Contd... |
“Figure 3: The average return H=1.23%,)° litt
“¢ The standard deviation 0=4.3%. 4 LH I |
10
Ow
con
fF HD
Number of days
Morgan's daily revenue
days).
“9 LL —_— $7.6 M. 30 -26 -22 -I18 14 [-10
i
“ily evenae (ns) 10
| | «18i I 22 Brrr
14 26
R*
*,OVN20
VaR-Computational Procedures
“* PARAMETRIC METHOD:
“Let's assume that the portfolio return is normally
distributed with mean=y and variance=o%,then, we can solve
for V* such that:
“ F(v*) =Prob(y <V*) = [ —e "gv = p
“* The standard normal distribution table directly gives us the
—c0 Oo 7. e . e ° ®
where: Z = —,
VaR-Computational Procedures
s PARAMETRIC METHOD:
“¢The standard normal distribution table directly gives us the
value of the limit variable (Z*) corresponding to V*, and
associated with the given confidence level.
“*It is therefore beneficial to transform V in order to obtain Z
V—-—
where: Z = —,
“ >F-1(0.05)=-1.65
“=> V*= pb — 1.650. https://keisan.casio.com/exec/system/1180573190
VaR-Computational Procedures
s PARAMETRIC METHOD:
“*Example: Contd... u=1.23%, 0=4.3%.
VaR, = —V* = F71(0.05) *o = 1.650 — pn = 5.9%
“VaR, =n —V*=1.650 = VaR, — b= 7.13%
“* Example: Suppose that the gain from a portfolio during
six months is normally distributed with a mean of $2 million
and a standard deviation of $10 million. Given a confidence
level of 99%, calculate the VaR for the portfolio.
“* Here, F~1(0.01)=-2.33. = VaRg, = —V*=2.330 —u
“*The VaR for the portfolio with a time horizon of six months
and confidence level of 99% is therefore $21.3 million.
VaR-Computational Procedures
“Delta Normal VaR: One of the simplest and easiest ways
to calculate VaR is to make what are known as delta-normal
assumptions.
“* For any underlying asset, we assume that the log returns
are normally distributed and we approximate the returns of
any option using its delta-adjusted exposure.
“* The delta-normal assumptions make it very easy to
calculate VaR statistics even with limited computing power.
“* This made delta-normal models a popular choice when VaR
models were first introduced.
VaR-Computational Procedures
“¢Delta Normal VaR:
“*To calculate the delta-normal VaR of a security, we start by
calculating the standard deviation of returns for the security
or, in the case of an option, for the returns of the option’s
underlying security.
“* For regular securities, we then multiply the return standard
deviation by the absolute market value or notional of our
position to get the position’s standard deviation.
“* For options we multiply by the absolute delta-adjusted
exposure.
VaR-Computational Procedures
“* Delta Normal VaR:
“* The delta adjusted exposure of a single option being the
underlying security's price multiplied by the option’s delta.
“* We then multiply the position’s standard deviation by the
appropriate factor for the inverse of the standard normal
distribution (e.g. —1.64 for 95% VaR).
“* Note: About the expected return.
“*In practice, most VaR models assume that the distribution
of returns has a mean of zero.
“¢This is almost always a very reasonable assumption at short
horizons.
“*At longer horizons this assumption may no longer be
reasonable.
VaR-Computational Procedures
“* Delta Normal VaR:
“* Example: You estimate the standard deviation of daily
returns for XYZ Corp.’s stock at 2.00%. You own both the
stock and a call option on the stock with a delta of 40% and
1-day theta of —0.01. The underlying price is $100. Calculate
the one-day 95% daily VaR for each security.
“*AnSwer: The 95% VaR corresponds to the bottom 5% of returns. For a normal
distribution 5% of the distribution is less than 1.64 standard deviations below the
mean. —1.64, the negative sign indicating that the result is below the mean.
“*For the stock, the final answer is simply: -1.64 x $100 x 2.00% = —$3.28. (If you use
additional decimal places for the standard deviation, you might get —$3.29.)
“*For the option, the final answer is only slightly more complicated: -1.64 x 40% x
$100 x 2.00% — 0.01 = —$1.32.
“The 1-day 95% daily VaR for the stock and option are a loss of $3.28 and $1.32,
respectively.
VaR-Computational Procedures
“* HISTORICAL VaR:
“Another very simple model for estimating VaR is historical
simulation or the historical method.
‘“eIn this approach we calculate VaR directly from past
returns.
“*Example: Suppose we want to calculate the one-day 95%
VaR for an equity using 100 days of data.
“The 95th percentile would correspond to the least worst of
the worst 5% of returns.
“In this case, because we are using 100 days of data, the VaR
simply corresponds to the fifth worst day.
VaR-Computational Procedures
“* HISTORICAL VaR:
“* Now suppose we have 256 days of data, sorted from lowest
to highest as in the given Table 1: 95% Historical VaR
°
*° Y
We still want to calculate the 95%
R Cum. Weight(%)
VaR, but 5% of 256 is 12.8.
Worst 1 —34.3% 0.4%
v Should we choose the 12th day? The 2 28.9% 0.8%
13th? 3 —25.0% 1.2%
v The more conservative approach is to 4 —24.9% 1.6%
Loss -V Gai
am Loss -V Gain
COHERENT RISK MEASURES
“A sensible risk measure in finance must be consistent with
the basic theory in finance.
“¢In 1999, Philippe Artzner and his colleagues proposed a set
of axioms that they felt any logical risk measure should
follow.
“They termed a risk measure that obeyed all of these
axioms coherent.
“*As we will see, while VaR has a number of attractive
qualities, it is not a coherent risk measure.
“The four axioms that a coherent risk measure must obey
are monotonicity, positive homogeneity, translation
invariance, and subadditivity.
COHERENT RISK MEASURES
“Let n be a risk measure.
“We say that 7) is coherent if it satisfies the following
four conditions :
1. Monotonicity: If X = Y for all possible outcomes,
then n(X) = n(Y).
2. Translation invariance: For any positive constant
c, n(X +c) =n(X) +c.
3. Positive homogeneity: For any positive constant c,
n(cX) = en(X).
4. Subadditivity: n(X + Y) < n(X) + n(Y).
COHERENT RISK MEASURES
>Monotonicity: If a portfolio produces a worse result than
another portfolio for every state of the world, its risk
measure should be greater.
“*Let’s assume that we have two portfolios, Portfolio X and Portfolio Y.
“*If Portfolio X loses more money than Portfolio Y in all scenarios, then
Portfolio X should be considered riskier.
“If Portfolio X loses the same amount as Portfolio Y in all scenarios
except one where it loses more, then Portfolio X should still be
considered riskier.
“* Thus, ifX = Y for all possible outcomes, then n(X) = n(Y).
“eA risk measure that obeys this logic is said to be monotonic, or to
display monotonicity.
“*VaR is a monotonic risk measure.
COHERENT RISK MEASURES
>»Translation invariance: The translation invariance means that
there is no additional risk if there is no additional uncertainty,
because in statistics adding a constant to a random variable does not
affect its variability.
¢* A portfolio composed solely of risk-free assets—cash or short-term
Treasuries, for example—has, by definition, zero risk.
“*If we add an amount of cash equal to C to a portfolio, the cash
provides a buffer against losses and should reduce the capital
requirement by C.
¢*Adding or subtracting risk-free assets to a portfolio should not alter
the risk of that portfolio.
«*A risk measure that is unaltered by the addition or subtraction of a
risk-free asset is said to obey translation invariance.
“*Thus, for any positive constant c, n(X + c) = n(X) + ¢.
“*Both standard deviation and VaR are translation invariant.
COHERENT RISK MEASURES
>» Positive homogeneity: Imagine that you double the size of
all the positions in your portfolio. The returns in all
scenarios will also be doubled, and you should consider the
new portfolio to be twice as risky.
“* More generally, if you multiply all outcomes by a constant,
c, and the associated risk measure is c times as great, then
the risk measure is said to display positive homogeneity.
“*For any positive constant c, n(cX ) = cn(X).
COHERENT RISK MEASURES
> Subadditivity: The subadditivity states that the risk measure for a
combined position should not be greater than risks of the two
positions treated separately.
“The risk of a diversified portfolio should not be greater than risks of
the individual components.
“*Thus, subadditivity simply expresses the fact that there should be
some diversification benefit from combining risks.
“* Thus, n(X + Y) < n(X) + n(Y).
¢* In other words, the risk of the combined portfolio, (X+Y), is less
than or equal to the sum of the risks of the separate portfolios.
“+ Variance and standard deviation are subadditive risk measures.
“*VaR, does not always satisfy the requirement of subadditivity.
“*The following example demonstrates a violation of subadditivity for
VaR.
COHERENT RISK MEASURES
Example: Suppose each of two independent projects has a
probability of 0.02 of a loss of $10 million and a probability of 0.98 of a
loss of $1 million during a one-year period.
The one-year, 97.5% VaR for each project is $1 million.
When the projects are put in the same portfolio, there is a 0.02 x 0.02
= 0.0004 probability of a loss of $20 million, a 2 x 0.02 x 0.98 =
0.0392 probability of a loss of $11 million, and a 0.98 x 0.98 = 0.9604
probability of a loss of $2 million.
The one-year 97.5% VaR for the portfolio is $11 million.
The total of the VaRs of the projects considered separately is $2
million.
The VaR of the portfolio is therefore greater than the sum of the VaRs
of the projects by $9 million.
This violates the subadditivity condition.
COHERENT RISK MEASURES
Example: Imagine a portfolio with two bonds, each with a
4% probability of defaulting. The bonds are currently worth
$100 each. If a bond defaults, it is worth $0; if it does not, it
is worth $105. Assume that default events are uncorrelated.
What is the 95% VaR of each bond separately? What is the
95% VaR of the bond portfolio?
For each bond separately, the 95% VaR is —§5. For an individual bond,
in (over) 95% of scenarios, the bond increases in value by $5. In the
combined portfolio, however, there are three possibilities, with the
following probabilities:
P[x] x
0.16% —$200
7.68% —$100
92.16% $10
COHERENT RISK MEASURES
Example: Imagine a portfolio with two bonds, each with a
4% probability of defaulting. The bonds are currently worth
$100 each. If a bond defaults, it is worth $0; if it does not, it
is worth $105. Assume that default events are uncorrelated.
What is the 95% VaR of each bond separately? What is the
95% VaR of the bond portfolio?
As we can see, there are no defaults in 92.16% = (1 — 4%)? of
the scenarios. In the other, 7.84% of scenarios, the loss is
greater than or equal to $100. The 95% VaR of the portfolio
is therefore $100.
Because the VaR of the combined portfolio is greater than
the sum of the VaRs of the separate portfolios, it seems to
suggest that there is no diversification benefit.
Expected Shortfall
“eA measure that can produce better incentives for traders
than VaR is expected shortfall (ES).
¢¢This is also sometimes referred to as conditional value
at risk, conditional tail expectation, or expected tail loss.
“¢ Whereas VaR asks the question: “How bad can things
get?”
“ES asks: “If things do get bad, what is the expected
loss?”
“ES, like VaR, is a function of two parameters: T (the
time horizon) and X (the confidence level).
“Indeed, in order to calculate ES it is necessary to
calculate VaR first.
Expected Shortfall
“One criticism of VaR is that it does not tell us anything
about the tail of the distribution.
“*Two portfolios could have the exact same 95% VaR but
very different distributions beyond the 95% confidence
level.
“*Beyond VaR, then, we may also want to know how big
the loss will be when we have an exceedance event.
“¢ If an actual loss equals or exceeds the predicted VaR
threshold, that event is known as an exceedance.
¢* Another way to explain VaR is to say that for a one-day
95% VaR, the probability of an exceedance event on any
given day is 5%.
Expected Shortfall
“*If an actual loss equals or exceeds the predicted VaR threshold,
that event is known as an exceedance.
“A risk manager who measures one-day VaR at the 95%
confidence level will, on average, experience an exceedance event
every 20 days.
“A risk manager who measures VaR at the 99.9% confidence level
expects to see an exceedance only once every 1,000 days.
“It is tempting to believe that the risk manager using the 99.9%
confidence level is concerned with more serious, riskier outcomes,
and is therefore doing a better job.
“* The problem is that, as we go further and further out into the tail
of the distribution, we become less and less certain of the shape of
the distribution.
“* Beyond VaR, then, we may also want to know how big the loss
will be when we have an exceedance event.
Expected Shortfall
“*Using the concept of conditional probability, we can define the
expected value of a loss, given an exceedance, as:
“* ELL|L = VaRy| = ES, Wherein value at risk is defined as: P[L =
VaRy] = 1-X.
“*We refer to this conditional expected loss, S, as the expected
shortfall.
“* The use of the term expected shortfall is not universal.
**Many practitioners refer to this statistic as conditional VaR
(cVaR).
«+ If the expected profit of a fund can be described by a probability
density function given by f(y), and VaR is the VaR at the X
confidence level, we can find the expected shortfall as:
’ 1 VaR
% ES=—J_., yf v)dy
Expected Shortfall
“*If the expected profit of a fund can be described by a probability
density function given by f(x), and VaR is the VaR at the X
confidence level, we can find the expected shortfall as:
. 1 VaR
SES =— J, vf (dy
“* Example: The probability density function (PDF) for daily
profits at Pyramid Asset Management can be described by the
following functions:
% p=24+ce for -10<2<0
1 1 °
. P= 1407 100” forO0<az<10
+*
12 10 8 6 -4 -2 0 2 4 6 8 140 12
** The density function is zero for all other values of x. What is the
one-day 95% VaR for Pyramid Asset Management? For the same
confidence level and time horizon, what is the expected shortfall?
ES-Computational Procedures
¢ Example : The probability density function (PDF) for daily
profits at Pyramid Asset Management can be described by
the following functions:
1 1
= 76 + 7997 for -10<2z<0O
1 1
e p= 10 100” forO<z<10
¢ The density function is zero for all other values of Tl. What j is
the one-day 95% VaR for Pyramid Asset Management?
° Answer: To find the 95% VaR, we need to find a, such that
a
0.05 = / pdx
-10
By inspection, half the distribution is below zero, so we need only bother with the
first half of the function,
0.05 =“alae )
a a "|
ES-Computational Procedures
¢ Example: For the same confidence level and time horizon,
what is the expected shortfall?
¢ Answer: Because the VaR occurs in the region where z < O,
we need to utilize only the first half of the function.
¢ Using the above Equation S = — pes yf (y)dy, we have
VaR
1
S= xpd
0.05
-10
“bea |
1 VaR
—_|_,2._
!' 23
0.00
-12
c T
-10
T
-8 -6
T
+4
T
-2
T
0
T
2
T
=
T
6
T
8
T
10
1
12
= 10-£v10
x
= 7.89
ES-Computational Procedures
“* Example : For the same confidence level and time horizon,
what is the expected shortfall?
“* Answer: Because the VaR occurs in the region where z < 0,
we need to utilize only the first half of the function.
“*Using the above Equation ES = — pes yf (y)dy, we have,
thus, the expected shortfall is a loss of 7.89.
“* Intuitively this should seem reasonable.
“*The expected shortfall > VaR(=6.84), but < the max. loss of 10.
“*Because extreme events are less likely in this example(the
height of the PDF decreases away from the center), it also
makes sense that the expected shortfall is closer to the VaR
than it is to the maximum loss.
Expected Shortfall when Portfolio Values are
Normally Distributed
“*If the expected profit of a fund can be described by a probability
density function given by f(y), and VaR is the VaR at the X
confidence level, we can find the expected shortfall as:
SES = — fi" yf dy
VaR
vES =u+o—=—
V2m(1-X)
“* Here, X is the confidence level and Y = N~!(X) where N ( .) is the
inverse cumulative normal distribution.
“where Y is the X" percentile point of the standard normal distribution (i.e., it is
the point on a normal distribution with mean zero and standard deviation one
that has a probability 1 —- X of being exceeded).
“* Note: when u is assumed to be zero, ES, like VaR, is proportional to o.
Expected Shortfall when Portfolio Values
are Normally Distributed
“* When the losses(gains) in the portfolio value are normally
distributed with mean u and standard deviation o,
“ VaR=put+oY
vhs
weES = LU + ° an(1—X)
“This implies, for T=1, then SD is:o,/T + 2(T — 1)p. For p = 0, SD will be:oVT
“* Similarly, the correlation between AP;_; and AP; is p/.
«* If there is autocorrelation p between the losses (gains) on successive days, the
standard deviation of the change in the portfolio value over T days )17_, AP; as:
% o/T + 2(T — Dp + 2(T — 2)p2 + 2(T — 3)p2 +. +2p7 ¥
Choice of Parameters for VaR and ES
“*Impact of Autocorrelation:
“*In practice, the changes in the value of a portfolio from one day to the next are
not always totally independent.
“*If there is autocorrelation p between the losses (gains) on successive days, the
standard deviation of the change in the portfolio value over T days )17_, AP; as:
% o/T + 2(T —1)p + 2(T — 2)p? + 2(T — 3)p3 ++. 4+2p7~ ¥
“¢ Table: Ratio of T-Day VaR CES) to One-Day VaR (ES) for Different Values of T When There Is
First-Order Correlation (and Daily Changes Have Identical Normal Distributions with Mean Zero).
+
+¢
“* The five-day 95% VaR is therefore: 7.265 x N (0.95) = 11.95 or $11.95 million.
The five-day ES is: 54... 8? _ syog
2a x 0.05
“+ Note: the ratio of the five-day standard deviation of portfolio changes to the one-day
standard deviation is 7.2658 = 2.42(This is the number we found in the previous table
for p = 0.1 and T = 5).
Choice of Parameters for VaR and ES
“Confidence Level:
“*Regulators have used 99% for market risk and 99.9% for credit/operational
risk.
“*For example, a bank that wants to maintain an AA credit rating might use
confidence levels as high as 99.97% for internal calculations.
“*The confidence level that is actually used for the first VaR or ES calculation is
sometimes much less than the one that is required.
“*This is because it is very difficult to estimate a VaR directly when the
confidence level is very high.
“*A general approach for increasing the confidence level is extreme value theory,
which we shall be discussing later.
“*If daily portfolio changes are assumed to be normally distributed with zero
mean, we can use VaR & ES equations: VaR = oY
ey?2/,
ES
~ ” V2n(1 —X)
“To convert a VaR or ES calculated with one confidence level to that with
another confidence level.
Choice of Parameters for VaR and ES
“Confidence Level:
‘*If daily portfolio changes are assumed to be normally distributed with zero
mean, we can use VaR equation as:
** VaR(X) = oY = N71(X) for all confidence levels X.
¢+It follows that a VaR with a confidence level of X* can be calculated from a VaR
with a lower confidence level of X using
N~1(X*)
“Var(X -) = VaR(X). wing
“¢ Similarly, If daily portfolio changes are assumed to be normally distributed with
zero mean, we can use ES equation as:
ey /2
“ ES(X) =a
V2m(1-X)
“It follows that a ES with a confidence level of X* can be calculated from a VaR
with a lower confidence level of X using
(1-x)e" FP" -YY"+¥)/2
SES(X ) = ES(X).
(=x)
Choice of Parameters for VaR and ES
«Confidence Level:
“*It follows that a VaR with a confidence level of X* can be calculated from a VaR
with a lower confidence level of X using
N~1(X*)
“Var(X ) = VaR(X).
N~1(X)
“* Similarly, If daily portfolio changes are assumed to be normally distributed with
zero mean, we can use ES equation as:
** Answer: Using the assumption that the distribution of changes in the portfolio
value is normal with mean zero, gives the one-day 99% VaR as: j5x a = 2.12
“*or, $2.12 million.
** Similarly, one-day 99% ES as: 2x ope OIE AS IIE 6852 =258 or, $2.58 million.
Marginal, Incremental, and Component
Measures for VaR (and ES)
“Consider a portfolio that is composed of a number of
subportfolios.
“* The subportfolios could correspond to asset classes (e.g.,
domestic equities, foreign equities, fixed income, and derivatives).
“*They could correspond to the different business units (e.g., retail
banking, investment banking, and proprietary trading).
“+ Analysts sometimes calculate measures of the contribution of each
subportfolio to VaR or ES.
“*Marginal VaR is the rate of change of VaR with the amount
invested in the ith asset.
“* Incremental VaR is the incremental effect of the ith asset on VaR
(i.e., the difference between VaR with and without the asset).
“*Component VaR is the part of VaR that can be attributed the ith
asset (the sum of component VaRs equals the total VaR).
Marginal, Incremental, and Component
Measures for VaR (and ES)
¢*Suppose that the amount invested in i” subportfolio is Z,.
¢*The marginal value at risk (mVaR) for the i“ subportfolio is the
sensitivity of VaR to the amount invested in the i* subportfolio.
OVaR
mVakR=
OZ;
!
PIK =1]= (;) 0.10'0,.902-! = oS x 0.10 x 0.90 = 0.18
2 5 = ! 5
= 2+902-
PK =2]=( ~ )0.1020. 2 1 =0.01
x 0.10?x
2 210!
Backtesting Value at Risk (VaR)
“*From the properties of the binomial distribution, the
probability of the VaR level being exceeded on m or more
days ts:
n!
“ £(k)(kK) == p(K
p( =k) ) = K(n-K!P K1—p)"*,
(1— p) k=0,1,...,n
“+ Example: As a risk manager, you are tasked with calculating a daily 95% VaR
statistic for a large fixed-income portfolio. Over the past 100 days, there have
been four exceedances. (a)How many exceedances should you have expected?(b)
What was the probability of exactly four exceedances during this time?(c) What
was the probability of four or less? (d)Four or more?(e)Should you reject the
model?
“+ Answer: Remember, by convention, for a 95% VaR the probability of an
exceedance is 5%, not 95%. Over 100 days, then, we would expect to see five
exceedances: (1 — 95%) x I 100 = 5. The probability of exactly four exceedances is
17.81%. f (4) = p(K =4)= srggi oo 0-95)", k=4=0.1781
we 100
° F(<4)=p(K<4)=>™ . 0.05*(0.95)'°*, k=0,1,...,4=0.4360
4196!
S
100
+¢
>
¢*For the final result, we can calculate the probabilities for k = 4, 5, 6, ..., 99, 100, a
total of 97 calculations. Instead, we realize that the sum of all probabilities from
O to 100 exceedances must be 100%. Therefore, if the probability of K < 4 is
43.60%, then the probability ofK > 4 must be 100% — 43.60% = 56.40%.
“* Be careful, though, we want the probability for K = 4.
Backtesting Value at Risk (VaR)
“*The probability of the VaR level being exceeded on m or more days is:
xmnewi? OOP)
«* Example: Suppose that we back-test a VaR model using 600 days of data. The
VaR confidence level is 99% and we observe nine exceptions. The expected
number of exceptions is six. Should we reject the model?
Thank You!!!