Professional Documents
Culture Documents
Page No.
1601 SCOPE 16-1
1602 GENERAL 16-1
1603 TYPES OF PILES 16-1
1604 PENETRATION AND BEARING VALUE 16-1
1605 PRECAST CONCRETPILES 16-2
1606 DELIVERY, HANDLING AND STORAGE OF PILES 16-2
1607 DRIVING EQUIPMENT 16-3
1608 PILE DRIVING 16-4
1609 CUTTING AND LENGTHENING OF PILES 16-5
1610 PILE HEAVE 16-5
1611 CAST-IN-SITU PILES 16-6
1612 BORED AND CAST-IN-SITU PILES 16-6
1613 DRIVEN SHELL CAST-IN-STIU PILES 16-13
1614 PILE TESTS 16-15
1615 PILE RECORDS 16-17
1616 MEASUREMENT 16-18
1617 PAYMENT 16-19
SECTION 1600 – PILING FOR STRUCTURES
1601. SCOPE
This section covers the works connected with various types of piles required for
structures.
1602. GENERAL
The requirements contained in this specification and in the Drawing are the
minimum requirements. Strict compliance with these minimum requirements
shall not relieve the Contractor of the responsibility of adopting whatever
additional measures which may be necessary to ensure the completion of the work
to the satisfaction of the Engineer. Unless contracted hereunder, the provision of
IRC: 78-1983 shall be strictly followed.
In addition to submitting the records required under Sub-clause 1607 (3) the
Contractor shall report immediately to the Engineer any circumstances which
indicate that the ground conditions differ from those expected by the Contractor
from his interpretation of the soil survey so as to materially affect the bearing
capacity of the piles.
Timber, steel and pre-cast concrete piles are of driven type. Piles may be of solid
or hollow Section or steel cased piles filled with concrete. They may be of
circular, square, hexagonal, H, I, or Z Section as applicable.
Timber and steel/steel sheet piles shall comply with their Specifications as
provided in the contract.
The bearing values of the piles shown on the Drawing or indicated in the contract
are the minimum bearing values to which must be driven or installed. The driving
or installation of the piles shall continue until the estimated penetration and set is
reached or until the pile has been driven to substantial refusal or to a penetration
and set satisfactory to the Engineer. When water jets are used the bearing
capacity of a pile shall be determined from the results of driving with the hammer
after the water jets have been withdrawn. The bearing value and set for the
purpose of this Clause shall be calculated from the appropriate formula as given
in IS 2911 or such other criteria as shall be indicated or described in the contract.
Every pile shall be marked with the date of casting and an identification number.
Pre-stressed piles shall also be marked with the pre-stressing force applied.
Pre-cast concrete piles shall be of the size and shape as shown on the Drawing. If
a square Section is employed, the corners shall be chambered at least 25 mm
unless otherwise specified on the Drawing. The length of pile shall not normally
exceed 25 metres. However, where special equipments for handling and
installation are available to the satisfaction of the Engineer, longer length shall be
permitted.
Piles shall be cast with a driving point for hard driving and shall be cat with a
metal shoe approved by the Engineer
When testing of piles are specified in the contract, the pile lengths as shown
on the Drawing or described in the contract shall be used for tendering
purpose only. The number, Section and length of piles as specified shall be
subject to change. No piles except test piles, shall be ordered, delivered to
site or manufactured on site for any units of a structure until the Engineer
has determined from the results of the driving of the test pile. When the test
piles are not specified, the number and lengths of piles to be ordered,
delivered to site or manufactured on site shall be as specified in the contract.
All piles shall be handled, transported and stored in such a way that they
shall not be damaged. The use of can hooks, lifting tongs or other pointer
tools shall not be permitted. Precast concrete piles shall be supported at the
indicated pickup points and shall only be lifted with bridles or slings
attached at such pickup points. If no pickup points are indicated they shall
be assumed to be at a distance of 0.207 times the length of pile from each
end for two points lifts. For three points lift it shall be at a distance of 0.145
times length of pile from each end with the middle point being at the centre.
The Contractor shall be responsible for any damage caused by handling or
storage.
Pile Hammers, other than drop hammers shall be of approved steam, air or
diesel hammers, that develop sufficient energy per blow to drive the piles at
a penetration rate of not less than 5 mm per blow at the required bearing
value. Steam or air hammers shall be with boiler or air capacity at least
equal to that specified by the manufacturers of the hammers to be used. The
boiler or compressor shall be equipped with an accurate pressure gauge.
The value, mechanism and other parts of the hammers shall be maintained in
good condition and working order so that the length of stroke and number of
blows per minute for which the hammer is designed shall be obtained.
Inefficient steam, air, or diesel hammers shall be removed from the site. As
a general guide the size of the hammer normally required for steel piles shall
be one which develops approximately 1100 kg metres energy per blow. Pre-
cast concrete piles and steel shell for cast-in-situ piles longer than 15 metres
shall normally require a hammer which develops 1725 kg metres energy per
blow. Drop hammers shall in no case weigh less than the combined weight
of the pile, dolly and helmet. The Contractor shall, upon request, furnish the
Engineer with evidence of the weight of the drop hammer as he requires.
A driving helmet shall be used which fits closely over the head of the
pile. A cushion block of coir or wood shall be used between the pile
head and the helmet and the helmet shall have a dolly of suitable
material on the upper side.
The jet or jets shall be freely eroding the material under the pile. The nozzle
of each jet shall have a minimum diameter of 19 mm and shall generally be
circular. The pump supplying the water shall be of such size & type that it
shall maintain a water pressure of at least 9 kg/cm_ at the orifice of each
nozzle.
(1) General
The Contractor shall notify the Engineer at least 24 hours before beginning
any pile driving operations and no piles shall be driven unless the Engineer
or his Inspector is present. Before any foundation piles are driven in any
unit including test piles, the excavation shall be made, approximately, to the
planned footing level. Piles to be driven through embankments over 1.5 m
in depth constructed by the Contractor shall be driven in holes excavated
through the embankment of dimensions not less than the pile dimensions
plus 15 mm. After driving, the space around the pile shall be filled with dry
sand or single size gravel. During pile driving operations the water level in
the excavation shall be kept below the top of the pile. Under water pile
driving shall only be permitted when the contract calls for a concrete seal
foundation. In such cases, the piles shall be driven by a mechanical hammer
equipped to drive when submerged. When the top of the hammer is
submerged during driving, it shall be equipped with accurate measuring
detachable measuring rods, for the purpose of recording pile penetration.
Care shall be taken to obtain accurate location and spacing of the pilling. In
all cases of under water driving, the equipment and method to be used shall
be approved by the Engineer in writing. When satisfactory penetration of
piles cannot be obtained without damage to the pile from driving, and the
character of the soil is considered suitable, the Contractor may with the
Engineer’s approval use water jets in sufficient numbers to obtain the
desired penetration. Before the desired penetration is reached the jets shall
be withdrawn and the pile shall be allowed the jetting or the provision of
jetting equipment. Water jets shall not be used as an aid for driving steel
piling. The driving of piles by means of followers shall be avoided if
practicable and shall only be done with the written permission of the
Engineer, who may require that one pile from any group of 10 or less shall
be a long pile driven without a follower to determine the average bearing
power of the group. Sawing or cutting the body of a pile to assist in
springing it to proper location shall not be permitted. If a pile vibrates
excessively or shows signs of buckling during it shall be braced or guyed as
directed by the Engineer. Broken, spilt or wrongly treated piles shall not be
measured for payment and if required by the Engineer they shall be
completely withdrawn and replaced by satisfactory piles.
(2) Installation
Installation of piles shall be carried out in accordance with the pile layout
Drawing or as directed by the Engineer.
The Engineer shall decide the sequence of the group of piles that the
Contractor should undertake for installation and shall follow this sequence.
In a group the installation shall proceed from those on the centre of the
group towards those on the periphery.
(3) Temporary
The Contractor shall ensure that free standing piles are temporarily braced
on stayed immediately after driving to prevent loosening of the piles in the
ground and to ensure that no damage resulting from oscillation, vibration or
movement of any free-standing pile length can occur.
During driving, the piles shall not deviate from the vertical or the specified
rake (in the case of raker piles) by more than 40 mm per metre of pile
length, and after driving the centre of the pile at cut-off level, shall be not
more than 150 mm from its planned location.
Concrete piles shall be cut off at such level that they shall extend into the
cap or footing as indicated in the Drawing. If piles are to be lengthened the
main or splicing reinforcement shall be stripped of concrete for the distance
necessary to effect a lapped reinforcement splice in accordance with Clause
2013. Alternatively, subject to the Engineer’s approval, the reinforcement
shall be exposed for a minimum of 250 mm and the extension reinforcement
butt welded to the original reinforcement is at least equal to the 28 days
cube strength of the concrete in the original pile and approval of the
Engineer to resume driving has been obtained. In cases, where a substantial
number of pile extensions are expected, the Contractor may propose special
extension methods and procedures. In such cases, the Contractor shall
submit full details of the method and procedure proposed and carry out such
tests as the Engineer may require to substantiate the soundness, strength and
durability of the extended piles and their suitability to fulfill their function
adequately.
Piles shall be cut off at the appropriate level for incorporation of the footing
or cap as shown in the Drawing. When driven to cut-off level without
damage to the head a tolerance of 25 mm from the true cut off level shall be
allowed.
The Contractor shall take and maintain records of the levels of every pile
immediately after driving in accordance with the requirements of the Engineer.
After all piles in the group have been completed, the levels shall be checked to
determine whether any of the piles has heaved. Such heaved pile shall be re-
driven and pile shall not be considered complete until all heaved piles have been
re-driven as directed by the Engineer.
Cast in situ concrete piles may be either installed by marking a bore into the
ground by removal of material or by driving a metal casing with a shoe at the tip
and displacing the material laterally. The two types of piles are termed as bored
and cast-in-situ piles and driven shell and cast-in-situ piles respectively.
(2) Concrete
(3) Reinforcement
(a) Supply
The Contractor shall get approval of the Engineer for any other
material proposed by him for the drilling fluid.
(b) Mixing
Bentonite and any other material shall be mixed thoroughly with clean
water to make a suspension which shall maintain the stability of the
pile excavation for the period necessary to place concrete and
complete the construction.
(c) Tests
The Contractors shall demonstrate to the satisfaction of the Engineer that his
proposed construction method for the pile do not weaken the pile shaft by
contamination of the concrete by sectional reduction, by washing out of
cement, by breaking during pulling of temporary casing or in any other way
including the construction of neighbouring piles.
(a) Procedure
(ii) Boring and excavation inside the steel casing shall be carried down
to the casing toe level or to a level approved by the Engineer. The
excavation shall be continue to final pile tip level using either
temporary casing under water or using drilling mud. The fluid
level inside casing shall at all times be at least 2 metres higher than
outside the casings.
(vii) After hardening, the top Section of the concrete pile shall be
broken to reach sound concrete in the pile.
After the contract has been awarded the Contractor shall prepare a
detailed programme and establish for the pile construction. The
detailed programme shall contain all required information on
materials, equipment, methods of work etc., and be approved in
writing by the Engineer. Such approval shall not however relieve the
Contractor of his responsibilities for pile construction. The import of
any boring equipment or materials by the Contractor, before he has
receive the Engineer’s approval of proposed construction methods,
shall be at the Contractor’s risk.
The Contractor shall check the casing position for each pile during and
immediately after placing the casing, and agree it with the Engineer.
(c) Tolerances
The Centre of the complete pile at cut off level shall not deviate more
than 100 mm from the theoretically correct position shown on the
drawing. The inclination of the pile shall not deviate more than 1:100
from vertical. The Contractor shall provide suitable equipement such
as inverted pendulum, to check the vertically of the boreholes at
intervals during drilling and prior to concreting.
(6) Boring
(a) Methods
Piles shall not be bored so close to other piles which are cast and
contain workable or unset concrete likely to flow.
Boring and excavation for a pile shall not commence until 24 hours
after completion of any pile within a radius of 6 metres center to
center.
Pile through water and/or soft upper soil layers shall be provided with
permanent steel casing if shown in the Drawing.
The pile boring shall be carried out using temporary steel casing bored in
pile toe, to the level of side fall or to a level approved by the Engineer.
Before concreting the temporary casing shall be gradually withdrawn.
Under certain circumstances the Contractor may permitted to bore all part or
the pile without casing under water or using drilling fluid to stabilize the
borehole.
Where borehole is formed without casing under water or using drilling fluid
for maintaining the stability of a boring, the level of the water or fluid in the
excavation shall be maintained so that the water or fluid pressure always
exceeds the pressure exerted by the soils and external ground water. The
water or fluid level shall be maintained at a level not less than 2 meters
above the level of the river water level or any artesian pressure level.
In the event of a rapid loss of water or bentonite suspension from the pile
excavation, the excavation shall be backfilled without delay and the
instruction of the Engineer shall be obtained before excavation at that
location is resumed.
(9) Pumping
Pumping from the borehole shall not be permitted unless a casing has been
placed into a stable stratum which prevents the flow of water from other
strata in significant quantities into the boring, or unless it can be shown that
pumping shall not have a detrimental effect on the surrounding soil or
property.
The final toe level of other piles may subsequently be altered according to
the results of the tests loading detail in the Section.
(12) Inspection and Cleaning bottom of Excavation
The time between final excavation including bottom cleaning and the start
of concreting shall be reduced as much as possible and in any case shall not
exceed 6 hours.
Joints in longitudinal bars in piles with tension (for instance for test loading)
shall be carried out by welding unless another method has been approved by
the Engineer.
(iii) The use of pumped concrete and the methods in its use shall be
approved.
(iv) The Contractor shall take precautions in the design of the mix
and placing of the concrete to avoid arching of the concrete in a
casing. No spoil, liquid or other foreign matter shall be
allowed to contaminate the concrete.
(x) The hopper and pipe of the tremie shall be clean and watering
throughout. The pipe shall extend to the base of the boring. A
sliding plug or barrier shall be placed in the pipe to prevent
direct contact between the first charge of concrete in the pipe
of he tremie and the water of drilling fluid. At all times the
pipe shall penetrate the concrete placed and shall not be
withdrawn from the concrete until completion of concreting.
The bottom of the tremie pipe shall be kept at least 1.5 metres
under the surface of concrete. At all times a sufficient quantity
of concrete shall be maintained within the pipe to ensure that
the pressure from it exceeds that from the water or drilling
fluid. The internal diameter of the pipe tremie shall not be less
than 150 mm for concrete made with 20 mm aggregate and not
less than 200 mm for concrete made with 40 mm aggregate. It
shall be so designed that external projection are minimized,
allowing the tremie to pass through reinforcing cages without
causing damage. The internal face to the pipe of the tremie
shall be free from projections.
Slump
Pilling mix
Minimum Range Typical conditions of use
workability
mm mm
A 75 75-150 Placed into water free unlined or
permanently lined bore of 600
mm diameter or over where
casting level lies below
temporary casting: reinforcement
widely spaced bearing ample
room for free movement of
concrete between bars.
The pile shall be concreted with certain over height to allow for
chiseling off the top concrete down to sound hard concrete.
(e) Supervision
When by test, the safe allowable bearing value of any pile is found to be less
than the design load, longer piles or additional piles shall be installed as
ordered in writing by the Engineer.
Steel shells for concrete in-situ piles which protruded above ground or bed
level shall be as shown on the Drawing, specified in the contract or ordered
by the Engineer.
(2) Construction
Steel casings shall be driven as per layout plan shown on the drawing
or as directed by the Engineer. Sequence of driving steel casing in pile
group shall be as agreed by the Engineer.
The piles shall be cast with the concrete using design mix as specified
in the contract.
The concrete shall be placed to fill the entire volume of the casing
without the formation of voids caused by entrapped air. Proper
compaction shall be employed to obtain a dense and high quality
concrete. The concrete shall be vibrated immediately after placing
each lift and lifts shall not exceed 1.25 m in height. The filling of piles
in conjunction with the placing of concrete in the footing shall not be
permitted. The volume of concrete placed shall be observed in the
case of few piles initially cast and the average figure obtained shall be
used to check, whether there is any deviations in the volume of
concrete placed for the subsequent piles.
(e) Miscellaneous
The Contractor shall furnish test piles of the type, number and length
specified in the contract. Generally the test piles shall be located so as to
permit their use in the finished structure and they shall be installed at the
positions shown on the Drawing or specified in the contract.
In order to obtain the best possible data from the test pilling the Engineer
shall have the right to change test piles from their planned location to any
other location in that group or any other group of the structure without any
adjustment in the Contract Prices.
The installation shall be done using the same equipment as is to be used for
installing the other piles in the works. The Contractor shall co-operate with
and assist the Engineer in obtaining data for bearing for the full length of the
installation.
When using driven piles in soft or plastic soils, the Engineer may require
test piles to be re-driven. In such cases the driving shall be stopped at a
point when the top of the pile is 600 mm to 1500 mm above cut off level and
driving shall be resumed after a minimum of 24 hours.
Loading tests shall be made on those piles shown in the Drawing or ordered
by the Engineer. All labour, material, equipment and attendance required to
complete the tests shall be furnished by the Contractor.
(c) The load after each increment shall be kept constant until
the rate of settlement does not exceed 0.25 mm per hour.
(e) The full test load shall be maintained for 48 hours and the
total settlement shall be recorded.
(g) The load after each reduction shall be kept constant until
the rate of recovery does not exceed 0.25 mm per hour.
(j) The settlement of the pile under the test load and recovery
of the pile after the removal of the load shall be within the limits
required in the contract or ordered by the Engineer.
(d) The load test shall not be started until the concrete has
attained a minimum compressive strength of 95% of specified
strength. If the Contractor so selects, he may use high early strength
cement (but not high alumina cement) in the concrete of the load test
pile and the tension piles in order to decrease the time for load testing.
(g) The first load to be applied to the test pile shall be 50%
of the pile design load and the first increment shall be up to the pile
design load. The load on the pile shall be increased to twice the design
load by applying additional loads in three equal increments. A
minimum periods of 2 hours shall intervene the application of each
increment. If there is a question as to whether the test pile shall
support the test load, the load increments shall be reduced by 50
percent, at the direction of the Engineer, in order that a more closely
controlled failure curve may be plotted.
The Contractor shall keep records as indicated below for the installation of each
pile and shall submit two signed copies of these records to the Engineer not later
than noon of the next working day after the pile was installed. The signed records
shall from a record of the work. The following data shall be recorded.
Those information which are not applicable for the given type of pilling work
may be omitted.
1616. MEASUREMETN
The piles shall be measured in line metres of pile as completed and accepted in
the structure. Pay lengths of the accepted piles shall be measured from the butt of
the shoe to the cut-off level of the pile shown on the Drawing or as instructed by
the Engineer. No allowance shall be made for cut-offs or reinforcing steel
projecting into the concrete structure as called for in the Drawing. Any additional
pile lengths that may be necessary to suit the Contractor’s method of operation or
for any other reasons shall not be included in the measurements.
Test piles shall be measured per number of load test carried out including the
complete installation of the pile. Piles driven by the Contractor for his own
information or for calibrating diesel hammers shall not be measured as test piles.
1617. PAYMENT
Pile shoes when called for on the Drawing or by the Engineer shall not be paid for
separately, but full compensation for all the work involved in supplying and
fitting pile shoes shall be considered as included in the unit rate for pre cast
concrete piles and no additional compensation shall be allowed.
Splicing of piles, when allowed, shall not be paid for separately but full
compensation for all the work involved shall be considered as included in the unit
rate fro pre cast concrete piles.