Professional Documents
Culture Documents
and building cofferdams, including driving both load-bearing piles and sheet piles.
12.3.1 Crane operators shall have a valid Saudi Arabian Government (SAG)
heavy equipment license and a valid SA certificate per GI 7.025.
12.3.2 Work permits per GI 2.100 shall be issued when conducting piling
operations. See Chapter I-4, Work Permit System, of this manual.
12.3.3 Overhead and underground utilities shall be properly located and marked
prior to start of work.
12.3.4 Personnel handling piles or working on piling operations shall wear hard
hats, safety shoes, safety glasses, stout gloves and be equipped with
suitable ear protection to protect against the actual noise levels they will be
exposed to. See Chapter I-3, Personal Protective Equipment (PPE).
12.3.5 Steam/air hoses leading to the hammer or jet pipe shall be securely
attached to the hammer with a 6 mm (1/4 inch) chain or cable to prevent
whipping in the event a joint at the hammer breaks.
12.3.6 A properly rated safety chain/cable or equivalent means shall be provided
for other hose connections to prevent whipping in case the coupling
becomes disconnected.
12.3.7 Piling operations shall be supervised at all times. The crew shall be
properly trained in piling operations.
12.3.9 The ram shall be blocked, residual air or steam pressure relieved and lines
disconnected before maintenance work begins on the hammer.
12.4.1 Before work begins, a piling operations plan shall be developed that
includes, but is not limited to:
C. The precise location and nature of any overhead and underground utilities
or other obstructions in the area.
12.4.3 An inspection shall be performed and repairs made as necessary before pile
driving equipment is used.
12.5.1 When cranes are to be used for driving piles with a drop hammer or driving
piles below the level of the crane using extended leaders, the distance of
the hammer from the center point of the crane shall be determined and this
distance used to calculate the crane’s safe working load.
12.5.2 Outriggers shall be used to maintain stability of the crane. See Chapter III-
7, Cranes and Lifting Equipment, for additional requirements.
12.6.1 The ground supporting a crane or pile driving rig shall be firm and level.
12.6.2 Digger mats or hard-core standing shall be provided if the ground could
sink or collapse.
12.7.1 Sufficient timber or steel shall be used for the construction of pile gates.
12.7.2 Pile gates shall have proper ladder access. When pile gates are 1.8 m (6 ft)
or higher, sufficient handrails or full-body harnesses with lanyards shall be
used. See Chapter II-5, Fall Protection.
12.8.1 Pile driving and associated equipment used on-site shall be inspected
before work starts each day and per GI 7.030.
12.8.2 Air compressors or steam boilers shall be inspected and all hoses/couplings
checked for leaks and general condition.
12.8.3 Steam and air hoses shall be inspected to ensure they are properly fitted
with regulator valves and quick acting shut-off valves for emergencies.
12.8.4 Hammers and extractors shall be inspected (e.g., for loose bolts) at the
beginning of each shift.
12.9.1 Stop blocks shall be provided for the leads to prevent the hammer from
being raised against the head block.
12.9.2 Guards shall be provided across the top of the head block to prevent the
cable from coming out of the sheaves.
12.9.3 Fixed leads shall be provided with ladder and adequate attachment points
(e.g., rings) so that the loft worker may engage his lanyard to the leads.
Loft platforms shall be protected with standard guardrails.
12.10.1 Pitching
A. Piles shall only be lifted and positioned in the pile gate, or onto the leaders
or rig, with sound lifting gear adequate for the purpose.
C. When hollow sections or concrete piles are lifted with chains or wire
slings, timber or burlap packing shall be placed between the lifting gear
and the pile.
B. The emergency shut-off valve and the crane or winch controls shall be
manned at all times during pile driving.
E. Piles, leaders and machines shall be aligned when driving raking piles.
F. Hammers shall not be touched until valves are closed and the system is
depressurized.
G. Operators shall take precautions to ensure that hammer exhaust and earth
vibration are not a threat to the surrounding area.
12.11.2 Extractor wedges shall be inspected for good condition and replaced when
worn.
12.12.4 Deviations from the design during the actual construction of the cofferdam
shall be approved by the design engineer.
C. Cofferdam walkways, ramps or bridges shall have at least two exit points.
These shall be provided with standard guardrails.
H. Personnel shall immediately evacuate the area when a large leak cannot be
sealed or if there is an indication that the piling has moved. The design
engineer shall be immediately notified of these conditions.
C. Sump pumps and intake fastenings shall be inspected at the start of each
shift.