Professional Documents
Culture Documents
ASSIGNMENT – 01 (UNIT 3)
SUBMITTED TO : SUBMITTED BY :
1
IT IS HELPFUL TO MANAGE THE PROJECT IN FOLLOWING
WAYS:
COORDINATION.
PLANNING & SCHEDULING.
PURCHASING & EXPEDITING.
SUPERVISION.
COST CONTROL.
DOCUMENTATION AND REPORTING.
QUALITY CONTROL/QUALITY ASSURANCE.
ESTIMATING.
SAFETY AND RISK MANAGEMENT.
CONTRACT ADMINISTRATION.
CLAIMS ANALYSIS/AVOIDANCE.
CONSTRUCTABILITY & SEQUENCING STUDIES.
ERECTION DIAGRAMS AND PROCEDURES.
2
THE RESOURCE AGGREGATION WILL CALCULATE
APPROXIMATELY THE WORK PRODUCTION AND SET UP
ESTIMATES FOR
REQUIRED
MAN-HOUR AND
EQUIPMENT.
IN THIS FIGURE
“TASK A” IS
LAND
PREPARATION,
“TASK B” IS
PROCUREMENT
OF INPUTS ETC.
LAND
PREPARATION
(TASK A) TAKES
FIVE DAYS
STARTING
FROM DAY ONE. HOWEVER IN PRACTICE THE TIME SCALE IS 1ST
SUPERIMPOSED ON A CALENDAR I.E., IF LAND PREPARATION
STARTS ON JUNE IT WOULD BE COMPLETED BY 5TH JUNE.
LENGTH OF THE BAR INDICATES REQUIRED TIME FOR THE
TASK WHEREAS THE WIDTH HAS NO SIGNIFICANCE.
THOUGH THE BAR CHART IS COMPREHENSIVE, CONVENIENT,
AND VERY EFFECTIVE, IT HAS THE FOLLOWING LIMITATIONS:
LIKE MANY OTHER GRAPHICAL TECHNIQUES ARE OFTEN
DIFFICULT TO HANDLE LARGE NUMBER OF TASKS IN OTHER
WORDS A COMPLEX PROJECT.
DOES NOT INDICATE THE INTER RELATIONSHIP BETWEEN THE
TASKS I.E., IF ONE ACTIVITY OVERRUNS TIME WHAT WOULD BE
THE IMPACT ON PROJECT COMPLETION.
3
MILESTONE CHART IS AN IMPROVEMENT OVER THE BAR CHART
(GANTT CHART) BY INTRODUCING THE CONCEPT OF
MILESTONE.
THE MILESTONE, REPRESENTED BY A CIRCLE OVER A TASK IN
THE BAR CHART INDICATES COMPLETION OF A SPECIFIC PHASE
OF THE TASK (FIGURE 2).
FOR EXAMPLE LAND PREPARATION (TASK A) INCLUDES
PLOUGHING AND LEVELING.
FROM THE SIMPLE BAR CHART IT IS DIFFICULT TO MONITOR
PROGRESS OF THE PLOUGHING. INTRODUCTION OF A
MILESTONE ON
DAY 3 WOULD
SPECIFY THAT THE
PLOUGHING
WOULD BE 3RD
COMPLETED BY
DAY 3 OF THE
PROJECT I.E. JUNE.
IN A MILESTONE
CHART A TASK IS
BROKEN DOWN IN
TO SPECIFIC
PHASES
(ACTIVITIES) AND
AFTER ACCOMPLISHMENT OF EACH OF THE SPECIFIC ACTIVITY
A MILESTONE IS REACHED OR IN OTHER WORDS AN EVENT
OCCURS. THE CHART ALSO SHOWS THE SEQUENTIAL
RELATIONSHIP AMONG THE MILESTONES OR EVENTS WITHIN
THE SAME TASK BUT NOT THE RELATIONSHIP AMONG
MILESTONES CONTAINED IN DIFFERENT TASKS.
4
AND THE ACTIVITY BETWEEN MILESTONE 1 AND 2 IS OVER.
SIMILARLY, IN TASK B THE MILESTONE 4 CAN BEGIN ONLY
AFTER COMPLETION OF MILESTONE 3. BUT THE
RELATIONSHIP BETWEEN THE MILESTONE OF TASK A AND
TASK B IS NOT INDICATED IN THE MILESTONE CHART.
OTHER WEAKNESSES OF THIS CHART ARE AS FOLLOWS:
DOES NOT SHOW INTERDEPENDENCE BETWEEN TASKS.
DOES NOT INDICATE CRITICAL ACTIVITIES.
DOES NOT CONSIDER THE CONCEPT OF UNCERTAINTY IN
ACCOMPLISHING THE TASK.
VERY CUMBERSOME TO DRAW THE CHART FOR LARGE
PROJECTS.
5
1. LIST ALL THE TASKS AND MILESTONES (A.K.A. EVENTS) REQUIRED
FOR COMPLETION OF THE PROJECT
2. DETERMINE THE REQUIRED SEQUENCE OF TASKS
3. DESIGN A CHART TO VISUALLY DISPLAY ALL THE STEPS
4. ESTIMATE THE TIME REQUIRED FOR EACH TASK
5. IDENTIFY THE CRITICAL PATH – THE LONGEST SERIES OF TASKS IN
THE PROJECT
6. ADJUST THE CHART TO REFLECT PROGRESS MADE ONCE THE
PROJECT STARTS
A PERT CHART USES NUMBERED CIRCLES OR RECTANGLES TO
REPRESENT MILESTONES AND STRAIGHT LINES WITH ARROWS
AT THE END TO REPRESENT TASKS TO BE COMPLETED. THE
DIRECTION OF THE ARROWS, AND THE NUMBERS, INDICATE
THE REQUIRED SEQUENCE. TYPICALLY, THE NUMBERS
INCREASE BY 10 AT EACH MILESTONE, SO THAT NEW TASKS
CAN BE ADDED ALONG THE WAY WITHOUT REQUIRING THE
WHOLE CHART TO BE REDRAWN AND NUMBERED.
FOR EXAMPLE, THE PROJECT MANAGER KNOWS THE
SUCCESSION OF THE PROJECT ACTIVITIES AND THE
OPTIMISTIC,PESSIMISTIC AND MOST LIKELY TIME (IN WEEKS)
FOR THE FOLL
6
THE ASSOCIATED NETWORK IS:
THE EARLIEST START TIME, EARLIEST FINISH TIME, LATEST
START TIME AND LATEST FINISH TIME FOR EACH ACTIVITY ARE
CALCULATED IN THE FOLLOWING TABLE:
7
8
Q5. WHAT IS “CPM”? EXPLAIN IN DETAIL WITH EXAMPLE.
9
FIND THE DURATION OF EACH PATH.
THE PATH WITH THE LARGEST DURATION IS THE CRITICAL
PATH.
EXAMPLE:
IN THIS EXAMPLE A, B, C, D, F,
G, H, I ARE THE ACTIVITIES.
NUMBERS ABOVE THE BOXES
ARE THE DURATIONS.
ACTIVITY B IS A PREDECESSOR
ACTIVITY THAT LOGICALLY
COMES BEFORE A DEPENDENT
ACTIVITY F IN THIS NETWORK SYSTEM.
ACTIVITY F IS A SUCCESSOR ACTIVITY IS A DEPENDENT
ACTIVITY THAT LOGICALLY COMES AFTER THE ACTIVITY F.
THERE IS A F-S RELATIONSHIP BETWEEN ACTIVITY B AND F.
PDM FORWARD PASS
CALCULATION FORWARD PASS
CALCULATIONS SPECIFY THE
MINIMUM DATES AT WHICH
EACH ACTIVITY CAN BE
PERFORMED AND, ULTIMATELY,
THE MINIMUM DURATION OF A
PROJECT.
PDM BACKWARD PASS
CALCULATION BACKWARD
PASS CALCULATIONS
DETERMINE THE LATEST DATES
BY WHICH EACH ACTIVITY CAN
BE PERFORMED WITHOUT
INCREASING THE PROJECTS
MINIMUM DURATION.
10
PDM FLOAT CALCULATION FOR
EACH ACTIVITY IS THE AMOUNT
OF TIME THAT AN ACTIVITY CAN
BE DELAYED WITHOUT
DELAYING THE PROJECT
COMPLETION DATE.
11
START-START: IN THIS DEPENDENCY, THERE IS A DEFINED
RELATIONSHIP BETWEEN THE START OF ACTIVITIES.
FINISH-FINISH: IN THIS DEPENDENCY, THERE IS A DEFINED
RELATIONSHIP BETWEEN THE END DATES OF ACTIVITIES.
START-FINISH: IN THIS DEPENDENCY, THERE IS A DEFINED
RELATIONSHIP BETWEEN THE START OF ONE ACTIVITY AND THE
END DATE OF A SUCCESSOR ACTIVITY. THIS DEPENDENCY IS
RARELY USED.
EXAMPLE:
IN THIS EXAMPLE A, B, C, D, F,
G, H, I ARE THE ACTIVITIES.
NUMBERS ABOVE THE BOXES
ARE THE DURATIONS.
ACTIVITY B IS A PREDECESSOR
ACTIVITY THAT LOGICALLY
COMES BEFORE A DEPENDENT
ACTIVITY F IN THIS NETWORK SYSTEM.
ACTIVITY F IS A SUCCESSOR ACTIVITY IS A DEPENDENT
ACTIVITY THAT LOGICALLY COMES AFTER THE ACTIVITY F.
THERE IS A F-S RELATIONSHIP BETWEEN ACTIVITY B AND F.
PDM FORWARD PASS
CALCULATION FORWARD PASS
CALCULATIONS SPECIFY THE
MINIMUM DATES AT WHICH
EACH ACTIVITY CAN BE
PERFORMED AND, ULTIMATELY,
THE MINIMUM DURATION OF A
PROJECT.
PDM BACKWARD PASS
CALCULATION BACKWARD
PASS CALCULATIONS
DETERMINE THE LATEST DATES
BY WHICH EACH ACTIVITY CAN
BE PERFORMED WITHOUT
12
INCREASING THE PROJECTS
MINIMUM DURATION.
-THANKYOU
13