Professional Documents
Culture Documents
(A) Project
(B) Project management
(C) Project cycle
2-Resources refers to
(A) Manpower
(B) Machinery
(C) All of the above
3-Developing a technology is an example of
(A) Process
(B) Project
(C) Scope
4-The project life cycle consists of
(A) Understanding the scope of the project
(B) Formulation and planning various activities
(C) All of the above
5-Following is(are) the responsibility(ies) of the project manager.
(A) 3-2-1-4
(B) 1-2-3-4
(C) 2-3-1-4
7-Design phase consist of
11-The probability of completing the project can be estimated based upon the ____ .
(A) Uniform distribution curve
(B) Normal distribution curve.
(C) U-shaped distribution curve
12-In the initial stage of the project the probability of completing the project is ___ .
(A) Zero
(B) High
(C) Low
13-The entire process of a project may be considered to be made up on number of sub process
placed in different stage called the
(A) Technical key resources
(B) Work key structure
(C) Work Breakdown Structure (WBS).
14-Tool used for comparison of the proposed project to complete projects of a similar nature
whose costs are known.
(A) Algorithmic model
(B) Top down
(C) Analogy
15-Each component of the software product is separately estimated and the results aggregated to
produce an estimate for the overall job.
(A) Algorithmic model
(B) Expert judgment
(C) Bottom-up
16-Following is (are) the component(s) of risk management
(A) Risk Assessment
(B) Risk Control
(C) All of the above
17-Following are the characteristics of Project Mindset.
(A) Time, Responsiveness, Information sharing, Processes, structured planning
(B) Time, Project management, Information sharing, Processes, structured planning
(C) Time, Responsiveness, Information sharing, capability, structured planning
18-“Devising and maintaining a workable scheme to accomplish the business need” is
(A) Initiating process
(B) Planning process
(C) Executing process
19-Controlling the changes in the project may affect
(A) The progress of the project
(B) Project scope
(C) All of the above
20-Following is (are) the tool(s) for changing a process
(A) Change Management System (CMS)
(B) Configuration Management (CM)
(C) Both (A) and (B)
21. Assembling project team and assigning their responsibilities are done during which phase of a
project management?
(A) Initiation
(B) Planning
(C) Execution
23. A process that involves continuously improving and detailing a plan as more detail become
available is termed as
(A) project analysis
(B) progressive deliberation
(C) progressive elaboration
24. A program is usually a group of
(A) plans
(B) people and work
(C) related projects
(D) unrelated projects
27. If any one factor of a project changes, _____ other factor(s) is/are likely to be affected.
(A) all
(B) one
(C) at least one
28. Business Value =
(A) Tangible Elements
(B) Intangible Elements
(C) Tangible Elements + Intangible Elements
32. The strategy used to correct resource over-allocations by balancing demand for resources and
the available supply is known as
(A) resource assignment
(B) resource leveling
(C) resource splitting
33. A horizontal bar chart that shows project tasks against a calendar is called
(A) milestone
(B) Gantt chart
(D) PERT chart
34. The statistical tool that depicts a project’s tasks and the relationships between those tasks is
known as
(A) milestone
(B) Gantt chart
(C) PERT chart
37. The scope of the work is defined in which phase of the project management?
(A) Initiating
(B) Executing
(C) Closing
38. How the project work will be carried out, monitored, and controlled? These questions are
answered in which phase of the project management?
(A) Initiating
(B) Planning
(C) Closing
39. The review of the successes and the mistakes is normally held during _____ phase.
(A) initiation
(B) execution
(C) closure
40. The business case and the justification for the project is determined during the _____ phase.
(A) initiation
(B) execution
(C) closure
41. According to Olivier Mesly, the 4 P’s critical for the success of a project are:
(A) plan, processes, people, policy
(B) plan, processes, people, power
(C) plan, processes, potential, policy
42. A communication management plan identifies the relevant information that should be
communicated to:
A. Independent reviews and quality audits form part of quality assurance to ensure the project
manager delivers on time and to budget.
B. Quality assurance provides confidence to stakeholders that requirements for quality will be
exceeded.
C. Quality control verifies that the project deliverables conform to specification, are fit for
purpose and meet stakeholder expectations.
48. Which one of the following statements best defines the purpose of a Product Breakdown
Structure (PBS)?
A. To define the hierarchy of deliverables that are required to be produced on the project.
B. To establish the extent of work required prior to project commissioning and the handover.
C. To identify the health and safety strategies and procedures to be used on the project.
50. Which one of the following is a valid project Key Performance Indicator (KPI)?
A. Staff appraisals.
B. Management buy in.
C. Milestone achievement.
A. The business case is owned by the sponsor and is created during the concept phase of the project
life cycle.
B. The business case is owned by the project manager and is created during the concept phase of
the project life cycle.
C. The business case is owned by the sponsor and is created during definition phase of the project
life cycle.
55. A project is typically defined in terms of scope, time, cost and which other parameter?
A. Benefits.
B. Quality.
C. Tolerance.
57. What is defined as “the ability to influence and align others towards a common purpose”?
A. Teamwork.
B. Management.
C. Leadership.
60. The main outcome of risk identification, in a risk management process, is to:
A. identify and determine the relative importance of the project risks.
B. identify and describe all risks that might occur on the project.
C. identify and determine the responses to the project risks.
62. Which one of the following does project change control primarily seek to ensure?
63. Which one of the following is captured in the Work Breakdown Structure (WBS)?
A. The life cycle phases.
B. The logical order of tasks.
C. The scope of the project.
64. Project reporting can best be defined as:
66. The justification for the investment to be made in a project is documented in the:
67. Which one of the following is a responsibility of the project steering group/board?
A. To identify potential problems for the project team to solve.
B. To provide strategic direction and guidance to the sponsor.
C. To manage the project team in all daily activities.
68. One of the reasons a project life cycle is split into phases is to:
A. facilitate formal go/no-go decision making during the project.
B. balance the costs of work in each phase of project development.
C. mirror the major deployments of resources throughout the project.
A. A project is a set of tools and techniques often used when delivering organisational change.
B. A project is the sum of activities needed to remove uncertainty from a unique piece of
work.
C. A unique transient endeavour undertaken to achieve a desired outcome.
71. The document that identifies what information needs to be shared, to whom, why, when and
how is called the:
A. communication management plan.
B. stakeholder mapping grid.
C. document distribution schedule.
73. The process that evaluates overall project performance to provide confidence is called:
A. quality assurance.
B. quality planning.
C. quality control.
74. Which one of the following statements about the project risk register is false?
A. It facilitates the review and monitoring of risks.
B. It facilitates the risk appetite.
C. It facilitates the recording of risk responses.
76. Once a change has been requested what is the next step in the change control process?
A. Evaluate the change.
B. Advise the sponsor.
C. Update the change log.
79. Which one of the following best describes project success criteria?
A. Actively seeking some senior management support.
B. Measures by which the success of the project is judged.
C. A motivated project team.
84. When a project has completed the handover and closure phase:
A. the project deliverables are ready for commissioning.
B. the project deliverables are ready for handing over to the users.
C. the capability is now in place for the benefits to be realised.
85. Which one of the following illustrates why effective project management is beneficial to an
organisation?
A. It utilises resources as and when required under direction of a project manager.
B. It advocates employing a consultancy firm which specialises in managing change.
C. It recommends using only highly skilled people in the project team.
88. A review undertaken to decide whether a project should proceed into its next phase is known as
a:
A. gate review.
B. feasibility study.
C. milestone review.
89. Which one of the following statements best describes the use of an issue log?
A. A summary of all possible alternative resolutions of an issue.
B. A summary of all the project issues, their analysis and status.
C. A tool to ensure that a process is in place for capturing all issues.
90. The main aim of a project risk management process should be to:
A. identify project risks and then manage them appropriately.
B. identify all project risks and transfer them immediately.
C. identify all the things that are threats or opportunities on a project.
91. What is a visual representation of a project’s planned activities against a calendar called?
A. A Gantt chart.
B. A critical path network.
C. A product flow diagram.
96. Which one of the following is true for the Project Management Plan (PMP)?
A. A draft of the Project Management Plan is developed by the sponsor at the same time as the
business case.
B. The Project Management Plan is developed by the sponsor and owned by the project
manager.
C. The Project Management Plan is developed by the project manager and team and owned by the
project manager.
104. Calculate four periods moving average forecast from the last six periods
Period Demand
1 38
2 40
3 42
4 40
5 44
6 38
1.40
2.41
3.42
4.43
Answer:
Year Dema Forec
s n as
d t
1 38 -
2 40 -
3 42 -
4 40 -
5 44 40
6 38 41.5
7 41
106. If the actual demand for a period is 100 units but forecast demand was 90 units. The
forecast error is
1.-10
2.+10
3.-5
4.+5
107. Calculate a weighted average forecast using a weight of 50 to the most recent period
40 for the next recent period and .30 for the next period
Period Demand
1 38
2 40
3 42
4 40
5 44
6 38
a. 46.6
b. 47.6
c. 48.6
d. 49.6
108. The difference between the maximum time available and the actual time needed to
perform an activity is known as _________
a) Free float
b) Independent float
c) Total float
d) Half float
1. CV = BCWP - BCWS
2. CV = BCWP - ACWP
3. CV = SV / BCWS
4. A and c
110. The BCWS = Rs 250, the ACWP = Rs 350, and the BCWP = Rs 200. Calculate the
Cost Variance.
1. -Rs150
2. Rs150
3. –Rs 50
111) Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish
times for the three activities are 12, 15, and 10, then the earliest start time for Y will be
A) 10
B) 12
C) Cannot be determined
Answer: Earliest Finish Time (EF) = the earliest time that an activity can be completed. EF =
ES + duration of activity.
112) Activities P, Q and R instantly follow activity M, and their current start times are 12, 19, and
10. Therefore, the latest finish time for activity M is
A) 11
B) 10
C) Cannot be determined
Answer: Latest finish (LF): this is the latest time that an activity can be finished and not delay
the completion time of the overall project (= latest start time + activity completion time).
115) Which of the following techniques does not contribute to increasing throughput at a
bottleneck?
a.increase capacity of constraint
117) An activity has an optimisitc time of 15days, a most likely time of 18days, and a pessimistic
time of 27 days. What is its expected time ?
a) 19 days
b) 60days
c) 20days
118) An activity has an optimistic time of 11 days, a most likely time of 15 days, and a pessimistic
time of 23 days. What is its variance?
a) 4
b) 16.33
c) 2
119) Activities A and B are both 6 days long and the only immediate predecessors to activity C.
Activity A has ES=8 and LS=8 and activity B has ES=7 and LS=10. What is the ES of activity C?
a) 15
b) 14
c) 13
120) What is the probability that a project with a mean completion time of 23.9 days and a
variance of 6 days will be finished in 26 days?
A) 0.80
B) 0.20
C) 0.37
121) If demand is 106 during January, 120 in February, 134 in March, and 142 in April,
what is the 3-month simple moving average for May?
A) 132
B) 126
C) 142
122) Given last period's forecast of 65, and last period's demand of 62, what is the simple
exponential smoothing forecast with an alpha of 0.4 for the next period?
A) 65
B) 62
C) 63.2
Answer:
123) Susie's department is implementing many projects. She finds herself starting and stopping
work on one task to go and work on another task, and then return to the work on the original task.
Susie is experiencing
A) Poor scheduling
B) Flexible tasking
C) Multitasking
124) An uncertain event or condition that, if it occurs, has a positive or negative effect on a project
objectives is termed.
A) Random chance
B) A disaster
C) Risk
1. If ta, tm and tb are the optimistic time, most likely time and pessimistic time respectively in
PERT network then the expected value formulae is
A. (ta + 3tm + tb)/6
B. (ta + 4tm + tb)/6
C. (ta - 4tm + tb)/6
ANSWER B
Note: For Question # 2 to Question # 4 one should use data given which is as follows:
The tasks, their respective precedence and their respective times for a job which has these activities, are
given as follows
Task Time Precedence
A 5 None
B 7 None
C 3 A, B
D 6 B, C
E 10 C, D
For the Project network shown, answer the Questions 5 and 6 based on the data
provided.
A B E G J
D I
C F H K
Year 1 15,000
Year 2 25,000
Year 3 40,000
Year 4 40,000
Year 5 35,000
Year 6 30,000
Using a discount rate of 20% the discounted payback period would be:
A. 6 years
B. 4 years
C. The investment does not pay back
D. 5
years (Ans.:
C)
Table below shows the information related to a project that involves the merger of two marketing firms (in days).
Activity Immediate Estimated Duration (days)
Predecessor(s)
A - 10
B - 15
C A 2
D B 12
E C, D 14
F B 8
G D, F 15
H E 10
I E, G 6
J F, I 9
4. If there is an option to delay one activity without delaying the entire merge project, which
activity would you delay?
A. Activity A
B. Activity B
C. Activity A and Activity C
D. None of these
(Ans.: C)
Activity Earliest Start Latest Start Earliest Finish Latest Finish Slack
Start 0 0 0 0 0
A 0 13 10 23 13
B 0 0 15 15 0
C 10 23 15 28 13
D 15 15 27 27 0
E 27 28 41 42 1
F 15 19 23 27 4
G 27 27 42 42 0
H 41 47 51 57 6
I 42 42 48 48 0
J 48 48 57 57 0
Finish 57 57 57 57 0
If a discount rate of 10% is used to calculate the NPV of the project, which of the following statements is
correct? (Assume the cash flows arise at the end of each year.)
(A) The project will yield a positive NPV of Rs.65.5k and have a payback period of 2
years and 3 months.
(B) The project will yield a positive NPV of Rs.65.5k and have a payback period of 2
years and 9 months.
(C) The project will yield a positive NPV of Rs.365.5k and have a payback period of 2
years and 3 months.
(D) The project will yield a positive NPV of Rs.365.5k and have a payback period of 2
years and 9 months.
(Ans.: A) Solution:
If you are required to find a project's internal rate of return it is necessary to try different discount rates: one
that results in a net present value and one that results in a negative NPV. The two rates should be as close
together as possible. The actual internal rate of return can then be found by interpolation.
Discounted Discounted
Discount Discount
Year Cash Flow (Rs.) Cash Flow 11% Cash Flow 17%
(Rs.) (Rs.)
Factor 11% Factor 17%
(829) (371)
829
By interpolation the IRR is 11% + (17% − 11%) ∗ ( ) = 11% + 6%(0.6908) =
(829+371)
(Ans.: D)
8. The par yield of the project (c)for a certain maturity is .
(A) the rate that causes the project to equal its NPV.
(B) the rate that causes the project price to equal its face value.
(C) the rate that causes the project to equal its discounted price.
(D) the rate that causes the project to equal its Market Price of the
project. (Ans.: B)
9. NPTEL Ltd. is considering two mutually exclusive projects. Project A has an internal rate
of return (IRR) of 12 percent, while Project B has an IRR of 14 percent. The two projects
have the same risk, and when the cost of capital is 7 percent the projects have the same
net present value (NPV). Assume each project has an initial cash outflow followed by a
series of inflows. Given this information, which of the following statements is most
correct?
(A) If the cost of capital is 13 percent, Project B's NPV will be higher than Project A's NPV.
(B) If the cost of capital is 9 percent, Project B's NPV will be higher than Project A's NPV.
(C) If the cost of capital is 9 percent, Project B's modified internal rate of return (MIRR)
will be less than its IRR.
(D) All of the statements above are
correct. (Ans.: D)
Statement (A) is true because at any point to the right of the crossover point B will have a higher
NPV than A. Statement (B) is true for the same reason that statement (A) is true; at any point
to the right of the crossover point, B will have a higher NPV than A. Statement (C) is true. If
B's cost of capital is 9 percent, the MIRR assumes reinvestment of the cash flows at 9
percent. When IRR is used, the IRR calculation assumes that cash flows are reinvested at the
IRR (which is higher than the cost of capital).
10. Tata Industry is considering a new project that develops a new iron pigment, PRISTINE.
The company has estimated that the project's NPV is Rs.3 million, but this does not
consider that the new pigment will reduce the revenues received on its existing pigment
products. Specifically, the
company estimates that if it develops PRISTINE the company will lose Rs. 500,000 in after-
tax cash flows during each of the next 10 years because of the cannibalization of its
existing products. Tata Industry's WACC is 10 percent. What is the net present value
(NPV) of undertaking PRISTINE after considering externalities?
Step 1: Calculate the NPV of the negative externalities due to the cannibalization of existing projects:
𝐶𝐹0 = 0; 𝐶𝐹1−10 = −500000; 𝐼 = 10; 𝑁𝑃𝑉 = 𝑅𝑠. 3,072,283.55.
You have joined a new MNC and you are made the manager of a Project which is shown below.
The details about the project are as follows:
Assumption: Improvement gains is linearly associated to costs. For example, we can assume
activity F to complete in 10 weeks at a cost of Rs.10000, in 9 weeks at a cost of Rs.11500, in 8
weeks at a cost of Rs.13000, etc. We have to assume that we can decrease the activity time one
week, up to 4 weeks, for each Rs.1500 spent.
A-I-K: 33 weeks
A-C-G-J-K: 67 weeks
B-D-H-J-K: 69 weeks
B-E-J-K: 43 weeks
Explanation: You should identify the critical path as B-D-H-J-K and a project length of 69 weeks. If
the project takes 69 weeks in normal time the direct costs are $1,992,000, indirect costs of
$552,000 (69 x
3. When we crash the project, which activity we crash FIRST and for how many
weeks we can crash it at most?
A) A for 1 Week
B) C for 4 Weeks
C) J for 3 Weeks
D) J for 2
Weeks (Ans.: C)
Explanation: If all activities on the critical path were crashed, that path duration would be 56
weeks. If all activities on A-C-G-J-K were crashed, this path length would be 47 weeks.
Since the other three paths are already less than these are, you may disregard them in the
analysis. The basic approach is to crash the lowest cost activity (or combination of activities)
on the critical path(s) keeping in mind that as activities are crashed other paths may become
critical and the cost of crashing must continue to provide a cost improvement. The cheapest
activity to crash on the critical path is activity J at $1000 per week and J can be crashed a
maximum of 3 weeks. You may not always be able to crash an activity the maximum number
of weeks because other paths may become critical. A good approach is to look at crashing
activities one week at a time and see what the effects on the project are. The new path lengths
are:
A-C-G-J-K: 64 weeks
B-D-H-J-K: 66 weeks
Explanation: By reducing the critical path by 3 weeks we have saved $60,000 ($20,000 x 3) in
penalty costs and $24,000 ($8000 x 3) in indirect costs for total of $84,000. It cost us $3000
($1000 x 3) in crashing costs to reduce the project length by 3 weeks, so the net savings is
$84,000 - $3000 = $81,000. The total projects costs are now $2,624,000 - $81,000 =
$2,543,000.
5. What is the minimum cost of the project and total time needed for
completion? A) Rs.2506200, 61 weeks
B) Rs.2506600, 60 weeks
C) Rs.2339000, 62 weeks
D) Rs.2342200, 61 weeks (Ans.:
A)
Explanation:
For the next iteration, crash activity D by the maximum of 2 weeks at $2000 per week.
The new path lengths are: A-C-G-J-K: 64 weeks and B-D-H-J-K: 64 weeks
The saving is $20,000 for one week (we are now out of the penalty period) and $8000
for two weeks with $4000 crashing costs for a net savings of $32,000 ($20,000 +
$16,000 - $4000). The project cost is now $2,511,000.
Notice now that we have two critical paths so to reduce the project length activities on both paths
must be crashes. We may crash one activity common to both paths or an activity unique to
each path.
Here are the alternatives to be considered: Crash (A and B), (A and H), (C and B), (C and H), (G
and B), (G and H), or K (which is common to both paths). The cost to crash all alternatives
except (C and B) at
$7600 per week and K at $4000 per week cost more than $8000 per week potential saving so we
can remove these from considerations. So, crash K the maximum possible amount - 1 week.
The paths are now: A-C-G-J-K: 63 weeks and B-D-H-J-K: 63 weeks.
The project cost is now $2,511,000 - ($8000 - $4000) = $2,507,000
The last step - Crash B and C 2 weeks simultaneously at a cost of $7600 per week yielding a net
saving of $800
The minimum cost project schedule is $2,506,200 with a project length of 61 weeks.
Question number 06 to 11 is based on the following data for a given project:
You are the project manager of a project to build toilets across a district under Swatch Bharat
Abhiyan. You are to build two toilets a month for 12 months. Each toilet is planned to cost
$100. Your project is scheduled to last for 12 months. It is the beginning of month 10. You
have built 20 toilets and your CPI is 0.9091.
= 18 toilets.
(B) $2000
(C)$2200
(D) $2400
(Ans.: C)
EV = 20 Toilets & $100 per Toilet
= $2000. CPI = EV/AC
0.9091 = 2000/AC, so multiply both sides
by AC AC (0.9091) = 2000, so divide
both side by 0.9091 AC = 2200
8. Assuming that the COST variance experienced so far in the project will continue, how
much more money will it take to complete the project?
(A) $400
(B) $440
(C) $2800
(D) $2840
(Ans.: B) ETC = BAC/CPI – AC. We already know the CPI from the problem and AC from the
solution to #2, so let’s find BAC.
ETC = BAC/CPI –
AC ETC =
2400/.9091 –
2200 ETC = 440
9. If the variance experienced so far were to stop, what is the project’s estimate at
completion?
(A) $2400
(B) $2440
(C) $2600
(D) $2800
(Ans.: C) This question is asking you for the EAC if a variance that was encountered on a project is
expected to stop, so use EAC = AC + BAC – EV.
10. What is the project’s TCPI using the project’s budget at completion?
(A) 0.5
(B) 1.0
(C) 1.5
(D) 2.0
(Ans.: D) TCPI = (BAC – EV)/ (BAC – AC) = (2400 – 2000) / (2400 – 2200) = 400/200 = 2.
11. Senior management wants to the percentage of the project that is complete. What should you
report?
(A) 75%
(B) 83%
(C) 92%
(D) 95%
(Ans.: B) (EV/BAC) *100%