You are on page 1of 52

Engineering Procedure

SAEP-14 13 February 2012


Project Proposal
Document Responsibility: Project Management Office Department

Saudi Aramco DeskTop Standards


Table of Contents

1 Introduction………………………………......... 2
2 Applicable Reference Documents……..….… 3
3 Proposal Contents and ER Estimate……...... 5
4 Project Improvement Effort……………….… 23
5 Reporting and Review Requirements…....... 32
6 Approvals and Waivers…………………....... 35
7 Contract Bid Package…………………….…. 37
8 Exhibits……………………………………...... 38

Exhibit I – Project Proposal Checklist………….. 40


Exhibit II – ER Estimate Package Checklist....... 42
Exhibit III – Contract Development Checklist….. 44
Exhibit IV – Benchmarking Data Sheet………… 46
Exhibit V – Bid Quantification Summary............. 50

Previous Issue: 4 April 2010 Next Planned Update: 4 April 2013


Revised paragraphs are indicated in the right margin Page 1 of 52
Primary contact: Doiron, Shannon Earl on phone +966-3-8809161

Copyright©Saudi Aramco 2012. All rights reserved.


Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

1 Introduction

This procedure outlines the requirements for preparing the Project Proposal and
Expenditure Request (ER) Estimate package. The procedure is not intended to give
instructions on the engineering effort, but to cover requirements that are important
during the Project Proposal process. In summary it covers:
 Engineering specifications, standards and selected design requirements
 Quality, cost reduction and schedule improvement techniques, i.e., benchmarking,
value engineering and value practices
 Risk Management
 Project Proposal reporting, review, approval & waiver requirements
 ER Estimate preparation requirements
 Project Proposal, ER Estimate Package & Contract Development Checklists
 Contract Bid Packages

The intent of the checklists is to insure compliance with key requirements. They are not
intended to cover all detailed requirements of this procedure.

1.1 Definition

The Project Proposal is a document, which establishes the preliminary (front


end) engineering scope definition, cost estimate basis and schedule for a
proposed facility from the requirements included in the Design Basis Scoping
Paper (DBSP) and the approved Project Execution Plan (SAEP-12).
This includes the proposed facility design, general layout and the appropriate
functional and performance specifications including the recently published
applicable standards & codes. Project Proposal shall be of sufficient detail to
prepare a ±10% accuracy ER estimate, provide sufficient technical information
for Saudi Aramco review and (where applicable) provide sufficient information
to obtain detailed engineering, procurement and construction contract bids in
accordance with the approved Contracting Plan.

1.2 Purpose

The Project Proposal documents the agreement on, and commitment to, the
project scope, the project cost and design basis by the Saudi Aramco Project
Management Team (SAPMT), Facilities Planning Department, Project
Management Office Department, Proponent and other technical support groups.
This is accomplished through careful evaluation of the project objectives during
Project Proposal preparation to ensure the optimum results. The Project

Page 2 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Proposal establishes the basis for Expenditure Request (ER) funding and is the
baseline from which all subsequently considered scope changes are measured.

1.3 Preparation Timing

Project Proposals must be completed and approved in time to support the


Expenditure Request Approval (ERA) date.

A complete ER Estimate Package must be submitted to Project Management


Office Department / Estimating Services Division (PMOD/ESD) at least
4 weeks prior to the 56D Estimate submittal due date to FPD Budget Director,
as per the Capital Program ER Processing Schedule for Board EXCOM and
local approval. Refer to Section 3.4.2 through 3.4.6 for ER Estimate Preparation
requirements. Approved Project Proposal from SAPMT Department Manager,
Facilities Planning and Proponent organization signatory is a mandatory
requirement prior to issuance of the ER Estimate (Saudi Aramco Form 56D) to
Budget Director.

1.4 Application

With the exception of Master Appropriation projects, Saudi Aramco requires a


Project Proposal and ER Estimate for all Capital, Non-Capital and Expense
Projects, valued more than $2 million, under the control of Engineering and
Project Management (E&PM). The Project Proponent and SAPMT shall agree
and document the level of detail needed prior to start of the Project Proposal.
Projects that combine the preparation of DBSP and Project Proposal into one
effort shall ensure that the requirements identified in this document which are
relevant to the Project are met.

2 Applicable Reference Documents

The latest edition of the applicable reference documents shall be applied:

Saudi Aramco Engineering Procedures


SAEP-12 Project Execution Plan
SAEP-13 Project Environmental Impact Assessments
SAEP-25 Estimate Preparation Guidelines
SAEP-26 Capital Project Benchmarking Guidelines
SAEP-31 Corporate Equipment and Spare Parts Data
Requirements
SAEP-140 Project Training Impact Assessment

Page 3 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

SAEP-302 Instructions for Obtaining a Waiver of a Mandatory


Saudi Aramco Engineering Requirement
SAEP-303 Engineering Reviews of Project and Detail Design
Engineering Documentation

Saudi Aramco Engineering Report


SAER-5437 Guidelines for Conducting HAZOP Studies

Saudi Aramco Best Practices


SABP-A-002 Load Management for Energy Efficiency: Pumps
and Compressors
SABP-A-008 Load Management for Energy Efficiency: Heat
Transfer Equipment
SABP-A-009 Pinch Technology for Energy Efficiency
Optimization
SABP-A-012 New Projects Energy Efficiency Optimization
Review Methodology
SABP-P-003 Adjustable Frequency Drives – Selection and
Application

Saudi Aramco Engineering Standards (SAESs)

Saudi Aramco Materials System Specifications (SAMSSs)

Saudi Aramco Cost & Scheduling Manual

Saudi Aramco Construction Safety Manual

Saudi Aramco Safety Management System

Saudi Aramco Form and Data Sheet


8362-ENG Certification of Review of Saudi Aramco Materials
Source Documents

General Instructions
GI-0005.002 Loss Prevention Policy Implementation
GI-0020.500 Expenditure Control – Expenditure Request Forms
GI-0020.520 Project Change Request
GI-0202.309 Allocation of Costs – New Facilities Start-up

Page 4 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

GI-0202.451 Engineering Work Order Authorization for


Preliminary Engineering Preparation
GI-0400.001 Quality Management Roles & Responsibilities

Design Basis Scoping Paper (DBSP) and applicable Study Documents


Corporate Loss Prevention Manual
Project Management Loss Prevention Program
Supply Chain Management Manual
Saudi Aramco Project Risk Management Guide
DC Surplus Materials - Plant M011 of SAP system
MVG076-01, “DC Surplus Deferred Materials System”
Unrestricted Use Materials of SAP system (for SAMS Excess Materials)
Saudi Arabian Manufactured Materials Listing from SAP
Saudi Arabian Government Safety and Security Directives (SSDs)
Construction Industry Institute (CII) Publications
Value Engineering Guide
Best Practices Guide

3 Proposal Contents and ER Estimate

The following sections outline the items normally included in Project Proposals.

3.1 Table of Contents

3.2 Technical Requirements

3.2.1 Project Summary

This section provides a history of the existing conditions, a brief


discussion of the proposed facilities and their justification, outlines the
project objectives/scope and schedule, and briefly describes how these
objectives will be achieved.

3.2.2 Project Description

This section provides scope and design information that establishes the
performance specifications for the facilities, process, waivers or

Page 5 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

limitations. It shall address details concerning the design basis, proposed


facilities including equipment design, capacities, location/layouts and
other project related information. The list below provides common
elements found in a typical scope.

1) Facility/plant layout and location


Note: The project scope boundaries and interfaces with other related
facilities must be clarified prior to developing the scope of the
project in the proposal phase.

2) Facility/process description, design basis and performance


specification
3) Process Flow Diagrams (PFDs) including heat and material balances
4) Major mechanical, electrical, and utility requirements (type and
quantity)
5) Electrical one-line diagrams electrical area classification drawings
6) Piping and Instrumentation Diagrams (P&IDs)
7) Temporary and permanent on-plot and off-plot facilities
8) Site survey, topography and soil data (Geotechnical Investigation)
9) Demolition and modifications to existing facilities/plants
10) Operating variables (as required by OSPAS)
11) Corrosion control
12) Impact on and interface with other related projects
13) Environmental Impact Assessment (see SAEP-13)
14) Security, fire protection & safety provisions (if required, Hazard
Identification Plan of Major Hazards, fire hazard zone drawings,
and fire system layout drawings)
15) Communications, including government approvals if required
16) Control systems (including SCADA) provided with Control System
Block Diagram or System Architecture, instrument index,
instrument cable routing and I/O count breakdown
17) Project Execution Plan/Schedule
18) Training requirements
19) Land use permits for new facility sites or addition of facilities
within existing plants. Include Proponent approved permits for lay-
down areas, staging areas and office sites

Page 6 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

20) Strategy for project compliance with Project Quality Plan


requirements
21) Process & utilities system definition and turnover sequence
22) Piping, electrical and control system tie-in /hot tap plan.
23) Studies & calculations developed during Project Proposal (i.e.,
ETAP study, HAZOP study, process simulation, etc.). All required
engineering studies, including those defined in DBSP, must be
carried out regardless of contracting strategy adopted, e.g., LSTK,
LSPB, etc.
24) Site Investigation Report
25) Project Risk Management Study in accordance with the Saudi
Aramco Project Risk Management Guide
26) Commissioning and Start-up Plan

3.2.3 Scope Change from DBSP


A) Definition of Scope Change

A scope change is defined as any deviation from the Approved


DBSP. In addition to the DBSP deviations, any design that
exceeds the current Saudi Aramco standards and specifications and
is not already specified as part of the DBSP shall be considered as
a scope change. Said changes shall be clearly identified in each of
the interim and final Project Proposal package. Following are
examples of typical scope changes:
1. Design exceeding the current Saudi Aramco standards and
specifications
2. Equipment capacity and sizing changes
3. Addition or deletion of equipment from the original list
provided to PMOD in conjunction with the DBSP for
preparation of the budget estimate
4. Plot plan changes
5. Process control plan or system changes (changes in I/O
counts, type of control system, etc.)
6. Other design changes as a result of the following:
 Environmental Impact Assessment
 Hazard and Operability (HAZOP) study

Page 7 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

 Energy System Optimization Assessment Study


 Project Risk Management Study in accordance with the
Saudi Aramco Project Risk Management Guide
 Underground obstructions such as rock or utilities
interferences, etc.
 Building Risk Assessment or any other Loss Prevention
requirements
 Cost avoidance realized from Value Engineering and
other Value Practices
 Site investigations

B) Notification of Scope Change

SAPMT shall promptly notify FPD, in writing, of any scope


change with the cost and schedule impact and justification as soon
as changes are identified. This allows timely assessment by FPD
of the impact of these changes to the project. Change will be
incorporated in the project scope based on FPD's assessment. All
approved scope changes shall be communicated to PMOD.

C) Implementation of Scope Change

If accepted for implementation, FPD shall issue a formal letter or


DBSP amendment to SAPMT within two (2) weeks of the initial
submittal and distribute a copy to PMOD.

D) Recording of Scope Change

All scope changes shall be recorded in a special section in the


Project Proposal package and ER Estimate Package. This section
shall contain a list of all scope changes with justification, cost
impact, schedule impact, initiator organization, date initiated /
approved and any supported cost estimate documents.

SAPMT shall maintain the list of the scope changes and


continuously update it from the start of Project Proposal until the
ER Estimate is complete.

3.2.4 Communication Requirements

Saudi Aramco construction projects normally require both temporary


(during construction) and permanent communication systems.
As procurement approval for radio frequencies and materials involves

Page 8 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

long lead times, communication systems require early identification and


coordination between Information Technology organization and
SAPMT. To facilitate these requirements, the Project Proposal shall
contain the following:
a) Summary of temporary and permanent communication system
requirements. Identification of additional communication facilities
and/or modification to existing facilities necessary to meet the
project requirements.
b) Identification of additional communication facilities and /or
modification to existing facilities necessary to meet the project
requirements.
c) Identification of communications requirements to be handled by
Information Technology organization and those, which shall be
provided and funded by the project.
d) Schedule of communication material requirements with an
estimated site required delivery date.
e) Identification and implementation plans of all communication
disaster recovery and business continuity aspects of the projects.

3.2.5 Safety and Security Directive (SSD)

The SSD (reference SAES-O series) shall be adhered to by all projects,


with exception of home-ownership & utility projects, in accordance with
the directives given to Saudi Aramco by the Saudi Arab Government's
Supreme Commission for Industrial Security. The SAPMT shall contact
Consulting Services Department, Dhahran and the Safety and Industrial
Security organization to obtain current safety and security requirements
before proceeding with Project Proposal engineering. A separate section
in the Project Proposal shall be devoted strictly to safety and security
requirements.

3.2.6 Hazard and Operability (HAZOP) Study

The objective in performing HAZOP study is to improve process safety


and/or minimize operability problems. The SAPMT in conjunction with
the Loss Prevention Department (LPD), and Environmental Protection
Department (EPD) shall decide which projects and specific facilities
require complete HAZOP study. Duplicate facilities shall not require a
new HAZOP study. Only new or upgrade facilities that use, produce,
process, transport, or store flammable, explosive, toxic or reactive
substances in large quantities are candidates for complete HAZOP study.

Page 9 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

The completed HAZOP study in the Project Proposal phase shall be


thoroughly reviewed during detailed engineering to ensure that all safety
issues are identified prior to the start of construction. The review shall
be focused on any changes arising from detailed engineering that could
not be foreseen earlier.

For buildings, a building risk assessment shall be performed when


required by SAES-B-014.

Any cost impact as a result of the HAZOP study or building risk


assessment must be identified and included in the ER Estimate package.

3.2.7 Environmental Impact Assessment (EIA)

EIA is required at the early stage in project planning. SAEP-13, “Project


Environmental Impact Assessments,” establishes the procedures
necessary to prepare the environmental impact assessments which shall
be submitted to Environmental Protection Department Manager by the
30% Project Proposal stage for review and approval. EPD will forward
the final EIA document to the Ministry of Petroleum and Mineral
Resources for their approval. Approval by the Ministry is required for
all capital projects prior to expenditure request. Any cost impact as a
result of the Environmental Impact Assessment must be identified and
included in the ER Estimate Package.

An environmental impact assessment:


 describes and quantifies project actions
 identifies those discharges and emissions regulated by environmental
standards
 predicts the environmental changes resulting from the project, and
 demonstrates compliance with applicable Saudi Aramco and/or Saudi
Arab Government environmental standards and policies.

The discovery of new information or significant project changes that


impact a previously completed and EPD approved EIA may result in
cancellation of the existing assessment and re-submittal of an amended
EIA to EPD for approval.

The full environmental report with appropriate calculations is to be


included with the Project Proposals issued to Environmental Protection
Department, Technical Information Center (TIC) Dhahran, and
Corporate Information Center (ASC) Houston. All other volumes will
contain a summary only.

Page 10 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

3.2.8 Obtaining a Waiver from Saudi Aramco Engineering Standards and


Materials System Specifications.

Identify standards, procedures, equipment and materials that will require


a waiver prior to incorporation into the facilities.

3.2.8.1 Projects shall meet the requirements of Mandatory Saudi


Aramco Engineering Requirements (MSAERs), which are in
effect on the Project Proposal approval date. Changes to
MSAERs approved after the Project Proposal approval date
shall be mandatory only when:

 the changes affect safety, health, environment or security


highlighted by the concerned organization. In this case, the
impact of the changes on the project should be reviewed by
Project Management with the Proponent, Loss Prevention,
Industrial Security Operations, Facilities Planning
Department, Project Management Office Department,
Process and Control Systems Department, Information
Technology, and others to determine applicability and
extent of implementation.

 the changes result in cost savings to the project. In this


case, SAPMT, Proponent and Engineering Services shall
review and decide on implementation.

A Project Change Request (PCR) shall be initiated to document


and obtain approval to implement changes after the project has
been funded (Refer to GI-0020.520, “Project Change Request”).

3.2.8.2 Include waivers (reference SAEP-302 – “Instructions for


Obtaining a Waiver of a Mandatory Saudi Aramco Engineering
Requirement”) that shall reduce project cost without impacting
design, safety or operational integrity of the facility.

Describe the variation in sufficient detail to permit technical


evaluation by the appropriate reviewing agency. Include
copies of waiver applications and approvals. Any approved
waiver that has an impact on the Project must be identified in
the Project Proposal and ER Estimate package and be
considered during the Project Risk Management Study.

3.2.8.3 Deviations from SSD requirements shall be submitted in a


letter format as per SAES-O-100 (General Requirements for
Safety & Security) that describes the variation in sufficient

Page 11 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

detail to permit technical evaluation by the appropriate


reviewing agency.

3.2.9 Drawing Index and Drawings

This section provides a list and copies of the drawings that define the
scope of the project. It shall include key drawings such as PFDs, P&IDs,
plant and equipment layouts, electrical one-line diagrams and other
necessary drawings that are required to establish the design basis and
assist in producing an ER quality estimate.

3.2.10 Project Quality Plan

SAPMT shall prepare a Project Quality Plan in accordance with


GI-0400.001 (Quality Management Roles and Responsibilities).
The SAPMT shall also ensure that the specific requirements for
inspection are included in Schedule “Q” Attachment VI for all applicable
contracts.

3.3 Materials Related Requirements

3.3.1 General

The Project Proposal provides a table of major materials and equipment


identified for the project. During preliminary engineering, the
Engineering Contractor, with guidance from the SAPMT, shall review
the Company DC (9COM) Surplus and Excess (9CAT) using SAP
MMBE transaction to identify all acceptable or substitute materials
which are available in Saudi Aramco inventories for possible use on the
project, with the objective of:
a) Incorporating materials, which require the least new cash outlay to
Saudi Aramco
b) Making maximum economic use of the materials available from
surplus and excess cataloged material inventories
c) Making maximum economic use of locally manufactured materials
d) Providing full justification for any proposed purchases of
contingent quantities or non-installed spares

During Project Proposal preparation, the SAPMT shall request review,


and may request assistance from the Materials Supply (MS) on all
portions of the plan that involve materials related aspects of the work.
SAPMT will continue to be responsible to ensure that the purchase order
is in acceptable technical compliance with relevant MSAERs during the

Page 12 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

time the Contractor is handling the order. Purchase Orders for


inspectable materials shall be reviewed by Inspection Department prior
to placement, to ensure compliance with the Regulated Vendor List,
Technical and Quality requirements.

If procurement of major equipment and materials is on the critical path


of the project schedule, SAPMT may elect to consider “novation” of
these items to reduce their impact on the project schedule. “Novation”
typically involves:
1. placement of purchase order by the Management Contractor or
Project Proposal Contractor with commitment only for engineering,
and
2. after ERA, transfer the purchase order to the successful LSTK
Contractor on contract award.

The purchase order transferred to the LSTK Contractor will cover the
complete scope involving engineering and manufacture. Use of novated
purchase orders should be approved by Services Review Committee
(SRC) either as part of the contracting plan or as an individual item.

3.3.2 Material Source List

The materials source list identifies major equipment and material items.
Where possible, an estimated dollar value and quantity required shall be
indicated. Also indicate responsibility for inspection, expediting, traffic
and transportation. The Project Proposal effort shall develop Quotation
Requests (QRs) for major engineered equipment and critical items, and
issue these QRs to vendors on a “For Development Only” basis to
determine prices and delivery schedules. For purpose of preparing the
ER Estimate, the major equipment list shall include account number, the
item number, a brief description, the data sheet, a requisition number if
available, the estimated value and other pertinent information.
The following areas shall be segregated:
a) Surplus Materials - 9COM Materials in Plant M011
b) Excess Cataloged Materials - Unrestricted use 9CAT Materials in
SAP transaction MMBE
c) Locally manufactured materials and vendor warehoused materials
(LDOR)
d) Cataloged Materials Reservation (9CAT)
e) Non-cataloged Materials (9COM)

Page 13 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

f) Contractor procurement Lump Sum Turnkey (LSTK) or Lump


Sum Procure/Build (LSPB)
g) Sole source materials and equipment

3.3.3 Use-up Target Values

The Surplus Inventory and the Excess Cataloged Materials Listings shall
be reviewed to prepare the listing and estimated values of possible
surplus and excess usage. During the Project Proposal development, this
list shall be further refined to set the target values for use-up of those
items that shall be reported during the life of the project. LSTK or LSPB
contracts shall use the same format and shall estimate total commodity
(9CAT) and engineered (9COM) material costs (regardless of originator)
as the basis for determining use-up values. The target values are goals
requiring extra effort to achieve rather than just a restatement of the
original major items listed in Section 3.3.2.

3.3.4 Locally Manufactured Material

During Project Proposal development, the SAPMT shall obtain a current


list of approved locally manufactured products and sources from MS.
This list shall be provided to LSTK & LSPB Contractors to encourage
use of locally manufactured materials.

3.3.5 Critical Plant Equipment Unit Spares

A list of proposed installed spares for critical plant unit equipment and a
list of non-installed capital spares proposed for entry into Saudi Aramco
stores custody shall be provided along with the estimated cost for each
item and justification for purchase. Comparison shall be made between
spares specified in the Design Basis Scoping Paper and spares specified
in the Project Proposal.

3.3.6 Start-up Spare Parts

Construct-only project materials furnished by Saudi Aramco need not


address this subject because spares shall be furnished per SAEP-31
(Corporate Spare Parts Data Requirement). For Procure/Build contracts,
the SAPMTs shall specify start-up spare responsibility including how
they shall be provided, the financial impact of purchase and final
disposition of residual spares.

The LSTK Contractor is responsible for providing start-up spares.


Residual and/or unutilized start-up spares remain Contractor's property;
such spares may not be purchased from the Contractor by Project

Page 14 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Management. Proponent at their discretion has the option to purchase


these residual spares against their Operating Budget for future use.
Operations shall communicate with MS (Materials Control Department)
to ensure the spares are reviewed against overall inventory needs, and do
not adversely affect existing supplies. Defined start-up spares may be
turned over to Saudi Aramco in accordance with the contract
requirements provided that the quantities and types are in accordance
with the Saudi Aramco stocking policy. For LSTK and LSPB contracts,
start-up spares responsibility for “free issue” equipment provided by
Saudi Aramco shall be stated clearly in the contract.

SAPMT and the respective Contractors are responsible for the spare
parts as outlined under SAEP-31. In all cases, the SAPMT/Contractors
shall provide complete and accurate spare parts data packages necessary
to support Saudi Aramco procurement of operating spare parts.

3.4 Scheduling & Estimating Requirement

3.4.1 Scheduling Requirements

This section contains a Level III project summary schedule that shall be
developed during the Proposal phase based on information from the
Project Milestone Schedule, WER Schedule and other data as they
become available during the DBSP and Project Proposal.

Project Summary Schedule should be developed as soon as Preliminary


Engineering starts and will be used as a “working” tool in the absence of
a detailed schedule by Contractor. The Project Summary Schedule shall
be used as a guide for ER estimate preparation, early identification of
long lead material procurement items, Contracting Strategy and technical
evaluation of Contractors and start-up planning. As-Built schedules
from similar projects can be made available from PMOD Scheduling
Group to be used as a guide for the initial preparation of the Level III
schedule.

Project Summary Schedule addresses all the project life cycle activities
in a summary format. It must be logic driven, based on the Critical Path
Method (CPM). The Schedule should contain sufficient detail to show
potential material or equipment “novation”, long lead items, contract
procurement activities, detailed engineering by discipline leading to
major deliverables, mobilization, early works, shutdown, tie-ins, testing,
loop checks, pre-commissioning, start-up, interface with Proponent and
other projects.

Page 15 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Project Summary Schedule shall also include ER estimate preparation


and approval activities including Estimate Kick-off, milestone dates for
Scope Compliance and any ER Estimate reviews or any other design
reviews, MTOs for the relevant disciplines, equipment pricing,
NOVATION of equipment and/or Prior Approval Expenditure Request
(PAER), Technical Review Meetings, and the final approval of the
Project Proposal and 56D preparation and submittal to the Facility
Planning Department (FPD).

The schedule shall form the basis for the original (Rev.0) Project
Completion Schedule (PCS). The Project Summary Schedule further
expands the level of detail while still supporting critical and key
milestone dates defined and prescribed in the contract (Schedule “B”).
Project Summary Schedule is expanded to include critical milestone
dates as well as any other key milestones that are provided by
Contractors. If “novation” material and equipment is included in the
execution plan, the date of purchase order and required delivery date
should be incorporated in the schedule. The schedule shall include
review time requirements specified in SAEP-303 (Engineering Reviews
of Project and Detail Design Engineering Documentation). Contact
PMOD for more detailed information on Project Summary Schedule.

3.4.2 ER Estimate Requirements

Project Proposals must be completed and approved in time to support the


Expenditure Request Approval (ERA) date. A complete ER Estimate
Package must be submitted to PMOD, at least four (4) weeks prior to
submittal of 56D Estimate to FPD Budget Director as per Capital Program
ER Processing Schedules for Board, EXCOM and local approvals.

SAPMT shall be responsible for preparation of the ER Estimate package:


 in accordance with SAEP-25 (Estimate Preparation Guidelines)
 in conformance with the Work Breakdown Structure and Standard
Code of Accounts (SCA) established by SAPMT and PMOD
 to achieve a quality estimate with an accuracy of (±10%) of project
final cost
 using the Estimating Tool Aspentech Kbase, particularly for oil and
gas process facilities, as a preferred estimating software. Selection of
any other estimating tool should be discussed with PMOD.

Effective January 2008, Aspentech KBase shall be used as a mandatory


estimating tool in the preparation of the ER Estimate for oil and gas

Page 16 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

projects greater than $100 million. Waiving this requirement must be


approved by the PMOD Manager.

The final ER Estimate shall be jointly reviewed and approved by PMOD


and SAPMT.

3.4.3 ER Estimate Review Meetings

Initial, Interim and Final ER Estimate review meetings will be held by


members of SAPMT, Engineering Contractor, and PMOD during the
course of Project Proposal phase. SAPMT will be responsible for
organizing the meetings, providing the required documents to PMOD
prior to review meetings and inviting all concerned parties to participate
in the ER Estimate Review meetings.

A) Initial Kick-off Meeting

The initial kick-off meeting will be conducted before the 30%


completion of Project Proposal. An ER Estimate Plan, as described
in Section 3.4.4, shall be prepared and completed prior to the Kick-
off Meeting. PMOD will take an active role in defining Saudi
Aramco ER estimate preparation requirements and providing basic
information to the SAPMT and Contractor.

B) Interim ER Estimate Review Meetings

The purpose of the interim meeting is to review the progress of the


ER estimate preparation activities. The number of interim meetings
should be established during the initial ER Review meeting.

Minimum one (1) week prior to the review meeting, SAPMT shall
provide a complete set (hardcopy and electronic file) of the ER
Estimate with support documents to PMOD for review.

The interim review meeting deliverables shall include, but not be


limited to:
 ER Estimate as developed to date, with MTOs by Area and
WBS
 ER Estimate Basis
 ER Estimate Detailed Schedule
 Multiple Discipline Drawings including PFDs, P&IDs, Plot
Plans, One Line Diagrams, etc.

Page 17 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

 A list of all scope changes from the DBSP identified to date.


The list will include itemized scope changes with justification
and cost/schedule impact for each deviation item (per Section
3.2.3)
 Major equipment quotations
 Recent quotations for Engineering and Construction rates
 All discipline Material Take-offs (MTOs) by Area and WBS
 Market Outlook study, as required
 Project Risk Management Study in accordance with the Saudi
Aramco Project Risk Management Guide

C) Final ER Estimate Review Meeting


1. A complete ER Estimate Package must be completed in
accordance with the established ER Estimate Plan and
submitted to PMOD/PCED at least four (4) weeks prior to the
56D Estimate submittal due date to FPD Budget Director.
Refer to Section 3.4.5 for ER estimate deliverables.
2. After receipt of the ER Estimate package, PMOD will conduct
a meeting with SAPMT and Engineering Contractor to review
and finalize the estimate as deemed necessary.
3. Minimum of two (2) weeks prior to 56D Estimate submittal due
date to FPD Budget Director, SAPMT shall provide PMOD the
Project Proposal sheet approved by SAPMT, FPD and
Proponent and a copy of the Technical Meeting minutes with a
complete list of all finalized items with detailed cost estimate of
impacted items. These documents are required for finalizing
the 56D Estimate for submittal to FPD Budget Director.

When the ER Estimate is over or under by more than 10% of the


Budget Estimate, PMOD and SAPMT shall jointly prepare a scope
reconciliation and comparison between the approved Budget and
the established ER Estimate. The review shall include a list of all
scope changes from DBSP which will be part of the ER Estimate
package.

D) Scope Compliance Review Meetings

Compliance Review meetings will be conducted, as deemed


necessary, by SAPMT in coordination with FPD and PMOD to
ensure that the scope of Project Proposal is in compliance with the

Page 18 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

approved DBSP.

SAPMT shall prepare and provide all attendees with a complete list
of accepted scope changes and relevant supported documents for
the Scope Compliance Review meetings. PMOD shall be
responsible for validation of cost and schedule impacts for all
scope changes.

3.4.4 ER Estimate Plan

SAPMT shall be responsible for developing an ER Estimate Plan which


will be reviewed and discussed during the initial kick-off meeting. At
the minimum, the ER Estimate Plan should contain:
 Project scope of work
 Site development plan and comprehensive soil investigation report
 A detailed schedule with major and interim milestones for
completing the ER Estimate deliverables
 A quality control plan for estimate preparation
 Specific plan and methodology for performing market outlook and
project risk assessment for selected projects greater than $300 million
(refer to Section 3.4.6)
 Project Risk Management Plan in accordance with the Saudi Aramco
Project Risk Management Guide
 Methodologies for developing estimate basis, material take-offs
(MTOs), pricing of material and equipment based-upon life cycle
cost, unit rate for engineering and construction based on current
market conditions and project risk assessment
 Plan and methodology for developing internal and external
benchmarking
 Identification of estimating software to be used for preparation of ER
Estimate
 Work Breakdown Structures (WBS) and Standard Code of Accounts
(SCA) to be used for the project
 A list of ER Estimate deliverables required for interim review and
final review
 An organization chart of the estimating team

Page 19 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

 Roles and responsibilities of all involved parties in developing the


ER Estimate and identifying point of contact from each organization

3.4.5 ER Estimate Deliverables

The ER estimate will be based on 100% Project Proposal which includes


equipment lists, equipment sizing, plot plans, P&ID, single line
diagrams, cable schedules, instrument index summaries, I/O counts, bulk
material take-offs, and other related project documents and drawings.
The following major contents of deliverables should be included in the
ER estimate package:
 Approved Project Proposal
 Drawings, specifications, reports and other relevant documents
necessary to define the project requirements
 Approved Execution and Contracting Plan
 Commissioning and Start-up Plan
 Project Summary Schedule
 An ER Estimate package which includes a hard-bound copy and an
electronic copy on a CD with all required backup documents as
specified in SAEP-25
 A complete list of all scope changes from the DBSP that will be
implemented in the Project Proposal. The list will include itemized
scope changes with justification and cost/schedule impact for each
deviation item
 Copies of Technical Review Meeting Minutes
 Copies of ER Review Meeting Minutes with status of outstanding
and implementation items
 Copies of PHA or HAZOP Meeting Minutes with summary of
changes, if applicable

For detailed listing of deliverables, refer to the Exhibit II, ER Estimate


Package Checklist.

3.4.6 Market Outlook Study & Project Risk Assessment

PMOD will coordinate with SAPMT to identify projects worth


$300 MM or greater that will be required to do a Market Outlook Study
and Project Risk Assessment. Market trends and project risks are
assessed to avert potential impacts on project development and

Page 20 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

execution. Results of these studies shall be included in the basis of


estimate and contingency rates shall be recommended accordingly.
These shall include, but not be limited to, the following:
 Worldwide demand for Engineering and Construction services
 Market conditions that affect major equipment procurement pricing
and delivery
 Trends related to supply and demand of major equipment and bulk
material in the Middle East that could affect schedule and costs on
the project
 Availability of Engineering Contractors to undertake LSTK contracts
in Saudi Arabia
 Assessing the financial markets and institutional support for current
and future Middle Eastern projects
 Project risks study on constructability, tie-in execution,
environmental, security and other factors related to a specific project
 Forecast of Engineering Contractors Overhead and Profit Margins
 Any other factor that can impact the future cost of the project

Following are some of the resources that can be used in developing a


Market Outlook study:
 Trade Organizations
 Trade Magazines
 Financial Institutions’ studies and surveys
 Government studies and surveys
 Industry studies and surveys
 Manufacturers and Suppliers data

3.5 Appendix

The Appendix shall include letters, minutes, land use permits and other pertinent
documents written during Project Proposal development.

3.6 Numbering Project

All Project Proposals shall be numbered by the issuing office as follows:

Saudi Aramco APP Series (Numbers assigned by the Technical


Information Center, Dhahran)

Page 21 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

ASC TPP Series (Numbers assigned by the Corporate


Information Center, Houston)

APP or TPP numbers shall be on the Project Proposal cover sheet.

3.7 Training Impact Assessment

SAEP-140 (Project Training Impact Assessment) requires that a Training Impact


Assessment be prepared as part of the Project Proposal for all projects for which
training programs for operations and/or maintenance personnel will be required.
These training programs will not be provided by the project and costs for training
after commissioning are not be paid for by capital funds. (Refer to GI-0202.309,
Paragraph 4.5).

The Proponent is responsible for identifying any training requirements for a


project by preparing a Training Requirement Statement (TRS) prior to the start
of the Project Proposal. SAPMT will provide equipment identification and any
details that may assist Proponent in preparation of the TSR. The Proponent will
provide the completed TRS to the Training & Development’s Early BI Training
Planning (EBTP) team to complete a Training Impact Assessment (TIA) if
training is required.

If training is to be required, a Training Impact Assessment is to be prepared in


accordance with SAEP-140. SAPMT is responsible for incorporating the
findings of the Training Impact Assessment in the final Project Proposal.

SAPMT may also be required to implement the findings of the Training Impact
Assessment as included in the approved Project Proposal. These may include:
 Incorporating contract provisions that require the Contractor to develop
multiple quotations for specified equipment so that the cost of training can
be taken into consideration when selecting the life-time, low-cost supplier.
These provisions will allow Saudi Aramco to direct the Contractor to place
its order with one of the proposed technically acceptable suppliers and will
provide for additional payment to the Contractor if the selected supplier did
not offer the lowest base price to the Contractor.
 Incorporating requirements for the Contractor to include provision in its
purchase orders for specified equipment that establish fixed prices for
training services or material to be procured at a later date by Saudi Aramco.
This will reduce the possibility of a supplier overcharging Saudi Aramco
when training services or materials are procured on a single-source basis.
 Providing the vendor training plans and quotes for the equipment identified
for training to the EBTP team for analysis. After the initial analysis of the
vendor training plans and quotes, the EBTP team will provide training

Page 22 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

recommendations to SAPMT for considerations during the vendor selection


process.

After vendors have been selected, SAPMT will provide the EBTP team a list of
the specific equipment required for training, general vendor data information,
training scope, cost and schedule required for training prior to commissioning.

4 Project Improvement Effort

This section consists of practices that when implemented would optimize project cost,
schedule & quality and enhance the efficiency of project planning and execution.
Budgeting for conducting value practices is included in the Preliminary Engineering
fund.

4.1 Value Engineering

Value Engineering (VE) is an organized functional analytical methodology.


VE focuses on fulfilling the basic function and optimizing the life cycle costs of
secondary functions without sacrificing the performance, quality and reliability
of the project deliverables.

4.1.1 VE Study Selection Criteria

Unless waived in the DBSP, SAPMT shall initiate a formal VE study


during the Project Proposal development stage when:
 The estimated BI value exceeds $100 million, or
 The estimated BI value is between $30 – $100 million and a VE
study was not conducted during the pre-planning or DBSP
development stage, or
 The estimated BI value is between $30 – $100 million, and the pre-
planning or DBSP stage VE Report recommends that a Project
Proposal stage VE study is required.

4.1.2 VE Study Planning & Coordination

VE studies should be completed during the early phase of the Project


Proposal, but not later than the 30% completion milestone date.
For scheduling purposes only, VE studies shall be coordinated with the
Project Management Office Department (PMOD). The requirements for
conducting VE studies shall be identified in the Project Proposal
Contractor’s scope of work and in SAEP-12. VE shall be conducted on
the plot plan for expansion and grass root process plant project to ensure

Page 23 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

that the facility is designed in the most efficient and cost effective
manner.

VE studies shall only be facilitated by either a Certified Value Specialist


(CVS), or local Engineering Contractor personnel who have been
certified by PMOD to conduct VE sessions.

Requests for VE study guidance, and information on Consultants and


local Engineering Contractor personnel certified to facilitate VE sessions
should be directed to PMOD.

4.1.3 VE Proposal Implementation & Reporting Requirements

The effectiveness of a VE study depends on the successful


implementation of accepted proposals and on the prompt resolution of
pending proposals. VE proposals that are accepted by the Proponent
Organization and SAPMT are to be reviewed by FPD, and CSD if
related to standards requirement, before being incorporated into the
Project Proposal Scope of Work.

The status and resolution of all accepted and pending VE proposals shall
be documented in the Value Engineering Section of the Project Proposal.

A copy of the final VE Report shall be distributed to the PMOD no later


than four weeks from the completion of the VE session.

4.2 Risk Management Study

Project Risk Management (PRM) is a structured and systematic approach for


decision making. The PRM process is defined in six steps - plan the approach to
risk management, identify risks, assess risk in qualitative and quantitative terms,
develop response plans, then monitor and control the risk. Each step is repeated
at each phase in the project life cycle. The PRM process provides for efficient
use of resources and reduction in the use of contingency and management
reserves. The process is described in the Saudi Aramco Project Risk
Management Guide.

The PRM process is applicable to all capital projects, but the number of
activities within the process, and the depth of these activities, is matched to the
size, complexity, uniqueness and level of importance of the project. The
activities required to implement PRM for a specific project will be jointly
decided between the Project and PMOD. Smaller projects will benefit from pre-
defined templates and desk top reviews, while larger projects will benefit from
facilitated group workshops. These are outlined in the Saudi Aramco Project
Risk Management Guide.

Page 24 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

4.2.1 PRM Implementation

PRM commences in the project study phase when the project is initiated.
At commencement of Project Proposal, a PRM Plan, Risk Assessment
Report and Risk Register should already exist for the project. During
Project Proposal the 6 steps risk management process is repeated and the
PRM Plan and Risk Register are updated. The information is then
reviewed and a Risk Assessment Report is generated. This complete
process is referred to as the Risk Management Study.

PRM for the Project Proposal phase commences prior to the Value
Engineering Study performed at 30% Project Proposal. The activities
required are documented in the Saudi Aramco Project Risk Management
Guide and include:
Prior to 30% Project Proposal
Risk Management Plan Review and update
Risk Awareness with Project Team
Risk Identification and qualification
Risk Response Planning
Risk Management Action summary
During Project Proposal
Execute Risk Actions
Collect risk information
Risk Quantitative Assessment if appropriate
Prior to 90% Project Proposal
Risk Information review
Risk Identification and qualification
Risk Response Planning
Risk Assessment Report

Large, unique or complex projects will be required to implement these


activities in depth. Smaller projects will rely on templates, checklists,
the Corporate Risk Database, and Risk Subject Matter Experts.
The depth of analysis and the level of detail required by this process will
be decided between the Project Department and PMOD, and documented
in the PRM Plan.

The outcome of the Risk Management Study is an updated PRM Plan, an


updated Risk Register, and an updated Risk Assessment Report.

Page 25 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

4.2.2 PRM Coordination

Each project is responsible for its own risk management. The first point
of contact for risk information, guidance and coordination, is either the
Risk Management Specialist assigned to the Project Departments or
PMOD.

4.2.3 Risk Management Reporting

The PRM Study produces three documents as described in the Saudi


Aramco PRM Guide. They are:

PRM Plan:
 Documents the project context, existing risk information, project
constraints, background risk information, major assumptions, project
uniqueness, risk strategy and risk tolerance.
 Identifies cross functional risk team (including subject matter
experts), risk relationships, escalation, process of enacting risk
responses, risk activity scheduling, risk reporting, and risk training
requirement.
 Defines the depth of analysis required during the PRM Process and
the level of detail required in the Risk Assessment Report.

Risk Register: The repository for all the risk information and response
planning. It captures risk decisions and risk trends, and is the primary
tool used to understand and plan the management of risk.

Risk Assessment Report: A summary of the pertinent information from


the PRM Plan and the Risk Register. It describes the risk exposure and
recommendations as to how this exposure can be reduced.

4.3 Other Value Practices

SAPMT shall implement applicable Saudi Aramco and other industry value
practices during Project Proposal development to optimize project planning and
execution. PMOD is available to assist SAPMT in selecting the appropriate
value.

The requirements for conducting specific Value Practices shall be identified in


the Project Proposal Contractor’s scope of work and in SAEP-12. Value
Practice sessions shall only be facilitated by either approved Value Practices
Consultants, or local Engineering Contractor personnel who have been certified
by PMOD. For information on approved Consultants and local Engineering

Page 26 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Contractor personnel certified to facilitate Value Practice sessions, contact


PMOD.

The following value practices have shown proven payback for Saudi Aramco
projects:
 Constructability

Effective and timely integration of construction knowledge into the


conceptual planning, design, construction and field operations of a project.
Optimum timing during project proposal phase is at 30% Project Proposal.
 Project Definition Rating Index (PDRI)

Held at 60% Project Proposal involving SAPMT, Proponent, Contractor, and


other parties as needed to measure project proposal completeness and clarity.
PDRI consists of about 70 elements that identify and very precisely
describes each critical element in a preliminary engineering scope definition
package.
 Lessons Learned Implementation

Lessons Learned Implementation (LLI) is a systematic search for applicable


existing lessons learned and frequently encountered project pitfalls from
Saudi Aramco Project Management Lessons Learned knowledge base and
the Pitfall Prevention Tool website, and other reliable sources. It entails the
development of mitigation strategies and specific action plans to prevent
repeat problems and build on successes experienced by other projects.
All SAPMTs are required to implement applicable lessons and pitfalls at the
beginning of Project Proposal and collect and submit lessons learned during
Project Proposal.
 Project Execution Planning Workshop

Project Execution Planning Workshop (PEPW) is a half-day workshop


conducted before or at the start of Project Proposal to promote ownership,
commitment, and alignment of all project stakeholders including SAPMT,
FPD, Proponent, Contracting, Loss Prevention, and other involved parties.
 Schedule Optimization

Schedule Optimization (SO) is conducted at the 60% of Project proposal.


SO utilizes “Schedule Reduction” and “Schedule Compression” techniques
to optimize the project schedule.

Page 27 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

 Planning for Startup

Extensive set of tools and techniques used by all Project Stakeholders, PMT,
Proponent, Contractors, etc., to help facilitate a successful facility start-up
and stable long term operation.
 Scope Control & Change Management

Scope Control (SC) is a preventative process that starts with a detailed


project scope and ensures discipline in changing the scope during execution.
Change Management (CM) involves establishing and clearly communicating
to all project stakeholders a system for recognizing, evaluating, and
implementing changes during all phases of the project. SC & CM is
conducted at the 60% of the Project Proposal.
 Other

PMOD will identify and implement other value practices that become
available between revisions of SAEP-14 that offer value improvement to the
project.

4.4 Benchmarking

Benchmarking is an improvement process used to discover and incorporate


project cost, schedule, front-end loading, value improvement and operability
into project execution strategy.

The benchmarking process will be centralized so that all benchmarking activities


are managed through PMOD. Benchmarking will be conducted at study, late
stages of the DBSP, early stages of the Project Proposal as well as towards the
completion of a project. Projects will be selected by PMOD for either external
or internal benchmarking.

The objective of Benchmarking analysis at the early stage of Project Proposal is


to identify and compare key project parameters such as project scope, quantity,
cost, schedule, value practices and execution strategy, against the Company’s
internal historical statistics of similar projects. The project data also are used for
benchmarking against the industry world class projects with similar scope.
The result of the benchmarking analysis can be used for improving project
execution plan.

4.4.1 Internal Benchmarking Requirements

For all projects except community projects, school and home-ownership,


SAPMT shall provide key project data to PMOD for internal
benchmarking purposes. A sample of benchmarking data sheet is shown

Page 28 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

in Exhibit IV. This internal benchmarking data will be part of the ER


Estimate package.

4.4.2 External Benchmarking Requirements

PMOD will coordinate with SAPMT to identify projects with value of


$100 MM or greater to be benchmarked. Projects less than $100 MM may
be benchmarked if related to core business. PMOD will perform the
leading role for the selection of the Consultant, development of
benchmarking criteria, and implementation of the formal benchmarking
study. The analysis starts as early as the study phase and DBSP, or at any
appropriate stage of the Project Proposal development, but no later than
90% Project Proposal progress, comparing key parameters of the project
with an external industry-wide database. The analysis would address key
project outcomes and associated risk based on the Project Proposal effort
to date. As a minimum, the following areas should be addressed and
compared to industry norms, the Gulf Region and Best in Class:
 Status of front-end loading (FEL), i.e., project definition, at the time
the benchmark analysis is prepared
 Use of value improvement practices
 The projected total installed cost (TIC) of the project
 An analysis of the contingency requirement based on project scope
and FEL
 Engineering as a percentage of TIC
 Time required for total project execution (ERA through Onstream)
 Time required for the construction phase
 Expected time required for start-up
 Long lead material deliveries comparison
 General or specific requirements included in the Project Proposal
Scope of Work that are non- industry standards
 Execution strategies

A Benchmarking section shall be included in the Project Proposal book


to include the summary benchmarking report prepared by an outside
Consultant or by the Engineering Contractor.

4.5 Energy System Optimization Assessment Study

Capital projects involving the addition of or modifications to industrial


processes with fuel and/or power consumption exceeding $2 million per year
(combined) shall conduct a mandatory Energy System Optimization Assessment

Page 29 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

study. The purpose of this study is to render optimized process and utility
capital as well as the efficient use of thermal and electrical energy.

For purposes of the energy study, an industrial process is defined as one that
includes fired heaters, boilers, pumps, compressors, steam turbines, or gas
turbines. Non-industrial facilities such as buildings, roads, warehouses, storage
depots, and non-process operations such as IT or instrumentation upgrades are
excluded.

The technical approach and work scope for the energy study should address all
of the following issues as applicable:
 Process Integration, using Pinch Analysis techniques (ref. SABP-A-009 and
SAEP-12)
 Equipment Load Management policies (ref. SABP-A-002 & SABP-A-008)
 Adjustable Speed Drives (ref. SABP-P-003)
 Driver Selection

4.5.1 A Process Integration study of the project facilities shall be conducted


when the combined fuel consumption used in electricity generation and
process heating exceeds 100 MM Btu/h. It is necessary to provide the
optimum practical utility consumption targets in comparison to the utility
requirements for the un-optimized process design and the desired utility
system and heat exchanger network configuration. Desired targets shall
be calculated based upon life cycle cost analysis of the process and
energy systems. Detailed design of the heat exchanger network and
combined heat/power system to achieve desired targets is not required at
this stage.

4.5.2 For energy consuming or conversion equipment (pumps, compressors,


turbines, boilers, and furnaces) in parallel operation, the study shall
identify the optimum number of equipment that should be operated over
the expected range of plant operating rates, considering the trade-off
between energy consumption and meeting production goals. Load
management policies are required only when the energy consumption for
a particular service or application exceeds 1000 HP (if rotating
machinery) or 16 MM Btu/h (if fuel-fired equipment).

4.5.3 The economic feasibility of Adjustable Speed Drives (ASDs), whether


variable frequency type or other, shall be evaluated for individual
motors/drivers of 2000 HP or greater. Capital costs should be balanced
against the combined energy and non-energy benefits based upon life
cycle cost analysis.

Page 30 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

4.5.4 Rotating machinery with individual power loads of 5000 HP and higher
shall be evaluated for selection of optimum driver type – electric motor,
steam turbine, or gas turbine using life cycle cost analysis.

4.5.5 Energy efficiency for individual items of equipment (e.g., motors,


boilers, fired heaters, refrigeration packages, etc.) need to be evaluated
for alternative equipment options and/or addition of accessories such as
economizers for boilers, air pre-heaters for furnaces.

The optimum time to conduct such a study is the earliest possible date
after preliminary PFDs, including heat and material balances, are
available, and the plant fuel/power consumption estimates have been
determined. Generally, this would be after 30% completion of the
Project Proposal.

Study shall be conducted by a qualified independent third party from


Saudi Aramco’s current Approved Energy Consultants list. The scope of
work of this study including deliverables and study report acceptance
criterion will be developed by the Energy Systems Unit of Process and
Controls Systems Department (P&CSD).

The full energy optimization study report, including all supporting data
and calculations, must be submitted to the Energy Systems Unit of
Process and Controls Systems Department for review and approval.
A minimum of one week will be required for P&CSD review and
approval of the report.

4.6 Corrosion Management Program

Any new project or major upgrade of a process facility shall be required to


implement a Corrosion Management Program (CMP) as specified in Section 8
of Saudi Aramco Engineering Standard SAES-L-133. The purpose of the
program is to reduce the total cost of ownership and to minimize the operational,
safety, and environmental impact of corrosion and material failure.
The program will include an integrated plan to address all corrosion and
material degradation aspects, material selection, corrosion protection, corrosion
monitoring, chemical treatment and corrosion risk assessment for all mechanical
equipment, piping and fittings during the design, procurement, construction and
commissioning of the facility. The CMP shall be submitted for review and
approval by Materials Engineering & Corrosion Control Division, Consulting
Services Department (CSD).

Page 31 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

5 Reporting and Review Requirements

5.1 Project Proposal Distribution for Review and Meetings

Draft Project Proposals shall be distributed for review to the appropriate


members of Saudi Aramco Management and attendees of the Technical Review
and Project Proposal Meetings. Distribution of the Project Proposal narrative
shall be in electronic format (in Microsoft Word).

The E-Review electronic review system is the Company’s standard method for
review of engineering drawings and documents. SAPMT should submit review
packages through this system unless there is a compelling reason to do
otherwise. The E-Review procedures and guidelines are provided in SAEP-303.

The SAPMT and proponent are responsible for determining the recipients. As a
minimum, the following represents a list of various organizations that shall be
considered for receipt of the Project Proposal. However, only those
organizations with direct involvement shall receive the Project Proposal.

Executive Management:
- Proponent Organizations, i.e.;
Ras Tanura Refining
Northern Area Producing
Southern Area Producing
Jeddah/Riyadh Refining
Yanbu Refining
Distribution Operations
Abqaiq Plants & Pipelines
Gas Operations
Medical Services
Employee Relations
- Petroleum Engineering and Development
(for production-related projects)

General Management:
- Industrial Security Operations
- Proponent organization

Management:
- Oil Supply Planning and Scheduling Department

Page 32 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

(for all proposals related in any way to oil, gas, NGL and/or refined product
movement and handling)
- Computer & Communications Engineering Department
(for all projects involving communications)
- Purchasing Department
- Power Operations Department
(for all projects related to power facilities at 2.4 kV and above)
- Abqaiq, Dhahran or Ras Tanura Utilities Department
(for the area community projects only)
- Facilities Planning Department (mandatory)
- Project Management Office Department (for information only)
- Consulting Services Department
- Inspection Department
- Loss Prevention Department
- Environmental Protection Department
- Process & Control Systems Department
- Roads & Heavy Equipment Department
- Industrial Security Department
- Fire Protection Department

5.2 Technical Review Meeting

The Technical Review Meeting shall be held no sooner than ten (10) working
days after distribution of the Project Proposal for review. Location, date, and
time of the meeting shall be announced in the cover letter distributed with the
Project Proposal. The Technical Review Meeting shall discuss all technical
aspects of the Project Proposal, resolve technical questions, address
environmental issues and review the Project Summary Schedule. Interim
technical review meetings shall be conducted as required by SAPMT depending
upon the type and complexity of the project. Items not resolved at the final
technical review meeting shall be addressed in the Project Proposal Meeting.
Substantive changes resulting from the technical review meeting shall be
incorporated as appropriate into the Project Proposal documents.

SAPMT shall prepare minutes of the Technical Review Meetings and distribute
the minutes, electronically whenever possible, to all persons who either received
the Project Proposal or attended the Technical Review Meeting. The minutes
shall include the estimated cost and schedule effects of major changes from the

Page 33 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

DBSP/Project Proposal as originally prepared. Refer to 3.2.3 for definition of


major scope change.

The subject of critical plant equipment unit spares (capital spares) per Section
3.3.5 shall be addressed, and proposed purchases shall be reviewed.

5.3 Project Proposal Meeting

The purpose of the Project Proposal Meeting is to resolve any outstanding items
remaining after the Technical Review Meeting and to finalize the project scope.
The Project Proposal Meeting shall be scheduled no sooner than five (5)
working days after distribution of the minutes of the Technical Review Meeting.

The delegated representatives of the Project Proposal approval authorities


(Section 6.1.1) shall attend this meeting in order to make decisions on matters
not resolved in the Technical Review Meeting.

SAPMT shall be responsible for preparing and distributing the minutes of the
Project Proposal Meeting to those persons who either received a copy of the
Project Proposal or attended the Project Proposal Meetings.

For selected small projects, the Technical Review and Project Proposal
Meetings can be combined into one meeting if concurred by Proponent and
FPD. In this case, the reviewing organizations should send personnel authorized
to make decisions to attend the meeting.

5.4 Distribution & Storage of Approved Project Proposals

Following the approval of the Project Proposal, a final approved copy shall be
distributed as follows:

5.4.1 ASC

An electronic copy of every Project Proposal shall be sent to Corporate


Information Center (CIC), Houston.

5.4.2 Saudi Aramco

SAPMT shall send electronic copies of the approved Project Proposal to:
- Facilities Planning Department (FPD) - one hard copy, to be used as
a “working” document for five years or for the duration of the
project, whichever is longer.
- Technical Information Center (TIC) - one electronic copy for
archival purpose.

Page 34 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

- Project Management Office Department (PMOD) - one electronic


copy, for input in the Electronic Image Document Management
System.

The electronics file submissions shall be on CD-ROM and contain an


index at the beginning of each file medium to facilities retrieval of stored
date. The electronic text, spreadsheet, and graphical data shall be in
Microsoft format, and drawings shall be in accordance with Saudi
Aramco standards and formats. Scanned documents shall be in Acrobat
format in accordance with the corporate standard maintained by
EK&RD/Drawing Management Unit.

6 Approvals and Waivers

6.1 Approval Process

6.1.1 Approvals

SAPMT shall be responsible for obtaining Saudi Aramco approval for


the Project Proposal from the appropriate individuals listed. Executive
Management may delegate the approval authority to General
Management level. Obtaining these signatures constitutes full Project
Proposal approval. The recommended order for routing and approval
will be as follows, however, SAPMT may seek parallel approval from
more than one organization at the same time where appropriate.
- Manager, Facilities Planning Department
- Manager, Loss Prevention Department
- Manager, Power Operations Department
(for all projects having power facilities of 2.4 kV and above)
- Manager, Consulting Services Department
- Manager, Environmental Protection Department
- Manager, Oil Supply Planning and Scheduling Department
(for all proposals related in any way to oil, gas, NGL and/or refined
product movement and handling)
- Manager, Process and Control Systems Department
(for Instrumentation & Control Systems)
- General Manager, Industrial Security
- Vice President, Petroleum Engineering and Development
(for production-related projects)
- Vice President, Engineering Services

Page 35 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

- Vice President/Executive Director, Proponent Organization


- Vice President, Project Management

6.1.2 Unresolved Items

If unresolved items exist that would preclude obtaining approvals as


described in Section 6.1.1, SAPMT shall refer any unresolved item(s)
through appropriate channels of authority until resolution is obtained.

The Project Proposal minutes shall show the estimated cost and schedule
effects of any changes from the DBSP/Project Proposal as originally
prepared.

6.1.3 Obtaining Changes to an Approved Project Proposal

For a project with an approved Project Proposal which has not yet
received Expenditure Request (ER) approval, scope changes shall be as
follows:
 SAPMT will document and estimate all scope changes approved by
FPD and submit the revised ER estimate to PMOD as an addendum
to the approved Project Proposal
 The proposed change in the meeting minutes or an addendum shall
include justification and the cost/schedule/ risk impact
 The required minimal approval authority for the proposed change is
Project Manager level
 SAPMT shall distribute the approved changes to PMOD and all those
that received the original Project Proposal

6.2 Project Proposal Waiver

6.2.1 Request

For selected projects, Project Management may request to waive the


requirement for a Project Proposal / Front End Engineering Design
(FEED) and proceed directly with detailed design using preliminary
engineering funds. This request will permit SAPMT to use TC-68 funds
to carry out detailed design, perform selected project proposal
requirements and to prepare an ER quality estimate for funding approval.
Project Proposal waiver does not exempt ER Estimate and any other
Value Practices requirements.

Page 36 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

6.2.2 Approval

The following steps are required to obtain a waiver of project proposal


and proceed with detailed design:
 SAPMT Department Manager shall prepare a formal letter requesting
to carry out detailed design during Project Proposal. The letter shall
be addressed to Vice President, Project Management and Vice
President Proponent. The letter should state the present situation,
scope of work, justification for the waiver and identify what project
proposal requirements, if any that will be performed during detailed
design, i.e., value engineering, CII concepts, etc.
 SAPMT shall obtain Vice Presidents, Project Management and
Proponent approval for this request.
 On receiving approval, SAPMT shall prepare an Engineering Work
Order Authorization for Project Proposal Preparation (Form 6891-
ENG) to request approval of TC-68 funds to carry out detailed
engineering and contract preparation based on GI-0202.451,
(Engineering Work Order Authorization for Preliminary Engineering
Preparation).
 Approval is accomplished on obtaining the signature on Form
6891-ENG.

7 Contract Bid Package

The Contract Bid Package will be developed in close coordination with the Contracting
Department. Refer to Exhibit III, Contract Development Checklist, for key activities in
developing Contract Bid Package.

A complete Contract Bid Package shall be prepared in accordance with Contracting


Manual and typically contain the following:
 Invitation for Bid documents
 Technical Proposal documents
 Commercial Proposal documents
 As part of Commercial Proposal requirements, Bidders shall be required to submit a
Bid Quantification Summary as shown on Exhibit V for bid analysis purposes.
Copies of the final Bid Quantification Summary from the awarded Contractor will
be provided to PMOD
 Fully developed and approved Contract documents which include Schedules A
through H, and Q

Page 37 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Issue for Bid package (normally prepared by Engineering Contractor) which includes,
but is not limited to, drawings, specifications, applicable reports, and other relevant
documents necessary to define the project requirements and clearly describes the
contract scope of work. SAPMT should take into consideration the current project
execution plan and responsibilities of all contractual parties when revising the Project
Proposal package to “Issue for Bid” Package.

The following Sections in the Project Proposal should be reviewed carefully to


determine if they are applicable for inclusion in the bid package. If they are to be
included, SAPMT shall modify as required to ensure that Contractor’s scope of work is
clearly defined in the “Issue for Bid” Package:
 Project Schedule
 Training requirements
 Land Permits
 Operating Variables (as required by OSPAS)
 Strategy for projects compliance with quality requirements
 Project Risk Management Plan, Risk Assessment Report and Risk Register
 Temporary construction and communications

8 Exhibits

The intent of the checklists is to facilitate the review and ensure all key requirements
are considered, but not to cover all detailed requirements as stated in this procedure.

8.1 Project Proposal Checklist

8.2 ER Estimate Package Checklist

8.3 Contract Development Checklist

8.4 Sample of Benchmarking

8.5 Bid Quantification Summary

Revision Summary
4 April 2010 Revised the “Next Planned Update”. Reaffirmed the contents of the document, and reissued
with minor revisions.
12 February 2012 Editorial revisions to correct typo error “that to than” in 3.4.2 paragraph 3, changed
responsible department name from Project Support and Controls Department to Project
Management Office Department, etc.

Page 38 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

EXHIBITS

TABLE OF CONTENTS

EXHIBIT I PROJECT PROPOSAL CHECKLIST

EXHIBIT II ER ESTIMATE PACKAGE CHECKLIST

EXHIBIT III CONTRACT DEVELOPMENT CHECKLIST

EXHIBIT IV BENCHMARKING DATA SHEET

EXHIBIT V BID QUANTIFICATION SUMMARY SHEET

Page 39 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

EXHIBIT I – PROJECT PROPOSAL CHECKLIST

Ref.
Item Description Included
Section
Project Proposal documents as described in Section
1 3.2.2
3.2.2.
Obtain necessary land use permit
Obtain proponent approved permits for construction site
area
Complete piping tie-in and hot tap plan

Complete electrical and control system tie-in plan

Prepare site investigation report


Temporary and Permanent Project Communication
2 3.2.4
Requirements
3 3.2.5 Comply with Safety and Security Directive (SSD)

4 3.2.6 Perform HAZOP Study

5 3.2.6 Perform of Building Risk Assessment

6 3.2.7 Perform of Environmental Impact Assessment


Apply Waivers from SA Engineering Standards and
7 3.2.8
Material System Specification
Include a list of drawings and drawings define project
8 3.2.9
scope
Prepare Project Quality Plan as per GI-0400.001
9 3.2.10
including Schedule “Q” Att. VI
Identify project major material and equipment to be
10 3.3.1
reviewed by Inspection Dept.
Develop a Material Source List of major material and
11 3.3.2
equipment
Develop a Surplus Inventory and Excess material
12 3.3.3
Listing

Page 40 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Ref.
Item Description Included
Section
Obtain a list of approved locally manufactured products
13 3.3.4
and source
14 3.3.5 Develop a list of critical plant equipment spares
Identify required start-up spares with Proponent with
15 3.3.6
concurrence of MS
16 3.4.1 Prepare Level III Project Summary Schedule
Prepare ER Estimate Package ( See Exhibit II - ER
17 3.4.2
Estimate Package Checklist)
Review Project Training Impact Assessment
18 3.7
(SAEP-140) and identify required implementation
19 4.1 Perform Value Engineering Study

20 4.2 Perform Project Risk Management Study

21 4.3 Perform Value Practices

1. Constructability Study

2. Project Definition Rating Index (PDRI)

3. Lesson Learned

4. Project Execution Planning Workshop

5. Schedule Optimization

6. Planning for Startup

7. Scope Control and Change Management

22 4.3 Perform Energy Optimization Study


Perform Benchmarking Analysis & provide project data
23 4.4
for Internal Benchmarking

Page 41 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

EXHIBIT II – ER ESTIMATE PACKAGE CHECKLIST

Following are minimum documents required to accompany the ER Estimate Request


to PMOD:

Item Description Included


100% Project Proposal package ( Project Proposal must be
1
approved prior to issuance of 56D)
2 Approved technical review meeting minutes
Project Scope summary including new as well as demolition of
3
existing facilities.
4 Internal/External Benchmarking data

5 Piping and Instrument Diagrams (P&ID’s)

6 Plot plan showing major facilities/buildings

7 Proposed Piping lay-out and routing


Electrical scope with one-line diagrams, MTO quantities for
8
Transformers, Switchgear, etc.
9 Field Instrument specifications and Data Sheets
Control system (DCS) scope with I/O counts, Block Flow
10
Diagrams and Vendor Quotations
11 Communications System scope including, MTO and quotations

12 Fire Protection, Safety and Security requirements

13 Building/Equipment data sheets

14 Material specifications including Materials Diagram.

15 DC Surplus, etc.

16 Identify Start-Up and Capital Spares

17 Catalyst, Chemicals & Licensor Fee costs.

18 HAZOP Review report if applicable.

Page 42 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Item Description Included

19 Site survey and soil data report

20 List of Deviations from DBSP with cost/schedule impact

21 Copy of Approved Waivers

22 SAPMT/PMC, Insp., CMT & other related costs

23 Exploratory Trenching

24 Environmental Assessment (Contamination)

25 Approved Project Schedule

26 Approved Project Execution Plan


Contracting and Material Procurements Plans. Identify customs
27
duties.
Detail Engineering Equivalent A size Drawings count and man
28
hours
29 Detail Design Location – i.e., (IK or OOK)

30 Draft ER brief and BISI from FPD

31 Facility Location and Camp Requirements

32 Identify Commissioning and As-Built Requirements

33 Quality Material take-off (MTO)

34 Process Equipment list, sizes, capacities & specifications.


Recent (valid for 3 months) quotations for major equipment &
35
material
36 Project Risk Management Plan and Risk Assessment Report

37 Commissioning and Start-up Plan

Page 43 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

EXHIBIT III – CONTRACT DEVELOPMENT CHECKLIST

Following are the list of key activities for developing the contract package.

Item Description Included


Contracting Strategy
Develop and Approve Contracting Strategy – Required as part of
1 the Abbreviate PEP for all projects (SAEP-12). Strategy is to be
updated if there are changed during the progress of the project.
Enter and maintain data on all contract action covered by the
2 Contracting Strategy in to the PMIS Contracting Action
Development and Administration (CADA) module.

Pro Forma Contract & Specific Instructions to Bidders (SIB)


Complete preliminary Evaluation Plan so appropriate technical
3
and commercial questions are included in the SIB.
Secure approvals for all singe source procurement and included
4
appropriate language in Schedule “H.”
Complete Schedule “Q” language in accordance with approved
5 Quality Plan (GI-0400.001) and review proposed language with
Inspection as needed.
Include language relating to approved training requirements in the
6 form of a preliminary TIA consisting of the knowledge and skills
matrix and approved training requirements’ language (SAEP-140).
Review any language related to contractor-supplied LAN and PC
7
equipment with the appropriated IT office(s).
Include requirements for bidder price breakdowns as part of the
8 Commercial Proposals and quantity lists as part of the Technical
Proposals.

Hypothetical Quantities and Bid Conditioners


Prepare hypothetical quantities to be used to evaluate rates
9
proposed by the bidders (e.g., change order rates).
Prepare, in conjunction with other members of the Bid Review
10 Team, data to be used for allowed bid conditioner (e.g., different
PMT cost for various locations).

Page 44 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

Item Description Included


Review of Contract and Contract Supplement as Part of the Bid
Review Team
Ensure the Contract is structured correctly for SAP SRV releases
(for lump sum, three items – lump sum price, change orders, and
11
other expenditures; and use of “VAL” with the amount in the
“quantity” column).
Ensure that that AEL includes reasonable amounts for all
applicable “Other Expenditures” (e.g., incidental services, Saudi
12 manufacturer equalization, stand-by time, reimbursable start-up
and commissioning assistance, variations from target quantities,
etc.).
Ensure the Contract Supplement includes an appropriate Change
13
Order limit (percent).

After award of the contract, provide copies of the bidders’ price


14
breakdowns and quantity lists to PMOD.

Note: For a project using an LSTK contracting strategy, these actions are required during or
just after the Project Proposal period. For other strategies (e.g., GES + LSPB) some of
the activities take place at later stages of the project.

Page 45 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

EXHIBIT IV – BENCHMARKING DATA SHEET


for
CRUDE PRODUCTION FACILITY (GOSP)

BUDGET ITEM (BI) : ERA :


JOB ORDER (JO) : ERC :
DESCRIPTION :

UNIT
AREA NAME PARAMETER UOM QUANTITY COST
COST

QUANTITY OF SCRAPER TRAPS EACH $ $


QUANTITY & SIZE (INCHES) OF TRAP A EACH
INLET FACILITY QUANTITY & SIZE (INCHES) OF TRAP B EACH
QUANTITY & SIZE (INCHES) OF TRAP C EACH
TOTAL INSTALLED COST (INLET
FACILITY) DOLLARS $ $

UNIT CAPACITY MBD $ $


NUMBER OF HIGH PRESSURE TRAPS EACH
NUMBER OF INTERMEDIATE PRESSURE
TRAPS EACH
PRODUCTION NUMBER OF LOW PRESSURE TRAPS EACH
TRAP
WATER CUT % VOL
GAS OIL RATIO
CRUDE TYPE (AL/AM/AXL/ASL) or ºAPI
TOTAL INSTALLED COST (PRODUCTION
TRAP) DOLLARS $ $

UNIT CAPACITY MMSCFD $ $


HP COMPRESSORS QUANTITY EACH
HP COMP DRIVER TYPE (MOTOR/CGT) EACH
IP COMPRESSORS QUANTITY EACH
IP COMP DRIVER TYPE (MOTOR/CGT) EACH
GAS GATHERING LP COMPRESSORS QUANTITY EACH
LP COMP DRIVER TYPE (MOTOR/CGT) EACH
HP COMPRESSORS TOTAL HP HP
IP COMPRESSORS TOTAL HP HP
LP COMPRESSORS TOTAL HP HP
TOTAL INSTALLED COST (GAS
GATHERING) DOLLARS $ $

Page 46 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

NUMBER DESALTING STAGES EACH


WET CRUDE
HANDLING & UNIT CAPACITY MBD $ $
WOSEP TOTAL INSTALLED COST (WET CRUDE
HANDLING & WOSEP) DOLLARS $ $

CONDENSATE UNIT CAPACITY MBD $ $


STABILIZATION TOTAL INSTALLED COST (CONDENSATE
STABILIZATION) DOLLARS $ $

CRUDE
STABILIZATION UNIT CAPACITY MBD $ $

UNIT CAPACITY MBD $ $


QUANTITY OF PUMPS EACH
WATER INJECTION
FACILITY PUMPS TOTAL HP HP
PUMP DRIVER TYPE (MOTOR/CGT) EACH
TOTAL INSTALLED COST (WATER
INJECTION FACILITY) DOLLARS $ $

COGENERATION
FACILITY ISO RATING MW $ $

TONNAGE STEEL (PIPERACK) TONS $ $


TONNAGE PIPE TONS $ $
WIDTH OF PIPERACK LM
LENGTH OF PIPERACK LM
PIPERACK &
PIPING HEIGHT PIPERACK LM
LEVELS OF PIPERACK EACH
TOTAL LENGTH OF ALL PIPES LM
TOTAL INSTALLED COST (PIPERACK) DOLLARS $ $
TOTAL INSTALLED COST (PIPING) DOLLARS $ $

SITE PREPARATION SM $ $
CONCRETE CM $ $
STRUCTURAL STEEL TONS $ $
FENCING LM $ $

SUPPORT CONTROL BUILDINGS (ALL BLDGS) SM $ $


INFRASTRUCTURE PIBS (ALL BLDGS) SM $ $
OTHER TYPES OF BUILDING SM $ $
SUBSTATION SM $ $
TOTAL INSTALLED COST (SUPPORT
BLDGS ONLY) DOLLARS $ $
TOTAL INSTALLED COST
(INFRASTRUCTURE) DOLLARS $ $

Page 47 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

BOILER QTY EACH $ $


BOILER CAPACITY LBS/HR
BOILER PRESSURE PSIG
COOLING TOWER CAPACITY GPM $ $
AIR COMPRESSOR QTY EACH $ $
OFFSITES &
UTILITIES AIR COMPRESSOR CAPACITY SCFM
FLARE SIZE SCFM $ $
FIREWATER SYS CAPACITY GPM $ $
NITROGEN GEN SYS CAPACITY SCFM $ $
WATER TREATMENT FACILITY GPM $ $
TOTAL INSTALLED COST (OFFSITES &
UTILITIES) DOLLARS $ $

TRANSMISSION LINE LENGTH KM $ $


TRANSMISSION LINE VOLTAGE KV
SWITCHYARD VOLTAGE KV $ $
MAIN SUBSTATION EACH $ $
MAIN SUBSTATION KVA $ $
ELECTRICAL
UNIT SUBSTATION EACH $ $
UNIT SUBSTATION KVA $ $
ELECTRICAL CABLE TRAY LM $ $
ELECTRICAL CABLE LM $ $
TOTAL INSTALLED COST (ELECTRICAL) DOLLARS $ $

DIGITAL CONTROL SYSTEM (DCS) I/O $ $


EMERGENCY SHUTDOWN SYSTEM (ESD) I/O $ $
VIBRATION MONITORING SYSTEM (VMS) I/O $ $

PROCESS WORKSTATIONS QTY EACH $ $


CONTROLS
NEW TRANSMITTERS QTY EACH $ $
INSTRUMENTATION CABLE TRAY LM $ $
INSTRUMENTATION CABLE LM $ $
TOTAL INSTALLED COST (PROCESS
CONTROLS) DOLLARS $ $

FIBER OPTIC CABLES LM $ $


COMMUNICATIONS COMMUNICATION EQUIPMENT EACH $ $
TOTAL INSTALLED COST
(COMMUNICATIONS) DOLLARS $ $

OTHERS LIST MISCELLANEOUS FACILITIES EACH $ $

Page 48 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

ENGINEERING (PROJECT PROPOSAL) MHRS $ $


ENGINEERING (DETAIL DESIGN) MHRS $ $
ENGINEERING
ENGINEERING (PMT SUPPORT) MHRS $ $
TOTAL COST (ENGINEERING) DOLLARS $ $

DIRECT CONSTRUCTION MHRS $ $


INDIRECT CONSTRUCTION MHRS $ $
CONSTRUCTION
CONSTRUCTION (PMT SUPPORT) MHRS $ $
TOTAL COST (CONSTRUCTION) DOLLARS $ $

CRUDE PRODUCTION FACILITY (GOSP) MBD $ $

ACTIVITY DESCRIPTION IN MONTH(S)

PROJECT PROPOSAL (PP) DURATION


PROJECT PROPOSAL (PP) TO ERA DURATION
DETAIL DESIGN DURATION
ERA-MCC DURATION
SCHEDULING
CONSTRUCTION DURATION
START-UP & COMMISSIONING DURATION
MATERIAL & EQUIPMENT WITH MORE THAN 6 MONTHS LEAD-TIME
DELIVERY

VALUE
LIST OF VALUE PRACTICES IMPLEMENTED
PRACTICES

CONTRACTING TYPE OF CONTRACT TO BE EXECUTED (LSTK, OPENBOOK, LSPB,


STRATEGY LSCR, etc.)

Page 49 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

EXHIBIT V – BID QUANTIFICATION SUMMARY SHEET

PROJECT TITLE : BI :
CONTRACT
NUMBER : JO :
CONTRACT TYPE :
:

SUMMARY OF COST
BY WORK BREAKDOWN STRUCTURE (WBS)
BULK
AREA OF WORK ENGINEERING CONSTRUCTION TOTALS
MATERIALS

AREA OF WORK 1 $ $ $ $
AREA OF WORK 2 $ $ $ $
AREA OF WORK 3 $ $ $ $
AREA OF WORK 4 $ $ $ $
TOTAL PROJECT COST $ $ $ $

SUMMARY OF QUANTITY AND COST


BY DISCIPLINE
DISCIPLINE DESCRIPTION UNIT QUANTITY COST UNIT COST

DEMOLITION
(SCA 007)
TOTAL DEMOLITION WORK COST LUMPSUM $ $

SITE PREPARATION /
DEVELOPMENT
(PLOT SIZE) SM $ $
CONCRETE CM $ $

CIVIL / STRUCTURE FENCE LM $ $


(SCA 200 & 400)
LANDSCAPING & IRRIGATION SM $ $
STRUCTURAL STEEL TONS $ $
BUILDINGS (TYPE OF BLDGS) SM $ $
TOTAL CIVIL/STRUCTURE
MANHOURS & COST MHRS $ $

Page 50 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

STATIC EQUIPMENT EACH $ $


HEAT EXCHANGERS EACH $ $

MECHANICAL/ AIR COOLERS EACH $ $


PROCESS PUMPS EACH $ $
EQUIPMENT
(SCA 500) COMPRESSORS EACH $ $
OTHER PACKAGE EQUIPMENT EACH $ $
TOTAL MECHANICAL/PROCESS
EQUIPMENT MANHOURS & COST MHRS $ $

LENGTH OF PIPERACK LM $ $
TONNAGE CARBON STEEL
(PIPERACK) TONS $ $
UNDERGROUND CARBON STEEL
PIPING PIPING LM $ $
(SCA 600) ABOVEGROUND CARBON STEEL
PIPING LM $ $
TONNAGE CARBON STEEL PIPES TONS $ $
TOTAL PIPING MANHOURS &
COST MHRS $ $

TRANSMISSION LINE LENGTH KM $ $


MAIN SUBSTATION MW $ $
UNIT SUBSTATION MW $ $
ELECTRICAL ELECTRICAL CABLE TRAY LM $ $
(SCA 700) UNDERGROUND ELECTRICAL
CABLE LM $ $
ABOVEGROUND ELECTRICAL
CABLE LM $ $
TOTAL ELECTRICAL MANHOURS &
COST MHRS $ $

PROCESS CONTROL SYSTEM


(DCS/ESD/VMS) I/O $ $
CONTROL VALVE COUNT
(MOV/GOV/MANUAL) EACH $ $
FIELD INTRUMENTS
(TRANSMITTERS/TGS) EACH $ $
INSTRUMENTATION
(SCA 800) INSTRUMENTATION CABLE TRAY LM $ $
UNDERGROUND
INSTRUMENTATION CABLE LM $ $
ABOVEGROUND
INSTRUMENTATION CABLE LM $ $
TOTAL INSTRUMENTATION
MANHOURS & COST MHRS $ $

FIBER OPTIC CABLES LM $ $


COMMUNICATIONS
(SCA 780) COMMUNICATION EQUIPMENT EACH $ $
TOTAL COMMUNICATIONS
MANHOURS & COST MHRS $ $

Page 51 of 52
Document Responsibility: Project Management Office Department SAEP-14
Issue Date: 13 February 2012
Next Planned Update: 4 April 2013 Project Proposal

INSULATION AND FIREPROOFING


INSULATION & (EQUIPMENT, STRUCTURES,
COATINGS BUILDINGS, etc.) $ $
(SCA 900) TOTAL INSULATION & COATINGS
MHRS & COST MHRS $ $

TOTAL DIRECT CONST


MANHOURS & COST MHRS $ $
TOTAL INDIRECT CONST
CONSTRUCTION
MANHOURS & COST MHRS $ $
TOTAL CONSTRUCTION
MANHOURS & COST MHRS $ $

TOTAL ENGINEERING MANHOURS


ENGINEERING
& COST MHRS $ $

TOTAL PROJECT COST DOLLARS $ $

ACTIVITY IN MONTH(S)
DETAIL DESIGN DURATION
SCHEDULING
CONSTRUCTION DURATION
EQUIPMENT WITH MORE THAN 6 MONTHS LEAD-TIME
DELIVERY

Page 52 of 52

You might also like