METHOD STATEMENT
Corporate Office:
PSP House,
Opp. Celesta Courtyard,
Opp. Lane of Vikramnagar Colony,
ISCON-Ambli Road,
Ahmedabad – 380058.
Tel Nos.: +91 -079 – 2693 6200, 2693 6300, 2693 6400
Fax Nos.: +91–079 – 2693 6500
E Mail: coordination@pspprojects.com
Web: www.pspprojects.com
1|Page
Project: Maruti Suzuki Hospital – Sitapur
CONTENTS
1 Introduction
2 Scope of Work
3 References and Standard
4 Material
5 Temporary Services
6 Methodology
7 Quality Assurance
Sign
Name
Date
1. Introduction:
2|Page
Project: Maruti Suzuki Hospital – Sitapur
This method statement describing the outline procedure to be followed for Plumbing Work to
be executed at Maruti Hospital, Sitapur.
2. Scope of Work:
Plumbing Work.
4. Material:
3|Page
Project: Maruti Suzuki Hospital – Sitapur
d) Shaft Piping
Check for funnels on the plastered shaft dividers as indicated by points of interest in the
working illustrations. Guarantee that the plastering is finished as it will be practically
difficult to plaster dividers after the pipes are set up.
Fix brackets as per details shown on the working drawings. A clear gap of 25 to 50mm
shall be maintained between pipe and wall surface.
Clamp pipe assemblies on to the brackets. ensure the pipes area unit in ‘line’ (horizontal
runs) or in ‘plumb’ (vertical stacks). Wherever enlargement / contraction is a priority,
make sure that pipes don't seem to be stiffly command to brackets.
Make cut-outs on the shaft walls for branch pipes at locations shown on the drawings.
Provide branches on the pipe assembly for connections to internal pipe work. Provide
uninflected valves on water system pipes at locations shown on operating drawings; at
simply approachable heights.
Test the pipes for leaks under specified pressure for the specified duration.
Tests must be witnessed and approved by client’s representative.
Paint the pipes as per approved colour code and provide identification labels where called
for.
4|Page
Project: Maruti Suzuki Hospital – Sitapur
Take measurement of pipes installed. A client representative must be present and should
acknowledge the records.
Terminate soil, waste and vent pipes with vent cowls at such heights higher than terrace
level. Make sure that vent cowls don't seem to be terminated among one meter
(horizontally and vertically) from any window openings.
Terminate installation risers with automotive air vents (with analytic valves) and down
pipes with drain plug/drain valve – all as per drawings. Make sure that installation pipe
work would be self-venting and self-draining.
Connect the soil stack to inspection chamber at ground level.
Connect waste stacks to the gully trap at ground level. Connect the gully trap to the
inspection chamber.
5|Page
Project: Maruti Suzuki Hospital – Sitapur
Ensure that pipes area unit in correct slope and area unit supported adequately. invariably
make sure that the spacing of supports is as per specifications. make sure that floor traps
area unit put in level (not tilted) so the water seal isn't diminished
Test the pipes with free flow test by means of water and attend to leaks, if any.
Manage the filling of depressed floors by civil contractual worker with the goal that the
arrangement and incline of waste funnels are not disturbed. It is in the pipes contractual
worker's enthusiasm to guarantee that water sealing of the center drills is done and tested.
Keep all open ends plugged to prevent ingress of construction debris.
i) Flanged Pipes
Two practical points need to be noted when setting up flanged piping
Care must be taken not to tighten up the flange bolts until it is certain that the exact
alignment required has been achieved. If there is lack of alignment between flanges the
tightening of the bolts can break the flange.
The stipulations of the appropriate IS code must be strictly adhered which are generally
followed by the manufacturers/suppliers.
6|Page
Project: Maruti Suzuki Hospital – Sitapur
j) Testing of Works
The works to be tested on site, pipeline laying and jointing, and hydrostatic leakage and
water tightness tested after completion.
All the materials proposed to be used in these works must have been tested by the
Contractor.
Required materials tests to be carried out.
The full requirement, for the testing of pipelines, is given within the provisions of the
contractor’s contract and specifications. Every section of pipeline laid must be tested
before it can be accepted by the supervising engineer.
The test should be carried out at specified pressure and any resulting losses should be
within the stipulated permissible levels.
The pipeline should only be accepted after ensuring losses within the permissible levels,
under the full terms of testing.
The test Pressure applied should not exceed following:
a) The designed maximum operating pressure in system.
b) The designed pressure rating of the pipe
c) The designed pressure rating of any system component, whichever is lowest.
A pressure test should be conducted at 150% of the working pressure in the line. The
working pressure is defined as maximum anticipated sustained pressure in the line being
tested. The working pressure shall be 3 bars for our design. (ref. Hydraulic calculations)
a) Plumbing water supply pressure testing Hyd. pressure test at 82®C required 36.5
Kgf/cm2.
b) Plumbing Upvc pressure test as per confirm IS 4985 (2000)
7. Quality Assurance:
a) Water supply &distribution system:
After all the joint completion & joint curing shall be ensured before performing
Hydro test.
Water supply pipeline & its assembly shall be tested with water at hydrostatic test
pressure of 7 Kg/cm2.
The leak proof shall be ensuring for 12 hours; individual joints shall be checked for
water moisture.
The pipeline shall be in case of drastic pressure drop at leaky joints & retested.
b) Drainage system:
All the vertical riser shall be installed with Upvc pipes as per IS: 4985 graded for 6
Kg/cm2 pressure rating or as per tender & on floor toilet pipes shall be installed with
UPVC pipe as per IS: 13592 graded for 6 Kg/cm2 pressure rating should be tested for
free flow test by means of water.
The pipes shall be provided with necessary supporting arrangement made of firm
Universal support system at recommended interval of Min.1.5m depending upon pipe
size & load.
7|Page
Project: Maruti Suzuki Hospital – Sitapur
The Horizontal overhead pipes shall be installed as per drawing & necessary slope to
be Maintained as per drawing.
8|Page