Measurement

Item Particular Qty. Dedu; Content Total of Each Unit


L B H

1 1 0

1 Site Clearing, Suverying & Layout Profiling. 1 1 1 82'- 0'' 57'- 0'' 4674 4674

1 1 0 0

1 1 0 0 4674.00 Sft

1 1 0 0

2 Earthwork Excavation . 1 1 0 0

Footing 1 1 0 0

Main Building 1 1 0 0

F1 1 1 2 5'- 0'' 5'- 0'' 6'- 0'' 300 300

F2 1 1 8 6'- 0'' 6'- 0'' 6'- 0'' 1728 1728

F3 1 1 6 6'- 6'' 6'- 6'' 6'- 0'' 1521 1521

F4 1 1 6 7'- 0'' 7'- 0'' 6'- 0'' 1764 1764

F5 1 1 2 7'- 6'' 7'- 6'' 6'- 0'' 675 675

Portico 1 1 0 0

F1 1 1 2 5'- 0'' 5'- 0'' 6'- 0'' 300 300

Retaining Wall 1 1 0 0

X-axis 1 1 0 0

Main Building 1 1 0 0

Line 1+3 (70'-0" Span) 1 1 2 37'- 0'' 2'- 6'' 3'- 6'' 647.5 647.5

Line 2 (70'-0" Span) 1 1 1 34'- 6'' 2'- 6'' 3'- 6'' 301.88 301.88

Line 4 (70'-0" Span) 1 1 1 41'- 0'' 2'- 6'' 3'- 6'' 358.75 358.75

Bath & W/C (7'-0" Span) 1 1 4 4'- 6'' 2'- 6'' 3'- 6'' 157.5 157.5

Stair Case (10'-0" Span) 1 1 1 7'- 6'' 2'- 6'' 3'- 6'' 65.63 65.63

Portico 1 1 0 0

Line 5 (10'-0" Span) 1 1 1 5'- 0'' 2'- 6'' 3'- 6'' 43.75 43.75

Y-axis 1 1 0 0

Main Building 1 1 0 0

Line A & F (30'-0" Span) 1 1 2 12'- 0'' 2'- 6'' 3'- 6'' 210 210

Line B & E (30'-0" Span) 1 1 2 9'- 0'' 2'- 6'' 3'- 6'' 157.5 157.5

Line C & D (30'-0" Span) 1 1 2 10'- 3'' 2'- 6'' 3'- 6'' 179.38 179.38

Bath & W/C (10'-0" Span) 1 1 4 7'- 6'' 2'- 6'' 3'- 6'' 262.5 262.5

1 1 0 0 8672.39 Cft