linked together through common objectives, a common budget, and intertwined schedules and
strategies?
A program can be seen as a group of projects and time-bound tasks that are closely linked together
through common objectives, a common budget, and intertwined schedules and strategies. The other
answers represent similar project management concepts that an auditor should be aware of, but each
serves a different purpose
A program
A portfolio
A procedure
A plan
The objective of program management is the successful execution of programs which include the
management of all except which of the following?
The objective of program management is the successful execution of programs which include the
management of a program scope, schedule, and communication. Program poolitics is not a defined
program management concept, although politics are present in most every project in an organization
Program Scope
Program Politics
Program Schedule
Program Communication
<F9B763AE-C084-4D45-8152-E0C809D0B5BB}">
Which of the following is defined as all the projects being carried out in an organization at a given
point in time?
A project portfolio is defined as all the projects being carried out in an organization at a given point
in time. The other concepts are valid project and program management concepts that an auditor should
be aware of, but with different definitions
< A project portfolio is defined as all the projects being carried out in an organization at a given point
in time. The other concepts are valid project and program management concepts that an auditor should
be aware of, but with different
definitions.</font></p></textformat></incorrectAnswerFeed
Project Portfolio
Project Charter
Project Schedule
Ghannt Chart
Which of the following is generally considered an owner of the project management and program
management process?
A Project Management Office (PMO) is generally considered an owner of the project management
and program management process. The important thing to remember here is that it manages the
process of project management. PMOs are not business sponsors, but they facilitate the management of
the project process itself
Business Owner
Executive Sponsor
Which of the following is generally NOT considered one of the objectives of project portfolio
management?
Project sponsorship is generally NOT considered one of the objectives of project portfolio
management. However prioritizing and scheduling projects, resource coordination, and knowledge
transfer throughout the project is generally considered valid objectives
Resource coordination
Project sponsorship
An initial business case would generally derive from which of the following?
An initial business case would generally derive from a feasibility study. The other concepts are also
valid project management concepts, but they do not occur at the same point in the project management
lifecycle
Feasibility study
Project portfolio
Ghannt Chart
The busines case for a project should answer which of the following questions?
The busines case for a project should answer the question, &quot;why should this project be
undertaken?&quot; Project sponsorship, budgets, and schedule are important aspects to consider,
but they occur later in the project planning process
The process of benefits management for Information Technology related projects generally does
NOT require which of the following?
The process of benefits management for Information Technology related projects generally does
NOT require determining the budget necessary for completion. This is a planning issue during a project,
but it is not considered part of the benefits analysis process, while the other choices are
The process of benefits management for Information Technology related projects generally does
NOT require which of the following?
The process of benefits management for Information Technology related projects generally does
NOT require defining the project manager and sponsor. This is a planning issue during a project, but it is
not considered part of the benefits analysis process, while the other choices are
Benefits realization often includes a postimplementation review of how long after the
implementation of systems?
Benefits realization often includes a postimplementation review of 6-18 months after the
implementation of systems. This is length of time determined by ISACA and other sources to be an
appropriate length to be able to determine benefits realization
1-3 months
3-6 months
6-18 months
18-24 months
Which of the following is generally NOT considered one of the de facto standards and organizations
for project management?
SPICE, while a valid software development methodology and maturity definition, is generally NOT
considered one of the de facto standards and organizations for project management. The PMBOK,
PRINCE2, and IPMA are generally all considered valid sources
PMBOK
PRINCE2
IPMA
SPICE
Which of the following can be perceived not only as a group of complex tasks, bust also as a social
system and/or a temporary organization?
A project can be perceived not only as a group of complex tasks, bust also as a social system and/or
a temporary organization. The other concepts are related project management concepts, but have
different purposes and definitions
Project
Portfolio
Program
Charter
A project context can be divided into which of the following two contexts?
A project context can be divided into a time and a social context. Financial and procedural contexts
are generally not considered contexts in the same light
Time and Social
Which of the following by definition has a specific start and end date?
A project by definition has a specific start and end date. Portfolios and programs are not bound by
the same time restrictions and charters are generally time time oriented aspects of a project
Project
Portfolio
Program
Charter
Which of the following is generally NOT considered a major form of organizational alignment for
project management?
A scaled project organization is generally NOT considered a major form of organizational alignment
for project management. Influence, pure, and matrix project organizations are common organizational
approaches to project management
In which of the following project organizations does the project manager have only a staff function
without formal management authority?
In an influence project organization the project manager have only a staff function without formal
management authority. The other forms or project organization do not meet the same definition
In which of the following project organizations does the project manager have formal authority over
those taking part in the project?
In a pure project organization the project manager have formal authority over those taking part in
the project. The other forms or project organization do not meet the same definition
Influence project organization
In which of the following project organizations does the project manager share management
authority with department heads?
in a a matrix project organization the project manager share management authority with
department heads. The other forms or project organization do not meet the same definition
Requests for major projects in an organization should be submitted to which of the following groups?
Requests for major projects in an organization should be submitted to the IS steering committee.
This group is generally composed of individuals responsible for setting the strategy for information
systems and therefore must directly approve new projects. The other groups will often exert influence
on the process but will not be the direct decision makers
Which of the following is NOT commonly used as a form of communication when initiating the
project management project process?
Budget strategy meetings are NOT commonly used as a form of communication when initiating the
project management project process. The other answers all represent valid methods for initial project
communication
One-on-one meetings
Kick-off meetings
Kick-off meetings are project initiation communication meetings that may be used by the project
manager to inform the team of what has to be done for the project. The other meeting types are not
generally used for this purpose
One-on-one meetings
Kick-off meetings
Which of the following project initiation communication meetings is a preferred method to ensure
that communication is open and clear among the project team?
Project start workshops are project initiation communication meetings that are a preferred method
to ensure that communication is open and clear among the project team. The other meeting types are
not generally used for this purpose
One-on-one meetings
Kick-off meetings
Which of the following job titles is generally NOT a part of project management steering
committees?
Quality assurance team members are generally not a part of a project management steering
committee. Senior management, project sponsors, and user managers however will often play a part in
this reponsibility according to the organizational charts defined by ISACA
Quality assurance
Senior management
Project sponsor
User management
Which of the following project objective types will always be directly coupled with business success?
Main objectives are project objective types that will always be directly coupled with business
success. The other objectives should still be considered in the course of managing a project, but they are
used for different purposes
Main objectives
Additional objectives
SMART objectives
Nonobjectives
Which of the following project objective types add clarity to scope and help project boundaries to be
clearer?
Nonobjectives are project objective types that add clarity to scope and help project boundaries to be
clearer. The other objectives should still be considered in the course of managing a project, but they are
used for different purposes
Main objectives
Additional objectives
SMART objectives
Nonobjectives
Which of the following project objective types are objectives that are not directly related to the main
results of the project but may contribute to project success?
Additional objectives are project objective types that are objectives that are not directly related to
the main results of the project but may contribute to project success. The other objectives should still be
considered in the course of managing a project, but they are used for different purposes
Main objectives
Additional objectives
SMART objectives
Nonobjectives
Which of the following approaches to define project objectives represents the individual components
of the solution and their relationship to each other in a hierarchical manner?
An Object Breakdown Structure (OBS) is an approach to define project objectives represents the
individual components of the solution and their relationship to each other in a hierarchical manner. This
is different from a Work Breakdown Structure, work package, or network diagram that may also be used
in the management of a project
Work Package
Network Diagram
Which of the following represents the project in terms of manageable and controllable units of work,
serves as a central communications tool in the project, and forms the baseline for cost and resource
planning?
A Work Breakdown Structure (WBS) represents the project in terms of manageable and controllable
units of work, serves as a central communications tool in the project, and forms the baseline for cost
and resource planning. This is different from an Object Breakdown Structure, work package, or network
diagram that may also be used in the management of a project
Work Package
Network Diagram
Which of the following is a list of actions to be carried out in relation to work packages and includes
assigned responsibilities and deadlines?
A task list is a list of actions to be carried out in relation to work packages and includes assigned
responsibilities and deadlines. The other concepts are also used by project managers to manage the
progress of a project, but they are used for different purposes
Task List
Network Diagram
Tasks lists, once compiled into a project schedule, are used to monitor and track the completion of
work packages in which of the following phases of the project?
Tasks lists, once compiled into a project schedule, are used to monitor and track the completion of
work packages in the controlling phase of project management. The other phases of project
management are valid, but other project issues are addressed during those phases
Planning
Controlling
Initiation
Closing