KARNAPHULI WATER SUPPLY PROJECT-Phase 2

FIELD HYDRAULIC PRESSURE TEST OF DMA NETWORK RECORD SHEET


Contract No KWSP2/W-3-…. Primary / Secondary / Tertiary Date:

Location DMA – …….

Working pressure: 4 bars (0.4 Mpa) Test Pressure: 6 bars (0.6 MPa)

Size/Type Length (m) Location /Remarks

Pipeline Details

All permanent thrust blocks complete : ☐ Yes ☐ NO

All permanent valves installed: ☐ Yes ☐ NO

Temporary air release points provided : ☐ Yes ☐ NO


Preparation
Water Source: …………………………………………………………………………..
Start time of filling: ………………………………………………….

Start time of working pressure reached: ………………(maintain 24 hrs min)

Start time of test pressure reached: …………………………

Pressure (bars)
Time (Clock) Tim (hr: min) Volume Added (L)
Before filling After filling

0:00 Start N/A


0:30
Pressure Testing
Record at P0 1:00
(Feeding Point) 1:30
2:00
2:30
3:00
3:30
4:00 End Total Volume:
………….

Pressure (bars) at other Pressure Gauges before and after filling

Hydraulic Pressure Testing Record for DMA-J2 Page 1 of 2


Pressure (bars)

Time Time P1 P2 P3 P4 P5
(Clock) (hr: min)
Befor Befor Befor
Before After Before After After After After
e e e

0:00 Start Start Start Start Start


0:30
1:00
1:30
2:00
2:30
3:00
3:30
4:00 End End End End End
Note: If the end of 2 hours, the pressure of pipe line does no drop, then the testing has to be stopped.

Maximum allowable volume [0.001389 Litre x dia (mm) x Length (km)


………..(Litres)
x Duration (hr) x Pressure (bars)]

Recorded maximum % pressure drop during last 30 min ……….


Results Analysis
Is volume added less than allowable? ☐ Yes ☐ NO

Is maximum pressure drop during last 30 min less than 10%? ☐ Yes ☐ NO

TEST ☐ PASSED ☐ FAILED

Comments

…………………………………… .……………………………………
CGC (Name, Signature and Date) NJS (Name, Signature and Date)

Hydraulic Pressure Testing Record for DMA-J2 Page 2 of 2