ID Task Task Duration Start Finish Predecessors

Oct 19, '20 Oct 26, '20 Nov 2, '20 Nov 9, '20 Nov 16, '20 Nov 23, '20
Mode Name W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
0 Project125 days Fri 10/23/20Fri 11/27/20
1 Start 0 days Fri 10/23/20 Fri 10/23/20 10/23
2 A 5 days Fri 10/23/20 Thu 10/29/20
3 C 8 days Fri 10/30/20 Wed 11/11/20 2
4 D 2 days Thu 11/12/20 Fri 11/13/20 3
5 B 7 days Fri 10/30/20 Tue 11/10/20 2
6 E 3 days Fri 10/23/20 Tue 10/27/20
7 F 6 days Wed 10/28/20 Thu 11/5/20 6
8 I 10 days Mon 11/16/20 Fri 11/27/20 4,5
9 M 8 days Fri 11/6/20 Tue 11/17/20 7
10 G 1 day Fri 10/23/20 Fri 10/23/20
11 H 2 days Mon 10/26/20Tue 10/27/20 10
12 K 17 days Wed 10/28/20 Fri 11/20/20 11

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Critical
Date: Mon 10/19/20
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

You might also like