Professional Documents
Culture Documents
Abstract
Airport construction projects are large, complex, and expensive ventures that often involve political,
economic, social, technical, environmental and legal (PESTEL) challenges. Despite these
challenges, large sums of money are invested in airport projects that run high risks of being over
budget and not within schedule. Though some degree of cost, schedule and quality risks are
considered during planning, an understanding of how risks impact on the performance of the project
still remains a challenge for project managers and stakeholders. Past experience from similar
projects indicate that there was a lack of tools to identify and assess risks in airport construction
effectively. In seeking to address these problems, this research aimed at identifying and analyzing
the key PESTEL risks associated with the development of airport construction projects in Zambia.
The expansion and upgrading of Kenneth Kaunda International Airport (KKIA) was used as a case
study. Due to time constraints, the research was conducted during the construction phase only.
Through interviews, the study established that there was lack of in-depth understanding and
knowledge of the inherent PESTEL risk issues and their impact in airport construction. There was
also no standard and effective technique or practice specifically targeted for assessing risks in
airport construction projects.
Based on a review of literature and a self-administered structured questionnaire, risks were
identified and a comprehensive assessment of the probability of these risks as well as their impact
on project objectives was carried out. Using the risk significance and identification score (RSIS),
the study identified and ranked 20 key PESTEL risk factors as having a significant impact on
project delivery. Among them “Unforeseen modification to project” was recognized to influence
project objectives mostly, followed by “Stakeholders’ pressure”, and “Material price changes”. It
was concluded that project stakeholders must work collaboratively during the construction phase to
address potential PESTEL risks in time to ensure the successful delivery of the project within time,
without cost overruns and to the expected quality.
1. Background
The construction process, especially in the context of airport construction projects, is complex and
has significant risks built into its structure (Ashley, 1977, Mohammad et al., 1991) which influence
the project from initiation through to the completion stages (Flyvbjerg et al., 2003). For example,
variable site conditions, subcontractor delays and uncertainty about changes in weather conditions
are some of the common risk variables that exist in every construction project.
Risk management is therefore paramount during construction for successful delivery of the project.
Project Managers who do not interact attentively with the environment of these projects usually face
challenges during planning and execution of their projects (Ali-Mohammed, 2010). Evidence
suggests that such projects are usually money pits and funds are simply ‘swallowed up’ without
achieving the required project objectives. This is as a result of the lack of information in assessing
risks and uncertainties, and not taking corrective actions to mitigate the identified risks. For
example, Anthony (2012) asserted that airport projects more often fly off course than other types of
1
Zambia Airports Corporation Limited, P. O. Box 30175, Lusaka; +260 96 666 6986; niassico@hotmail.com
infrastructure construction because they are more complicated and involve more uncertainty.
Project costs and completion time is often grossly underestimated.
It is generally accepted that not all risks can be removed but it is also accepted that identification of
risks and their proactive management can decrease the probability of occurrence, and in the event
that they do occur, their severity can be minimized with robust control processes and mitigation in
place. The delivery of KKIA therefore, presents Zambia Airports Corporation Limited (ZACL) with
a challenge in respect of airport construction risks. The key factors contributing to this are: $365
million project financed through contracted loan from the Bank of China; the scale of project not
undertaken previously by ZACL; and ambitious technical challenges to be delivered in an airport
environment. The objectives are to deliver on time, within budget, compliant with specifications
that are safe while meeting customer needs and expectations.
Against this background, the main objective of this research was to determine the key PESTEL
risks which affect project delivery in airport construction and recommend adequate risk
management strategies in order to improve their implementation. In order to achieve the main
objective, the following specific objectives were devised:
a) to identify and describe the significant risks associated with PESTEL problems for
airport construction projects;
b) to quantify the qualitative PESTEL risk effects on project objectives and rank them in
relation to their influence on project objectives; and
c) to determine the key PESTEL risks having a significant impact on project delivery.
The above examples clearly indicate that the construction cost and time estimating on airport
infrastructure projects still remain a challenge. According to Flyvbjerg et al. (2002), new ideas and
techniques are needed to develop and improve this area where there is knowledge gab. One of the
main reasons for airport construction cost and time overruns in Flyvbjerg’s study was that “risk is
simply disregarded in feasibility studies by assuming what the World Bank calls the EGAP
principle: Everything Goes According to Plan.” This approach, however, has resulted in delays,
litigation and budget overruns (Hayes et al., 1986). According to Leung and Chuah (1998), an
effective risk management can help project managers to identify and assess potential risk factors
and take suitable actions in order to achieve the desired project objectives. However, many project
stakeholders’ analyze and assess risk based on experience and intuition (AI-Bahar, 1988).
Figure 3 is a representation of the conceptual framework for the applications of risk management in
airport construction projects based on literature and theories of past researchers. The problem at
hand is the project risk factors (PESTEL risk factors) which affect project cost, time and quality
objectives. The framework placed risk management in the context of project decision making while
considering the over-lapping contexts of behavioral responses, organization structure, and
technology. The project objectives and construction risk management objectives should clearly be
established within the context of project decision-making, and will be governed largely by the
attitude of project stakeholders towards risk. The framework for risk management provides an
effective and systematic way for quantitatively identifying, analyzing, and responding to risk in
airport construction projects. In this framework, emphasis is placed on how to identify and manage
PESTEL risks before, rather than after, they materialize into losses or claims.
PESTEL Risk Factors
Project Success
(Time, Cost & Quality)
Table 1: Matrix for the calculation of the risk significance index (Shen et al. (2001) and Wang
and Liu (2004))
All of this information summarized in Table 3 indicates that respondents were competent enough
and capable of participating in the survey. A plausible conclusion therefore is that the respondents
were sufficiently well vested in the construction of the case study project to provide data which was
credible.
The respondents were requested to state the probability and impact of each of the identified risks
using the three-point scale in Table 1. The results were used to determine the RSIS. The RSIS
represent the relative importance of a risk. It was used to rank risks in relation to their impact on
project performance. The results of this analysis are shown in Table 6.
Table 6: Risks ranked as per their significance in each category (Author, 2016)
Figure 4: Graphical presentation of Key PESTEL risks in airport construction projects (Author,
2016)
5. Conclusion and recommendations
5.1 Conclusion
The theoretical foundation of this study was risks in construction. The study successfully addressed
an important research topic in the risk assessment literature; PESTEL risk factors during airport
development in the construction phase. While most research has focused on some aspects of
construction management, this research endeavored to identify key risks associated with the
achievement of airport construction project objectives in terms of cost, time and quality. On the
basis of a survey with industry practitioners owning robust experience and knowledge of airport
construction projects, 20 key risks were highlighted on a comprehensive assessment of their
likelihood of occurrence and level of impacts on project objectives. “Unforeseen modification to
project” was found to have significant impact on the project objectives. Project stakeholders should
work cooperatively during the construction phase to address potential risks effectively and in time;
contractors and subcontractors with robust construction and management knowledge must make
sound preparation for carrying out safe, efficient and quality construction activities.
5.2 Recommendations
This research showed that there was a lack of knowledge of risks that affect airport construction
projects in Zambia and rarely do project stakeholders apply risk management procedures. Risk
management is more often based on intuition and experience. In light of this finding it is important
to enlighten the stakeholders on risk management procedures and strategies to improve their
capacity. Based on the foregoing, the researcher made the following recommendations which would
guide the actions of stakeholders to effectively develop and implement risk management in airport
construction projects in Zambia.
Risk analysis and management in airport construction should be deployed during the
construction phase and project stakeholders must strive to identify all potential risks and
adopt strategies to mitigate their effects.
Stakeholders involved in airport construction and development must have properly structured
risk identification, analysis and mitigation processes or options to moderate the risks
associated with airport construction projects.
Project stakeholders must endeavor to plan and coordinate airport construction projects well
to avoid risk. In instances where they cannot avoid the risks, the necessary tools or mitigants
should be put in place to insulate the project against all possible risks.
Risk management documentation is very critical. Project stakeholders should therefore
document and properly record the identification, analysis, and risk mitigation plans and
results for risk elements. This allows for lessons to be learnt and actions to be taken if
necessary.
Lastly, it is recommended that risk management should be incorporated into the academic
curriculum of tertiary institution who undertakes engineering biased courses so that graduates
are introduced to the subject before practicing after school.
References
Adrem, A., Schneiderbaur, D., Meyer, E., and Majdalani, F. (2006). “Managing Airports
Construction Projects”, Booz/Allen/Hamilton Inc.
Ahmad, B. & Mohammed, K., 2015. Saudi Arabian aviation construction projects: Identification of
risks and their consequences: Creative Construction Conference 2015 (CCC2015)
Ahmed, S., Azher, S., Castillo, M., & Kappagantula, P. (2002) Construction delays in Florida: an
empirical study, Final report submitted to the state of Florida, Department of Community Affairs.
Ali-Mohammed, B.A. (2010) Risk and Stakeholder Management in Mega Projects beyond the
Realms of Theory (online), Ministry of Works and Housing, Kingdom of Bahrain, available:
www.works.gov.bh/media/Researchs/pw04p06.pdf (accessed May, 2016).
AS/NZS 4360 (2004) Australian / New Zealand Standard on Risk Management, Standards Australia
and Standards New Zealand.
Ashley, D. B. (1977) ‘Construction project risk-sharing’, Technical Report No. 220, Department of
Civil Engineering, Stanford University, Stanford, CA, 1977.
BCIS, (2012) ‘BIS Construction Price and Cost Indices’, Available: http://www.bcis.co.uk:
Building Cost Information Services, UK.
Chan, W.M.C. and Kumaraswamy, M.M. (2002) ‘Compressing construction durations: lessons
learned from Hong Kong building projects’, International Journal of Project Management, 20, 23-
35.
Chau, K. C. (1995) ‘The 3 Gorges Project of China - Resettlement Prospects and problems’, Ambio,
24(2) 98-102.
Del-Caño, A. and De-La Cruz, M. P. (2002) ‘Integrated Methodology For Project Risk
Management’, Canadian Journal Of Civil Engineering, 35(5) pp. 473 – 485.
Flyvbjerg, B. (2006) ‘From Nobel Prize to Project Management: Getting Risks Right’, Project
Management Journal, 37(3), 5-15.
Flyvbjerg, B. (2009) ‘Survival of the unfit test: why the worst infrastructure gets built-and what we
can do about It.’, Oxford Review of Economic Policy, 25(3), 344-367.
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of
ambition. Cambridge University Press.
Flyvbjerg, B., Holm, M. K. S. and Buhl, S. L. (2002) ‘Cost underestimation in public works
projects: error or lie?’ Journal of the American Planning Association, 68(3), 279-295.
Garry, G. (2005) ‘Risk Factors Leading to Cost Overrun in Highway Projects’, Queensland
University of Technology, Australia.
Gould, F. E. (2002) ‘Managing the construction process: Estimating, scheduling, and project
control’, Upper Saddle River, NJ: Prentice Hall.
Hayes, R.H. & Wheelwright, S.C. (1986). Restoring our competitive edge; Competing through
manufacturing. New York: Wiley.
Jyh-Bin Y. (2010) ‘Causes of Delay in the Planning and Design Phases for Construction Projects’,
Journal of Architectural Engineering, pp.80-83.
Luke (14:28) The Holy Bible, New International Version (NIV, 1982). Thomas Nelson, Inc.
Mohammad, A., Mustafa, Z. M. and Jamal, F. A. (1991) ‘Project Risk Analytic Assessment Using
the Hierarchy Process’, Transactions on Engineering Management, 38 (1).
Murphy, S. and Salzman, J. (2008) More Big Dig charges brought, Boston Globe.
National Audit Office. (2001). Modern policy making: Ensuring policies deliver value for money.
HC289, November 2001. London: TSO
Pickavance, K. (2005) ‘Delay and disruption in construction contracts’, 3rd edition, Informa-Legal
Publishing, UK.
Reid, R. L. (2007). “Logan’s Smooth Landing”, Journal of Civil Engineering, March, pp. 44-55.
Rubin, A., & Babbie, E. (2009). Research methods for social work (4th ed.). Pacific Grove, CA:
Brooks/Cole.
Safer Ali et al (2012) ‘Time waste and delay in construction projects’, NICMAR-journal of
construction management, 27(4), 64-75.
Shen, L.Y., Wu, G.W.C. and Ng, C.S.K. (2001) Risk Assessment for Construction Joint Ventures in
China, Journal of Construction Engineering and Management, 127(1), 76-81.
Tommy, Y. Lo et al (2006) ‘Construction Delays in Hong Kong Civil Engineering Projects’,
Journal of Construction Engineering and Management, 132(6), 636-649.
Wang, S. Q., Dulaimi, M. F., & Agura, M.Y. (2004). Risk management framework for construction
projects in developing countries. Construction Management and Economic 22, 237-252.
World Bank, (2009) ‘Publishing Information on Public Construction Projects’, mimeo: World
Bank.