Professional Documents
Culture Documents
INDEX 1
MIDTERM EXAMINATION
Name:
Assoc Prof. Ho Thanh Phong Mr Nguyen Hoang Minh
INSTRUCTIONS:
1. This is an open book examination.
2. Calculator and dictionary are allowed. Students takes 2 decimal digits in calculation
3. Laptop, mobile phone, discussion and material transfer are strictly prohibited
4. There are two parts in this exam. Students do Part 1 in the Question paper, Part II in the
answer paper
Total pages: 06 (including this page)
3. The project’s existence is formally recognized, possibly for the first time, in the project’s:
A. Project SOW
B. Charter
C. Scope statement
D. Project management plan
4. The critical path can be defined as the longest track through a network. The computation of the
network will determine that there are:
A. Only one critical path
B. One or more critical paths
C. Always more than one critical path
D. Always more than two critical paths
5. In a precedence diagram, the placement of the connecting lines to other activities is significant
because the lines indicate:
A. One of the relationships of logic
B. A dashed connectivity for dummy activities
C. The required delay between the finish of one activity and the start of another
D. Resources needed to complete the next activity
6. A project manager is trying to complete a software development project, but cannot get enough
attention for the project. Resources are focused on completing process-related works and the
project manager has little authority to properly assign resources. What form of organization must
the project manager be working in?
A. Matrix
B. Functional
C. Expediter
D. Projectized
9. What is a program?
A. An initiative set up by management
B. A means to gain benefits and control of related projects
C. A group of unrelated projects managed in a coordinated way
D. A government regulation
10. A detail project schedule can be created after only creating the:
A. Project budget
B. Work breakdown structure
C. Project management plan
D. Detailed risk assessment
11. In which process group does the team measure and analyze the work being done on the project?
A. Initiating
B. Executing
C. Monitoring and controlling
D. Closing
12. Which of the following would be the MOST appropriate thing to do during the initiating process
group?
A. Create a detailed description of the project deliverables
B. Get familiar with the company culture and structure as it relates to the project
C. Identify the root cause of problems
D. Ensure all project management processes are completed
13. When a project is performed under contract, the SOW (Statement of Work) is provided by which
of the following?
A. The buyer
B. The project sponsor
C. The project manager
D. The contractor
15. According to A Guide to the PMBOK, the project SOW (Statement of Work) should contain or
reference which of the following elements?
A. Strategic plan, product scope description, stakeholder influences, and business need
B. Business need, strategic plan, and product scope description
C. Project purpose, business case, stakeholder influences, and product scope statement
D. Requirements, business need, and stakeholder expectations
19. The work breakdown structure is a deliverable-oriented grouping of project elements (products or
services) which defines, or provides a structure for defining the:
A. Project staffing, skill requirements, scope definition
B. Work packages, control accounts, schedules
C. Project change control, risk identification, labor rates
D. Project charter, project plan
20. Which of the following BEST describes the contents of a WBS Dictionary entry?
A. The definition of the work package including its net present value
B. Work Package ID and Name, Statement of Work, Required Resources, and Monte Carlo
Analysis
C. Work Package ID and Name, Statement of Work, Risk Register, Earned Value Calculation,
Scheduled CompleteDate, and Cost
Question 2:
An engineer has received two bids for an elevator to be installed in a new building. The bids, plus his
evaluation of the elevators, are as follows:
If the interest rate is 10%, using the present worth method, which bid should be accepted?
Question 3:
Consider the following project:
GOOD LUCK!
Index 1 Index 2
1 C 1 C
2 A 2 D
3 B 3 A
4 B 4 D
5 A 5 C
6 B 6 B
7 C 7 C
8 D 8 A
9 B 9 B
10 B 10 A
11 C 11 B
12 B 12 D
13 A 13 D
14 D 14 A
15 B 15 B
16 C 16 D
17 D 17 D
18 D 18 C
19 B 19 D
20 D 20 D
25 years × $75000
$100,000
$12,600,000
$14,200,000
PW = 14,200,000 + 75,000(P/A, 6%, 25) + (12,600,000 + 100,000(P/A, 6%, ))(P/F, 6%, 25)
= 14,200,000 + 75,000(12.783) + (12,600,000 + 100,000(16.667)(0.233)
= 18,481,624.4
$100,000
$22,400,000
In this case, we calculate the present worth of cost the alternative with the smaller cost is chosen
we should build in two stages. (1 point)
PW = 45,000 + 2,700(P/A, 10%, 30) + (45,000 – 3,000)(P/F, 10%, 10) + (45,000 – 3,000)(P/F, 10%,
20) – 3,000(P/F, 10%, 30)
= 45,000 + 2,700(9.427) + 42,000(0.3855) + 42,000(0.1486) – 3,000(0.0573)
= 92,713.2
Itis: (7 points)
$4,500 $4,500
$54,000 $54,000
PW = 54,000 + 2,850(P/A, 10%, 30) + (54,000 – 4,500)(P/F, 10%, 16) – 4,500(P/F, 10%, 30)
= 54,000 + 2,850(9.427) + 49,500(0.2394) – 4,500(0.0573)
= 92,459.4
The present worth of the cost of Itis is smaller than that of Westinghome Itis bid should be
accepted. (1 point)
E
J
Start A C
M
F I
N
D End
G K
H L
c) Determine the critical path of the project and the project completion time: (14 points – 1 for
each activity)
d) Find the probability that the project will finish within 36 days: (3 points)
Mean = 33 days (1 point)
Variance = σA + σD + σF + σJ + σM + σN = 23/9 (1 point)
36 33
P( X 36) P( Z ) P( Z 1.877) 0.5 0.4697 0.9697 (1 point)
23 / 3