Line Up / Cleaning
Inspection
No. Activity Date
Result
Internal surface of pipes shall be free of any mud, sand, etc. The
2 external and internal of pipes near the groove shall be free of any
rust and oil, etc. before lining up.
Damaged and unsatisfied pipe ends shall be repaired as per the
3
specifications.
Pipes shall be lifted and assembled with the approved special
4
lifting equipment.
Spiral and straight welds between two adjacent pipes shall be
5
staggered according to relative standards.
Inspection Conclusion:
Name: Name:
Date: Date: