You are on page 1of 8

Statistical-Fuzzy Approach to Quantify Cumulative Impact

of Change Orders
Awad S. Hanna, P.E., M.ASCE1; Wafik B. Lotfallah2; and Min-Jae Lee, S.M.ASCE3

Abstract: This paper presents a hybrid approach to quantify the impact of change orders on construction projects using statistical
regression and fuzzy logic. There are many qualitative variables affecting the impact of change orders on labor productivity; statistical
analysis falls short of addressing the fuzziness of those variables. Because of their complementary nature, fuzzy logic and regression
analysis can be integrated; regression analysis is used to determine the membership functions of the input linguistic values. In this paper,
each input variable is statistically treated before entering a general rule relating its space to the space of loss in labor productivity. The
relative weight of each input variable is determined by its coefficient of determination (R 2 ) value. The expected loss of labor productivity
and its standard deviation are then determined from the output fuzzy membership function. The proposed methodology is general and can
be applied in areas of system analysis and decision making when a complex input-output function is to be predicted in the presence of
some fuzzy knowledge and a large number of real input-output data.
DOI: 10.1061/共ASCE兲0887-3801共2002兲16:4共252兲
CE Database keywords: Productivity; Fuzzy sets; Change order; Construction.

Introduction 共752兲 of the projects were completed with a combined total of


6,413 change orders of various sizes with an estimated value of
A fact of life for a construction project is change. Changes result $94 million. The audit report stated that one-third of the total
from the necessity to modify aspects of the construction project in number of change orders, or $35.4 million, could have been
reaction to circumstances that develop during the construction avoided. Inadequate field investigation, unclear specifications,
process. The changes may be small, well managed, and have little plan error, and design change or mistakes by the consulting engi-
effect on the whole construction project. On the other hand, neer were cited as causes for these changes 共Cambridge System-
changes may be large, poorly managed, and have tremendous atics, Inc. 1998兲.
negative impacts on the construction project performance in terms Few studies have attempted to quantify the impact of change
of time and cost. orders on project cost and schedule as well as labor productivity.
Estimating the cumulative impact of change orders on project
performance in terms of cost and schedule faces two major diffi-
Problem culties.
Change orders can frequently cause significant disruptions to a 1. There are many input parameters that affect the loss of labor
construction project, which may decrease the labor productivity productivity; and
of the contractor and extend the project duration. An earlier study 2. Many of these parameters are qualitative in nature and are
showed that the United States construction industry spends $50 hard to quantify—e.g., the quality of bid documents, the
billion annually on new construction change orders 共Ibbs and quality of contractors’ preplanning efforts, the contractors’
project management experience, and the quality of the engi-
Allen 1995兲.
neering designs.
A recent audit report of state projects built in the state of
A literature review revealed that no research study has dealt with
Washington reviewed a total of 865 projects and found that 87%
a statistical-fuzzy analysis of the qualitative variables affecting
1
labor productivity in construction projects.
Professor, Dept. of Civil and Environmental Engineering, Univ. of
Wisconsin-Madison, 1415 Engineering Dr., Madison, WI 53706. E-mail:
ashanna@facstaff.wisc.edu Limitations of Traditional Methods
2
Lecturer, Dept. of Mathematics, Univ. of Wisconsin-Madison, 1415
Engineering Dr., Madison, WI 53706. E-mail: lotfalla@math.wisc.edu A literature review revealed three academic methods that are gen-
3
PhD Candidate, Dept. of Civil and Environmental Engineering, Univ. erally used to predict the outcomes of engineering systems—
of Wisconsin-Madison, 1415 Engineering Dr., Madison, WI 53706. namely, regression analysis, artificial neural networks, and fuzzy
E-mail: mlee@cae.wisc.edu logic. However, when handling a problem like quantifying the
Note. Discussion open until March 1, 2003. Separate discussions must
impact of change orders on productivity, each of these methods
be submitted for individual papers. To extend the closing date by one
month, a written request must be filed with the ASCE Managing Editor.
has its own limitations.
The manuscript for this paper was submitted for review and possible 1. Both regression analysis and neural networks have limita-
publication on September 26, 2000; approved on February 6, 2002. This tions in dealing with a qualitative input variable; and
paper is part of the Journal of Computing in Civil Engineering, Vol. 16, 2. As the system complexity increases, fuzzy logic faces the
No. 4, October 1, 2002. ©ASCE, ISSN 0887-3801/2002/4- difficulty of determining the right set of rules and member-
252–258/$8.00⫹$.50 per page. ship functions.

252 / JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002


Fig. 1. Breakdown of productivity loss

Hybrid Statistical-fuzzy Method The owner’s budget or schedule might change and force a reduc-
tion of scope. Unforeseen natural events might occur. All of these
This paper presents a hybrid system that encapsulates both statis- reasons for change frequently cause disruption in the planned
tical analysis and fuzzy logic to study the effect of the quantita- work schedule, and result in increased costs through rework and
tive and qualitative input variables on enhancing or reducing the decreased efficiency of the base contract work. Some examples of
impact of change orders on labor productivity. Regression analy- causes of inefficiency due to change orders are 共Fig. 1兲
sis is used here to determine the membership functions of the
• Increased frequency of planning and replanning,
input linguistic values as well as the forms of the if-then rules.
• Loss of efficiency due to interruption, interference, and lack of
Equivalently, each input variable is statistically treated before en-
availability of tools, labor, and materials to meet the require-
tering a general rule relating its space to the space of loss in labor
productivity. Also, the relative weight of each input variable is ments of the changes,
determined by its coefficient of determination (R 2 ) value. When • Increased project management and supervision involvement,
linguistic input values are determined, the general rules are sepa- • Loss of efficiency due to a ripple impact that is a direct result
rately fired and the resulting fuzzy values are aggregated with of change orders, such as stacking of trades, schedule com-
their relative weights. The expected loss of labor productivity as pression, and out-of-sequence work, and
well as its standard deviation are then determined from the output • Difficulty in determining equitable adjustment compensation
fuzzy membership function. for the parties involved.

Scope Labor Efficiency, Productivity, and Loss


of Efficiency
This paper investigates the effects of change orders on the elec-
trical and mechanical sectors of the construction industry. The Efficiency is the ratio of actual performance to the theoretical
reason for selecting electrical and mechanical contractors is that maximum performance, and therefore is dimensionless 共Hanna
they represent a labor-intensive segment of the construction in-
et al. 1999a兲. Productivity can be defined either as the input 共re-
dustry. Also, as subcontractors, these disciplines are typically the
sources兲 divided by the output 共completed work兲, or as the output
‘‘last in line’’ and must carry the delays caused by previous
divided by the input.
trades. In addition, electrical and mechanical construction projects
The variable that will be used to determine the loss of effi-
are complex, and small changes in plans and specifications can
have large ripple effects on the rest of the project. ciency has been labeled ‘‘delta’’ 共symbolically, ⌬兲. Delta is de-
fined as the difference between the base project labor hours 共ac-
tual total project hours less the estimate of change order hours兲
Background and the original estimate of labor hours at the contract award. Fig.
1 shows a graphical distribution of delta.
After a contractor is awarded a construction project, an owner Delta can take a positive value or a negative value. Positive
frequently finds it necessary to order changes on the project. Con- values of delta indicate that the actual productivity is less than the
tract documents are an imperfect expression of the design profes- planned or estimated productivity. On the other hand, negative
sional’s and owner’s intent for a project. Circumstances develop values of delta are an indication of higher efficiency than origi-
during the construction process that make revisions of the draw- nally anticipated or estimated. Positive deltas can be attributed to
ings and specifications necessary. The design might prove to be a variety of factors such as a contractor’s low estimate, a contrac-
inadequate. Materials specified might be unavailable or scarce. tor’s inefficiency, and the impact of productivity-related factors

JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002 / 253


such as change orders, weather conditions, work interruptions, This study showed several limitations, as follows:
and rework, among others. To study the impact of change orders, 1. In an attempt to relate the loss of productivity associated
the research team acquired data for projects where change orders with change orders to several independent variables such as
were the main reason for loss of efficiency. Projects impacted by project percent complete and engineering percent complete,
change orders were selected based on observing the deviation of the study reported low values for the coefficient of determi-
actual manpower loading. Manpower loading is a graphical rela- nation R 2 . Low R 2 values limit the ability of the owners
tionship between percent of time and work hours consumed per and/or contractors to explain the variation present within the
week. As a result, certain qualitative and quantitative criteria were data.
developed to define projects that were impacted mainly by change 2. The study assumed that the ratio between the installed ma-
orders 共Hanna 1999a,b兲. Projects that were impacted by other terial cost and the installed total cost is an indication of
factors or impacted because of the contractors’ low estimates efficiency when late changes are implemented into a project.
were eliminated from the database. This can lead to difficulties when reductions of scope or
changes occur that do not consume materials.
3. The study failed to support the concept that changes imple-
Change Orders Quantification: Literature Review mented late in a project are implemented less efficiently than
changes that occur early in a project. Changes implemented
Four studies are discussed below to provide an understanding of
late in a project cause a greater loss of labor efficiency be-
the current literature regarding the effects of change orders on
cause the peak of labor occurs 50– 80% of the time.
project performance in terms of cost and time. In addition, the
There were two studies completed at the University of
benefits and limitations of these studies are discussed.
Wisconsin-Madison that used statistical methods to quantify the
Leonard et al. 共1991兲 put forth a significant effort to quantify
impact of change orders on labor productivity for mechanical and
the effect of change orders on labor efficiency. The study used 90
for electrical contracting 共Hanna et al. 1999a, b兲. Both studies
cases that had resulted in disputes between owners and contrac-
used questionnaires that were distributed to mechanical and elec-
tors. The data were collected for the following three different
trical contractors, respectively. The data from the questionnaires
categories:
were used in a regression analysis to determine a model to predict
1. Electrical/mechanical contracts on building projects;
the delta as a percent of the total hours spent on the project.
2. Electrical/mechanical contracts on industrial projects; and
The two studies identified four factors that impact the loss of
3. Civil/architectural contracts on building and industrial
labor efficiency. These were change order hours as a percent of
projects.
original estimate hours, number of change orders, timing of
The change order impacts were divided into three types—共1兲
change orders, and contractors’ project managers’ experience.
minor; 共2兲 medium; and 共3兲 high. Graphs were presented in each
The mechanical and electrical studies at the University of Wis-
impact category that related the loss of efficiency to the percent-
consin have some shortcomings. Both studies looked at only a
age of changes. There were, however, several deficiencies in this
limited number of qualitative variables. The present research pro-
study.
poses to investigate over 70 possible factors that impact how
• Limited number of variables. The study considered the amount
change orders might affect productivity.
of change as the only factor that was related to the loss of
efficiency. The study did not consider other factors such as the
timing of changes, the size of each change, or project-specific
characteristics such as project size, labor type, and project de- Fuzzy Logic Literature in Construction
livery system, among others.
• Data adjustment. The study modified the loss of efficiency due Zadeh 共1965, 1975a,b,c, 1979兲 outlined the theory of fuzzy sets
to learning. This adjustment was not justified, because loss of for incorporating vague and imprecise data into analyses. Ayyub
productivity, as defined by Leonard, represents the cumulative and Haldar 共1984兲 pioneered the use of fuzzy set theory to evalu-
impact that includes loss of efficiency due to learning. ate the impact of qualitative variables such as site conditions,
• Combination of data. The study combined the data for electri- weather conditions, and labor experience on activity cost and du-
cal and mechanical trades without any evidence that the loss of ration. They emphasized primarily the assessment of the mean,
efficiency between the two trades may be different. variance, and covariance of the activity duration.
• Biased sample. Data were collected from projects that reached Wu and Hadipriano 共1994兲 introduced the fuzzy modus ponens
a disagreement and dispute between parties. There were no deduction technique for construction scheduling to assess the im-
opportunities to compare impacted and unimpacted projects. pacts of qualitative factors on activity duration. They quantified
• Classification of impact. The classification of impact as minor, linguistic values into numerical measures using angular fuzzy set
medium, and high was subjective and based on the judgment theory. These numerical values are used to modify the activity
of the researcher. duration affected by the cumulative impact of different site, cli-
The Construction Industry Institute 共CII兲 commissioned a matic, resource, and management factors. Others have used the
study titled ‘‘Quantitative impacts of project change’’ 共Ibbs and theory to provide start and finish times along with fuzzy project
Allen 1995兲. In this study, a total of 89 projects were obtained durations 共Dubois and Prade 1980兲.
from CII member companies. The data were gathered in order to Lorterapong and Moselhi 共1996兲 calculated activity duration
examine the following three hypotheses: using traditional fuzzy set operations as well as newly developed
1. Changes that occur late in a project are implemented less fuzzy network scheduling 共FNET兲. The results generated by
efficiently than those early on; FNET are reasonable, but the computations are not as simple as
2. The greater the project change, the greater its negative im- for the program evaluation and review technique.
pact on labor productivity; and Recently, Hanna and Lotfallah 共1999兲 used fuzzy logic to se-
3. The hidden or unforeseeable costs of change 共the cumulative lect the best crane type for a construction project. In their ap-
change effect兲 increase with more project change. proach, they used the max-min extension principle to transform

254 / JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002


linguistic information about the suitability of each crane type with
respect to each factor of the project into an overall efficiency of
each crane type.
M 共 x 兲⫽ 再 1⫺a 共 x⫺c 兲
1⫹a 共 x⫺c 兲
for x⭓c
for x⭐c
The case when a⬍0 is similarly treated, where the if-then rules
will take the form
Fuzzy Set Concepts „Statistical-fuzzy If-then Rules… If x is H, then y is N; If x is M , then y is Z;

The novel approach in this paper is the use of statistical data to If x is L, then y is P
choose the fuzzy membership functions and to form the fuzzy The values of H, M, and L are determined in a similar way.
if-then rules. The following example illustrates this method. Our method can be applied even if the regression function y
Suppose that a fuzzy if-then rule is to be formed between the ⫽ f (x) is not a linear function. Another way to view this method
universe of an input variable x, and an output variable y. Assume is that we used the function f (x) to map the input variable x to an
further that x lives in the unit interval 关0, 1兴 and y lives in the intermediate variable u⫽ f (x) such that the relationship between
interval 关⫺1, 1兴. For the output variable y, we fix the linguistic u and the output variable y can be represented by an identity
values P 共for positive兲, N 共for negative兲, and Z 共for zero兲, whose fuzzy functional; i.e., we have
fuzzy membership functions are given by


If u is N, then y is N; If u is Z, then y is Z;
y for 0⭐y⭐1
P共 y 兲⫽ ; If u is P, then y is P
0 otherwise


The above functional can be generalized to the following state-
⫺y for ⫺1⭐y⭐0 ment:
N共 y 兲⫽ ;and
0 otherwise
If u is A, then y is A

Z共 y 兲⫽ 再 1⫺y
1⫹y
for 0⭐y⭐1
for ⫺1⭐y⬍0
where A⫽any fuzzy set.
Thus, by statistically treating the input x, we managed to simplify
We also have some statistical data represented by the points the fuzzy rules used to the general rule
(x i ,y i ), for i⫽1,...,n, from which we get the regression line If f 共 x 兲 is A, then y is A
y⫽ f 共 x 兲 ⫽ax⫹b (1)
where the values of a and b are picked to minimize the sum of the Fuzzy Set Concepts „Aggregating Rules…
squares of the errors
n Starting with k input variables x 1 ,x 2 ,...,x k affecting an output
E⫽ 兺
i⫽1
共 y i ⫺ax i ⫺b 兲 2 variable y, we use the method of the previous section to get a
separate regression function u i ⫽ f i (x i ) for each input variable x i
In traditional regression analysis x and y are correlated and a with the generalized fuzzy rule
⫽0. We then prefer to write Eq. 共1兲 in the form Ri If f i 共 x i 兲 is A, then y is A
y⫽ f 共 x 兲 ⫽a 共 x⫺c 兲 Now suppose that for each input variable x i we have the fuzzy
Let us assume for now that a⬎0. We then seek some if-then rules statement
of the form f i 共 x i 兲 is A i
If x is H, then y is P; If x is M , then y is Z; Since our belief in rule Ri can be measured by the coefficient
If x is L, then, y is N of determination R 2i of the correlation between x i and y, we can
deduce that our belief that ‘‘y is A i ’’ is also measured by R 2 . We
where the values H 共for high兲, M 共for medium兲, and L 共for low兲 can then aggregate the fuzzy membership A i by the formula
are yet to be determined.
According to the above rules, it is plausible to say that our 兺 i⫽1
k
R i2 •A i 共 y 兲
belief-strength that some particular value of x is high can be iden- A共 y 兲⫽ (2)
兺 i⫽1
k
R i2
tified with our belief-strength that the corresponding predicted
value of y is positive. This suggests that we can define the fuzzy Calling
membership function H by
R i2
H 共 x 兲 ⫽ P 关 f 共 x 兲兴 w i⫽
兺 i⫽1
k
R i2
and similarly Eq. 共2兲 can be written in the form
M 共 x 兲 ⫽Z 关 f 共 x 兲兴 and L 共 x 兲 ⫽N 关 f 共 x 兲兴 k

Thus, in our example we have A共 y 兲⫽ 兺 w iA i共 y 兲



i⫽1
a 共 x⫺c 兲 for x⭓c
H共 x 兲⫽ , where A⫽weighted average of the A i s. Now to defuzzify the
0 otherwise output y, we find the centroid y * from

L共 x 兲⫽ 再 a 共 c⫺x 兲
0
for x⭐c
otherwise
; and y *⫽
兰 y•A 共 y 兲 dy
兰 A 共 y 兲 dy

JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002 / 255


Table 1. Significant Factors Affecting Delta
Input variable Definition
Industrial 1⫽Industrial projects; 0⫽all other projects 共commercial, institutional, etc.兲
EA – P Estimated/actual peak human-hours 共0.15–3.25, from database兲
%OwnInitiatedCO Percent of change orders initiated by owner 共0.00–1.00兲
%COHrsApproved Percent of change order hours approved by owner 共0.00–1.00兲
%Additions Percent of change order hours that were additions or deletions 共0.00–1.00兲
Productivity-Track Did the contractor track productivity for the project? 共0⫽No; 1⫽yes兲
Absenteeism Absenteeism ratio 共1⫽0 – 5%; 2⫽6 – 10%; 3⫽11– 20%; 4⫽greater than 20%兲

representing the expected value of the output y, and the standard since the R 2 value of %Additions is 0.000, this variable (x 5 ) will
deviation ␴ with not appear in our statistical-fuzzy model.
兰 共 y⫺y * 兲 2 •A 共 y 兲 dy
␴ 2⫽
兰 A 共 y 兲 dy Case Study
representing the accuracy of our estimation. In practice we may
want to use discrete spaces for the input and the output variables, To illustrate our method, we show the calculations for the follow-
and replace integration by summation. ing case study, where each input variable takes either a given
crisp value or a fuzzy value determined by the available informa-
tion:
Application: Impact of Change Orders on 1. Not an industrial project (x 1 ⫽0).
Productivity 2. Estimated/actual peak work hours is 0.71 (x 2 ⫽0.71).
3. Change orders initiated by the owner is 90% (x 3 ⫽0.9).
Using regression analysis, Hanna et al. 共1999a, b兲 developed a 4. Change orders hours approved by the owner is 81.3% (x 4
linear model that quantifies the impact of change orders on labor ⫽0.813).
productivity. In their model, the output dependent variable was 5. Additions or deletions of change order hours is 75% (x 5
the percent loss of labor productivity 共Delta兲. They pointed out ⫽0.75).
some significant independent variables affecting Delta. Table 1 6. The contractor’s productivity tracking system is not
gives the definition and the range of possible values for each sophisticated, but adequate. In this case, we assume that
independent variable. The regression model found was x6 has the following fuzzy value: x6
⫽ 关 0.0,0.2,0.4,0.6,0.8,1.0,0.8,0.6,0.4,0.2,0.0兴 .
%Delta⫽0.3495 7. Absenteeism was not recorded, but the contractor identified
his strength of belief about the absenteeism ratio as follows:
⫹0.139 Industrial 0–5% with strength 70%; 6 –10% with strength 30%. Thus,
as a fuzzy subset of 兵1,2,3,4其, x 7 ⫽ 关 0.7,0.3,0.0,0.0兴 .
⫺0.0984 EA – P
Next we determine the fuzzy sets A i representing f i (x i ). As
Delta ranges between ⫹50 and ⫺50%, we take its discrete uni-
⫺0.0368%OwnInitiatedCO
verse to be
⫺0.190%OwnInitiatedCO* Industrial D⫽ 兵 ⫺0.5,⫺0.4,⫺0.3,⫺0.2,⫺0.1,0.0,0.1,0.2,0.3,0.4,0.5其 .
⫺0.100%COHrsApproved Since the input variables x 1 ,...,x 5 take crisp values, their re-
gression outputs f 1 (x 1 ),..., f 5 (x 5 ) take the following crisp values:
⫹0.0627%Additions
A 1 ⫽ f 1 共 0 兲 ⫽0.077⬇0.1
⫺0.0593 Productivity-Track
A 2 ⫽ f 2 共 0.71兲 ⫽0.115⬇0.1
⫹0.0544 Absenteeism (3) A 3 ⫽ f 3 共 0.9兲 ⫽0.035⬇0.0
From their statistical findings, we get a separate regression A 4 ⫽ f 4 共 0.813兲 ⫽0.080⬇0.1
linear function for Delta against each input variable. Table 2
shows those functions together with their R 2 value. Note that A 5 ⫽ f 5 共 0.75兲 ⫽0.0912⬇0.1

Table 2. Regression Models with x i ⫽Input Variable and u i ⫽Delta Estimator


Input variable x i Regression function u i ⫽ f i (x i ) R 2i value Weight w i
Industrial (x 1 ) u 1 ⫽0.0313•x 1 ⫹0.077 0.005 0.011
EA – P (x 2 ) u 2 ⫽⫺0.122•x 2 ⫹0.202 0.128 0.268
%OwnInitiatedCO (x 3 ) u 3 ⫽⫺0.199•x 3 ⫹0.214 0.097 0.203
%COHrsApproved (x 4 ) u 4 ⫽⫺0.301•x 4 ⫹0.325 0.073 0.153
%Additions (x 5 ) u 5 ⫽⫺0.000105•x 5 ⫹0.0913 0.000 0.000
Productivity-Track (x 6 ) u 6 ⫽⫺0.0765•x 6 ⫹0.132 0.033 0.069
Absenteeism (x 7 ) u 7 ⫽0.121•x 7 ⫺0.082 0.141 0.296

256 / JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002


Table 3. Validation of Models for % Delta Prediction

Input Variables (x i ) Percent Delta Output

%Own %COHrs
Industrial EA – P Initiated CO Approved %Additions Productivity-Track Absenteeism Project Statistical Statistical
Case project (x 1 ) (x 2 ) (x 3 ) (x 4 ) (x 5 ) (x 6 ) (x 7 ) actual model fuzzy model

Example No 共0兲 0.71 0.9 0.813 0.75 Not sophisticated, 0–5% with strength 70%; 10.80 23.70 7.20
project but adequate 共1兲 6 –10%
with strength 30%

M3132 Yes 共1兲 1.21 1 0.81 0.62 No 共0兲 0–5% 7.24 15.49 9.65

M3182 No 共0兲 0.43 0.4 0.8 0.75 Yes 共1兲 0–5% 7.90 25.46 9.72

M3362 Yes 共1兲 3.96 0.75 0.75 0 No 共0兲 11.20% 6.52 1.70 5.20

E042-2 Yes 共1兲 0.45 0.923 0.846 0.4 Yes 共1兲 0–5% with strength 13.27 17.05 9.54
70%; 6 –10%
with strength 30%

E131 No 共0兲 0.82 1 0.94 0.65 Yes 共1兲 0–5% with strength 10.61 17.39 8.51
70%;
6 –10%
with strength
30%

E262 Yes 共1兲 0.28 0.95 0.5 0.65 Yes 共1兲 Greater than 20% 10 39.45 25.31
with strength 70%;
12–20%
with strength 30%

Average — — — — — — — 0.00 129.82 43.70


%Error
Note: Average %Error⫽ 兩 X actual⫺X estimated兩 /X estimated⫻100.

Since x 6 takes a fuzzy value, the outputs f 6 (x 6 ) take the follow- Thus, as a subset of D
ing fuzzy value:
A 7 ⬇ 关 0,0,0,0,0,0.7,0.5,0.3,0,0,0兴
A 6 ⫽ f 6 共关 0/0⫹0.2/0.1⫹0.4/0.2⫹0.6/0.3⫹0.8/0.4⫹1.0/0.5
where we added the entry 0.5⫽(0.7⫹0.3)/2 to maintain the con-
⫹0.8/0.6⫹0.6/0.7⫹0.4/0.8⫹0.2/0.9⫹0/1.0 兴 兲 vexity of A 7 .
Now we use A(y)⫽ 兺 i⫽1 k
w i A i (y) to find the output fuzzy set A
⬇ 关 0/0.13⫹0.4/0.12⫹0.6/0.11⫹0.8/0.10⫹1.0/0.09⫹0.6/0.08 representing the relative loss in labor productivity, as follows:
⫹0.4/0.07⫹0.2/0.06兴 .
A⫽0.011关 0,0,0,0,0,0,1,0,0,0,0 兴
To get that value, we applied f 6 of Table 2 on the elements of the
universe 共denominators兲, rounded up the values to two decimal ⫹0.268关 0,0,0,0,0,0,1,0,0,0,0,兴
digits, and added the membership values 共numerators兲 corre-
⫹0.203关 0,0,0,0,0,1,0,0,0,0,0 兴
sponding to the same denominator.
If we further try to represent A 6 as a subset of D, we have to ⫹0.153关 0,0,0,0,0,0,1,0,0,0,0 兴
round up the denominators even more to one decimal digit. How-
ever, as the regression function f 6 has a very small slope, A 6 gets ⫹0.000关 0,0,0,0,0,0,1,0,0,0,0 兴
approximated by the crisp number
⫹0.069关 0,0,0,0,0,0,1,0,0,0,0 兴
A 6 ⫽0.1
⫹0.296关 0,0,0,0,0,0.7,0.5,0.3,0,0,0兴
indicating that our discrete model cannot capture the fuzziness of
the variable x 6 . Also, x 7 takes a fuzzy value and the correspond- ⫽ 关 0,0,0,0,0,0.410,0.649,0.089,0,0,0兴
ing f 7 (x 7 ) takes the fuzzy value
Thus, the expected loss in labor productivity 共centroid兲 is
A 7 ⫽ f 7 共关 0.7/1⫹0.3/2⫹0.0/3⫹0.0/4 兴 兲 ⫽ 关 0.7/0.039⫹0.3/0.160
兺 y•A 共 y 兲 0 * 0.410⫹0.1* 0.649⫹0.2* 0.089 0.0827
y *⫽ ⫽ ⫽
⫹0.0/0.281⫹0.0/0.402兴 ⬇ 关 0.7/0.0⫹0.3/0.2⫹0.0/0.3 兺A共 y 兲 0.410⫹0.649⫹0.089 1.148

⫹0.0/0.4兴 ⫽0.072⬇7.2%

JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002 / 257


with variance
兺 共 y⫺y * 兲 2 •A 共 y 兲 共 0⫺0.072兲 2 * 0.410⫹ 共 0.1⫺0.072兲 2 * 0.649⫹ 共 0.2⫺0.072兲 2 * 0.089 0.0041
␴ 2⫽ ⫽ ⫽ ⫽0.0036
兺A共 y 兲 0.410⫹0.649⫹0.089 1.148

Thus, ␴⫽0.060⬇6%. Cambridge Systematics, Inc. 共1998兲. ‘‘Department of


A comparison between the statistical-fuzzy model estimate and Transportation highways and rail programs performance audit.’’ Rep.
the pure statistical model estimate is shown in Table 3. It provides 98-2.
the actual %Delta, predicted %Delta, and the analysis of the av- Dubois, D., and Prade, H. 共1980兲. Fuzzy sets and systems: Theory and
erage percent error for seven case studies 共including this ex- applications, Academic, New York.
Hanna, A. S., and Lotfallah, W. B. 共1999兲. ‘‘A fuzzy logic approach to the
ample兲. The statistical-fuzzy approach shows significant improve-
selection of cranes.’’ Autom. Constr., 8, 597– 608.
ment in the prediction accuracy of productivity loss.
Hanna, A. S., Russell, J. S., Gotzion, T. W., and Nordheim, E. V. 共1999a兲.
‘‘Impact of change orders on labor efficiency for mechanical construc-
tion.’’ J. Constr. Eng. Manage., 125共3兲, 176 –184.
Conclusion Hanna, A. S., Russell, J. S., Nordheim, E. V., and Bruggink, M. J.
共1999b兲. ‘‘Impact of change orders on labor efficiency for electrical
This paper provides a new methodology using the statistical- construction.’’ J. Constr. Eng. Manage., 125共4兲, 224 –232.
fuzzy approach to quantify the cumulative impact of change or- Ibbs, C. W., and Allen, W. E. 共1995兲. ‘‘Quantitative impacts of project
ders. The proposed methodology uses statistical results in forming change.’’ Source Document 108, Construction Industry Institute, Univ.
fuzzy if-then rules as well as choosing membership functions of of Texas at Austin, Austin, Tex.
linguistic values. Leonard, C., Moselhi, O., and Fazio, P. 共1991兲. ‘‘Impact of change
The new methodology provides substantial improvement com- orders on construction productivity.’’ Can. J. Civ. Eng., 18,
pared to traditional statistical models. The new model improves 484 – 492.
the prediction accuracy and is capable of integrating fuzzy knowl- Lorterapong, P., and Moselhi, O. 共1996兲. ‘‘Project-network analysis using
edge into quantitative data. fuzzy sets theory.’’ J. Constr. Eng. Manage., 122共4兲, 308 –318.
The proposed methodology can also be applied in areas of Wu, R. W., and Hadipriano, F. C. 共1994兲. ‘‘Fuzzy modus ponens deduc-
tion technique for construction scheduling.’’ J. Constr. Eng. Manage.,
system analysis and decision making when a complex input-
120共1兲, 162–179.
output function is to be predicted in the presence of fuzzy knowl-
Zadeh, L. A. 共1965兲. ‘‘Fuzzy sets.’’ Inf. Control., 8, 338 –353.
edge and fuzzy variables. Computer implementation of this meth- Zadeh, L. A. 共1975a兲. ‘‘Concept of a linguistic variable and its application
odology is suggested for future research, so stakeholders can to approximate reasoning, I.’’ Inf. Sci., 8, 199–249.
easily implement this methodology for their purposes. Zadeh, L. A. 共1975b兲. ‘‘Concept of a linguistic variable and its applica-
tion to approximate reasoning, II.’’ Inf. Sci., 8, 301–357.
Zadeh, L. A. 共1975c兲. ‘‘Concept of a linguistic variable and its application
References to approximate reasoning, III.’’ Inf. Sci., 9, 43– 80.
Zadeh, L. A. 共1979兲. ‘‘A theory of approximate reasoning.’’ Machine
Ayyub, B. M., and Haldar, A. 共1984兲. ‘‘Project scheduling using fuzzy set intelligence, Vol. 9, J. Hayes, D. Michie, and L. I. Mikulich, eds.,
concepts.’’ J. Constr. Eng. Manage., 110共2兲, 189–204. 149–194.

258 / JOURNAL OF COMPUTING IN CIVIL ENGINEERING / OCTOBER 2002

You might also like